SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP5 - C-TSCM42-65 模擬練習
Which function is supported by production orders?
正解: C
Where can you define the default storage location for the material component of a production order? (Choose three)
正解: B,C,D
The final assembly of a finished product should only be triggered when a customer order arrives.
Which planning strategy for the finished product do you use?
Which planning strategy for the finished product do you use?
正解: D
Which of the following elements can be used in a process order? (Choose three)
正解: B,D,E
Which of the following statements about consumption are correct? (Choose two)
正解: A,D
Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three)
正解: B,D,E
Which functions can be triggered before releasing a production order? (Choose three)
正解: A,B,E
You want to produce a finished product only when it is requested by a customer order in make-to-order production. However, all assemblies need to be procured beforehand.
How can you fulfill these requirements in SAP ECC? (Choose two)
How can you fulfill these requirements in SAP ECC? (Choose two)
正解: B,D