Oracle Project Management Cloud 2023 Implementation Professional - 1Z0-1057-23 模擬練習
Select two correct statements about project classifications on a template.
Response:
Response:
正解: A,D
Which precedence order is used by the system for labor schedules to distribute payroll cost?
正解: C
解説: (PassTest メンバーにのみ表示されます)
When implementing Project Performance Reporting, your customer has the following requirements:
Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)
Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)
正解: B
解説: (PassTest メンバーにのみ表示されます)
Identify three correct statements about project types.
(Choose three.)
Response:
(Choose three.)
Response:
正解: A,C,E
When setting up capitalization options on a project type, you have decided to enable the Require Complete Asset Definition option. If this option is enabled, the "Transfer Assets to Oracle Fusion Assets" process will place asset lines with complete definition into which queue in Oracle Fusion Assets?
正解: A
解説: (PassTest メンバーにのみ表示されます)
Your client has decided to import time cards into Project Costing from Oracle Fusion Time and Labor. They have a requirement to make adjustments to time card entries whenever needed.
In which work area will the employees and contingent workers be able to modify their time cards?
In which work area will the employees and contingent workers be able to modify their time cards?
正解: A
解説: (PassTest メンバーにのみ表示されます)