ISQI ISTQB Certified Tester Advanced Level - Test Analyst (Syllabus 2012) - CTAL-TA_Syll2012_UK 模擬練習
In an organization using keyword-driven automation, which of the following activities typically is the responsibility of the test analyst?
[K2] 1 credit
[K2] 1 credit
正解: D
While identifying scenario's for the use case "copy A4 - A4" for a new copier, the following scenario's were identified:
Basic scenario: single side to single side
Deviations: single side to double side, copy of a set, copy using the automatic document feeder Failures: no paper in paper tray, paper jam, out of staples During interviews with both development and end-users it has been established that the failure scenario's can occur during the basic scenario and during each of the deviations.
How many test cases will be needed to achieve full coverage both for valid and invalid situations?
[K3] 2 credits
Basic scenario: single side to single side
Deviations: single side to double side, copy of a set, copy using the automatic document feeder Failures: no paper in paper tray, paper jam, out of staples During interviews with both development and end-users it has been established that the failure scenario's can occur during the basic scenario and during each of the deviations.
How many test cases will be needed to achieve full coverage both for valid and invalid situations?
[K3] 2 credits
正解: C
To enhance both the effectiveness and efficiency of the test design phase the purchase of a test design tool is being considered. Which one of the statements hereafter best characterizes a test design tool?
[K2] 1 credit
[K2] 1 credit
正解: B
Which of the following is a type of testing that someone in the role of a test analyst, working with the test manager, should typically consider and plan for?
[K2] 1 credit
[K2] 1 credit
正解: C
As a test analyst you are involved in the early stages of an acceptance test for a Product Data Management system. You are asked to write test designs and test cases based on use cases. An early version of the system is also already available. It is a known fact that on the implementation level many things will change (including the user-interface). The tests will be carried by end-users with much domain knowledge who have also been involved in the project defining the user requirements and reviewing documentation. What is the BEST option regarding the level of detail and documentation required for test cases in the project?
[K4] 3 credits
[K4] 3 credits
正解: A
Which of the following criteria on test progress would enable the business to determine a likely 'go live' date?
(i) Number of tests planned versus number of tests executed
(ii) Number of high priority defects outstanding
(iii) The test team's timesheets in order to show how much effort has been devoted to testing
(iv) Number of tests passed and number failed
(v) Number of defects found in each development area
(vi) The rate at which defects are being found
[K2] 1 credit
(i) Number of tests planned versus number of tests executed
(ii) Number of high priority defects outstanding
(iii) The test team's timesheets in order to show how much effort has been devoted to testing
(iv) Number of tests passed and number failed
(v) Number of defects found in each development area
(vi) The rate at which defects are being found
[K2] 1 credit
正解: D