NCARB ARE 5.0 Project Management (PjM) - Project-Management 模擬練習


Refer to the exhibit.
The following changes occur during the project:
* The owner delayed the project kickoff until September Year 1 due to delays in finalizing the Owner- Architect Agreement.
* The architect did not have enough staff available to start the project on time, so the firm hired temporary staff for 2 months.
* The owner made a design change in January Year 2 that added 2 weeks to the schedule.
* Not enough bids were received, and the project was bid a second time with additional advertising.
* The owner made design changes in May and July of Year 2 that each added 3 weeks to the schedule.
When were the construction documents completed based on the project changes?

正解: A
解説: (PassTest メンバーにのみ表示されます)
A key Project Manager leaves an architectural firm halfway through a project. Several days of lost productivity pass while the new Project Manager determines the customized organization that the previous Project Manager used. The new Project Manager recommends implementing new office policies to create standards and quality control methods for the entire office.
Which methods should be implemented? Check the four that apply.

正解: A,C,D,E
解説: (PassTest メンバーにのみ表示されます)
A principal architect is working with a school district on designing an 18,000-square-foot athletics training facility. During the DD phase, the principal notices that the firm's younger staff has produced equipment plans that do not coordinate with the electrical engineer's sheets.
How should the principal architect respond to the lack of coordination? Check the three that apply.

正解: A,E,F
解説: (PassTest メンバーにのみ表示されます)
An architecture firm has a C401 agreement with their consultants for a new design-bid-build residential tower.
The architect has approved a schedule provided by the mechanical engineer that includes a two-week quality control review after each delivery milestone.
During the design development phase, the owner requests that the architect change the 8,000-square-foot business center amenity for tenants to a private restaurant. The mechanical engineer informs the architect that their schedule must be extended by four weeks to meet the owner's request.
What should the architecture firm do first to maintain the start of construction?

正解: C
解説: (PassTest メンバーにのみ表示されます)
What is the architect's primary responsibility when responding to a contractor's Request for Information (RFI) during construction?

正解: A
解説: (PassTest メンバーにのみ表示されます)
A project achieves refinement and coordination in which of the following phases?

正解: B
解説: (PassTest メンバーにのみ表示されます)

Design Firm ABC is awarded two projects, but they do not have enough staff to support the execution of both projects due to unexpected staffing issues. ABC is deciding if they need to hire staff from an outside firm to execute the projects.
Which one of the following sets of staff members would adequately support ABC's staffing needs?

正解: D
解説: (PassTest メンバーにのみ表示されます)
What does "substantial completion" mean in the context of a construction contract?

正解: D
解説: (PassTest メンバーにのみ表示されます)