Under a/an __________ cost system, a company accounts for output by identifying specific physical units.
正解: A
解説: (PassTest メンバーにのみ表示されます)
Scenario 6.0: 2
ABC Corporation (ABC) entered into a firm-fixed-price, indefinite-delivery/indefinite-quantity (IDIQ) contract with a Federal buyer for the purchase of various "Soviet-style" parts. The contract language allowed for changes to:
o Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the buyer; o The method of shipment or packing; and o Place of delivery.
The contract also specified that:
If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the buyer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.
ABC was unable to obtain a particular part required to fulfill a delivery order under the contract, and missed the deadline for delivery. Two years after the deadline passed, with no delivery, the failure provided cause for termination for default under the conditions outlined in the contract. To avoid default, ABC entered into Bilateral Modification 4 with the buyer. The modification required ABC to provide additional parts as consideration for late delivery. The modification also stated that a new delivery date for the original delivery would be determined in another modification.
ABC remained unable to purchase the parts to fulfill the original order. A new modification, Bilateral Modification 7 , provided that ABC would deliver "new production" models of the parts in question, rather than the "new surplus" parts specified in the original delivery order. The idea to deliver new production models of the parts had originated with ABC and was accepted by the buyer. ABC did not attempt to negotiate any changes in price, no discussions of price were held, and no price adjustment was included in this modification.
ABC completed delivery of these parts on time. However, the new production models cost significantly more than the new surplus parts originally ordered.
Approximately four months later, ABC submitted a request for equitable adjustment (REA) to the buyer. In the REA, ABC requested $1,369,377.47 , which represented the difference in price between the parts called for by the original delivery order and the parts ABC ultimately delivered. The buyer rejected the request.
Question:
Based on the contract language that specified how the contract would handle changes, was ABC entitled to an equitable adjustment?
ABC Corporation (ABC) entered into a firm-fixed-price, indefinite-delivery/indefinite-quantity (IDIQ) contract with a Federal buyer for the purchase of various "Soviet-style" parts. The contract language allowed for changes to:
o Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the buyer; o The method of shipment or packing; and o Place of delivery.
The contract also specified that:
If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the buyer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.
ABC was unable to obtain a particular part required to fulfill a delivery order under the contract, and missed the deadline for delivery. Two years after the deadline passed, with no delivery, the failure provided cause for termination for default under the conditions outlined in the contract. To avoid default, ABC entered into Bilateral Modification 4 with the buyer. The modification required ABC to provide additional parts as consideration for late delivery. The modification also stated that a new delivery date for the original delivery would be determined in another modification.
ABC remained unable to purchase the parts to fulfill the original order. A new modification, Bilateral Modification 7 , provided that ABC would deliver "new production" models of the parts in question, rather than the "new surplus" parts specified in the original delivery order. The idea to deliver new production models of the parts had originated with ABC and was accepted by the buyer. ABC did not attempt to negotiate any changes in price, no discussions of price were held, and no price adjustment was included in this modification.
ABC completed delivery of these parts on time. However, the new production models cost significantly more than the new surplus parts originally ordered.
Approximately four months later, ABC submitted a request for equitable adjustment (REA) to the buyer. In the REA, ABC requested $1,369,377.47 , which represented the difference in price between the parts called for by the original delivery order and the parts ABC ultimately delivered. The buyer rejected the request.
Question:
Based on the contract language that specified how the contract would handle changes, was ABC entitled to an equitable adjustment?
正解: A
解説: (PassTest メンバーにのみ表示されます)
Scenario 4.0:
The buyer intended to change the pricing structure for a contract for garbage collection services at one of its facilities. Previously, the contract included contract line items priced on a "per-ton" basis, along with overhead line items covering the contractor's variable costs. The buyer intended to issue a solicitation that eliminated the overhead line items, thus requiring all costs to be included in a "price-per-ton" pricing method.
Prior to issuing a solicitation, the buyer conducted market research to determine whether it was customary industry practice to price garbage collection services based on the weight of the garbage collected. This market research included three parts:
* Reviewing refuse contracts at three other locations;
* Posting a notice to potential sellers asking for feedback on the proposed structure, to which the buyer received seven responses-four of which suggested a monthly line-item structure, which would include variable costs and not be on a "per-ton" basis, since these four respondents indicated that a "per-ton" pricing structure was not a "customary commercial practice," and three had no comment about the line-item structure; and
* Obtaining "historical market research" that had been performed during the previous year by personnel at another buyer location, consisting of talking to a sales representative from a waste removal company who indicated that his company used a "per-ton" pricing structure that was a "practical method of pricing for trash removal services." Following this market research, the buyer determined that it was "in the buyer's best interest" to utilize the
"per-ton" approach and that it was a "customary commercial practice."
A solicitation was issued requiring offerors to submit fixed prices on a per-ton basis for several line items, for which the solicitation provided estimated quantities. The buyer removed the line items for overhead costs that had been present in the prior contract for waste removal. Instead, the new solicitation required offerors to submit prices that reflected "all fixed and variable costs" on a per-ton basis and only permitted the seller "to invoice on tonnage collected." The resulting statement of work indicated that the seller was required to provide all items necessary to perform the required services, including personnel, equipment, supplies, facilities, materials, and supervision.
Question:
The new contract structure, in which all costs were to be included in the "per-ton" price, shifted more risk to which party?
The buyer intended to change the pricing structure for a contract for garbage collection services at one of its facilities. Previously, the contract included contract line items priced on a "per-ton" basis, along with overhead line items covering the contractor's variable costs. The buyer intended to issue a solicitation that eliminated the overhead line items, thus requiring all costs to be included in a "price-per-ton" pricing method.
Prior to issuing a solicitation, the buyer conducted market research to determine whether it was customary industry practice to price garbage collection services based on the weight of the garbage collected. This market research included three parts:
* Reviewing refuse contracts at three other locations;
* Posting a notice to potential sellers asking for feedback on the proposed structure, to which the buyer received seven responses-four of which suggested a monthly line-item structure, which would include variable costs and not be on a "per-ton" basis, since these four respondents indicated that a "per-ton" pricing structure was not a "customary commercial practice," and three had no comment about the line-item structure; and
* Obtaining "historical market research" that had been performed during the previous year by personnel at another buyer location, consisting of talking to a sales representative from a waste removal company who indicated that his company used a "per-ton" pricing structure that was a "practical method of pricing for trash removal services." Following this market research, the buyer determined that it was "in the buyer's best interest" to utilize the
"per-ton" approach and that it was a "customary commercial practice."
A solicitation was issued requiring offerors to submit fixed prices on a per-ton basis for several line items, for which the solicitation provided estimated quantities. The buyer removed the line items for overhead costs that had been present in the prior contract for waste removal. Instead, the new solicitation required offerors to submit prices that reflected "all fixed and variable costs" on a per-ton basis and only permitted the seller "to invoice on tonnage collected." The resulting statement of work indicated that the seller was required to provide all items necessary to perform the required services, including personnel, equipment, supplies, facilities, materials, and supervision.
Question:
The new contract structure, in which all costs were to be included in the "per-ton" price, shifted more risk to which party?
正解: B
解説: (PassTest メンバーにのみ表示されます)
What are the two components of Social Competence?
正解: B
解説: (PassTest メンバーにのみ表示されます)
A bid is __________ when it complies in all material respects with the invitation for bids.
正解: D
解説: (PassTest メンバーにのみ表示されます)
There are four essential laws of supply and demand, assuming that all other factors remain equal, which of the following statements is true?
正解: D
解説: (PassTest メンバーにのみ表示されます)
The personal competence of emotional intelligence is comprised of self-management and __________.
正解: D
解説: (PassTest メンバーにのみ表示されます)
To excel in work, life, or as a leader, contract managers must commit to __________.
正解: A
解説: (PassTest メンバーにのみ表示されます)
If a party to the contract does not have the capacity to contract (such as being underage or having a mental infirmity), a contract is __________.
正解: D