SAP Certified Application Associate - SAP Integrated Business Planning - C_IBP_2111 模擬練習

Which of the following approaches could you take to reduce run times of an optimizer? Note: There are
2 correct Answers to this question.

正解: B,D
What is a prerequisite for modeling outsourced manufacturers with production capacity?

正解: B
You are reviewing the master data types for supply planning. Which master data types are compound master data types? Note: There are 2 correct Answers to this question.

正解: A,B
How can you make charts and dashboards private?

正解: A
You created a key figure and want to add calculations. Which of the following rules do you consider?
Note: There are 2 correct Answers to this question.

正解: A,B
Which SAP IBP planning operator can be run to delete planning objects in a certain version?

正解: A
Which header name displays are available in the Report Options menu of the SAP IBP Excel interface?Note:
There are 2 correct Answers to this question.

正解: A,B
NO.23 You are redesigning planning for supply chain that is facing the issue of variability. What is the best solution for dampening variability via demand classification?

正解: C
You have set up a planning area and data is available. You adjust the necessary time profile settings and run the consistency check. Which settings can you change and still run a successful consistency check? Note:
There are 2 correct Answers to this question.

正解: C,D