To reduce the subassembly stock with no impact on material planning of child components of the subassemblies stock, you need to modify the multilevel item structure of a product.
Identify the action that meets this requirement.
Identify the action that meets this requirement.
正解: A
A manufacturing plant works for two shifts of 8 hours each. The Manufacturing user wants a work center resource R1 of 4 units to be available during a nonworking time outside the regular shift on a particular day.
Identify the sequence of steps to create a resource exception in the Manage Work Center Resource Calendar page.
Identify the sequence of steps to create a resource exception in the Manage Work Center Resource Calendar page.
正解: B
In a manufacturing plant, the work definition and rate plans of Material, Resource, and Overhead of an assembly have been defined as required.
A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting.
Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.
A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting.
Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.
正解: B,D,E
The production user wants to report Work Order completion.
Identify two ways of reporting the progress of work order at work order operation level.
Identify two ways of reporting the progress of work order at work order operation level.
正解: B,D
While creating an item in Product Information Management (PIM), the following two item templates are selected in sequence and applied.
1. Template: Finished Goods (WIP = No, Customer Ordered = Yes)
2. Template: Sub-assembly (WIP = Yes, Customer Ordered = No)
Identify the Item Attribute values in the application.
1. Template: Finished Goods (WIP = No, Customer Ordered = Yes)
2. Template: Sub-assembly (WIP = Yes, Customer Ordered = No)
Identify the Item Attribute values in the application.
正解: D
You can generate and manage work order exceptions in Oracle Manufacturing Cloud. Which users can report production exception and who gets notified after an exception is raised?
正解: A
In a manufacturing plant, a production operator in a given shift completes a car assembly and reports this using orderless completion by referencing a Work Definition.
Identify the two purposes of the referenced Work Definition in Orderless reporting.
Identify the two purposes of the referenced Work Definition in Orderless reporting.
正解: B,E