A project manager in a function organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date.
Which of the following should the project manager do NEXT?

正解: A
The project sponsor wishes to implement a 24/7 solution for the service desk, requiring the establishment of the capability on three different continents. Which of the following factors is MOST likely to influence communication methods across the project?

正解: D
A project has just begun, and people are not clear about the objectives.
Which of the following meeting types is needed?

正解: A
A project's stakeholders have not been informed of project updates and milestones by the CCB and project team. The stakeholders have threatened to withdraw project support. Which of the following should the project manager do to get buy-in from the stakeholders for the project?

正解: D
Which of the following documents would MOST likely provide a broad, non-customized overview of a product or service?

正解: A
During a CCB, a SME evaluated the impact and provided new information because of business process changes for handling potential failure. Which of the following documents should be updated?

正解: B
A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days.
Which of the following characteristics classifies this as a project?

正解: B
A company was originally organized using a functional structure; however, the company has decided to go forward with a matrix structure to get the most utilization of resources. This is an example of:

正解: C
A project has activities on the critical path that must be completed before other activities can start.
Task A is dependent on Task C before Task D can be completed.
Task A requires task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?

正解: C
Which of the following are examples of organizational change? (Choose two.)

正解: A,D
Which of the following BEST describes the relationship between portfolios, projects, and programs?

正解: B
Which of the following project phases occurs when requirements are detailed?

正解: A
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?

正解: A