SAP Certified Application Associate - SAP S/4HANA Project Systems - C-TS412-1909 模擬練習

Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20.
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?

正解: C
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question

正解: A,B,D
What are some of the advantages of using project simul-ations? Note: There are 3 correct answers to this question

正解: A,B,E
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

正解: B
Dates
You want to exchange data between SAP Project System and Microsoft What interface do you use?

正解: D
Cost & Budget
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ...
What is the typical sequence for the following business transactions and document.

正解: A
Material
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question

正解: A,C
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question

正解: A,C,D
Materials
Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO).

正解: D