The data center has been in operation for about 1 year and 2 months. The dust levels in the computer room are relatively high.
What is the most likely root cause?

正解: B
解説: (PassTest メンバーにのみ表示されます)
What is the focus of the Open Compute Project (OCP)?

正解: D
解説: (PassTest メンバーにのみ表示されます)
The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.
What is the set-up in this data center?

正解: A
解説: (PassTest メンバーにのみ表示されます)
Which efficiency indicator accounts for all cooling costs (installation, operation, disposal)?

正解: B
解説: (PassTest メンバーにのみ表示されます)
What indicates the overcurrent of a fuse or breaker?

正解: A
解説: (PassTest メンバーにのみ表示されます)
The UPS of a data center with ANSI/TIA-942 Rating-4 is installed with the rectifier connected to power feed A and the bypass/reserve input connected to power feed B. To which feed will the UPS output be synchronized?

正解: D
解説: (PassTest メンバーにのみ表示されます)
The building in which the computer room is housed is required to have a sprinkler system. The building is therefore equipped with a wet pipe system.
What action, if any, should you recommend for the computer room?

正解: A
解説: (PassTest メンバーにのみ表示されます)