SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing - C_P2W22_2504 模擬練習
Which of the following processes lead to an indicator in the planning file?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
正解: C,D
In the bucket planning mode of the capacity scheduling table, what happens if the sum of the requirements of all operations exceeds the available capacity of the bucket?
正解: C
You want to set up a make-to-order planning scenario for a finished product. The bill of material contains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
正解: A
When working with the material status, for which business areas can you set a warning message?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
正解: B,D
How would you define a pegging structure for an order in the context of Advanced Planning?
正解: A
In which master data objects do you maintain data to determine the duration of an operation for production?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
正解: B,C
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
正解: A,D
What is the purpose of the pull list in material staging?
正解: A
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of a material shortage. What must you do?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
正解: B,C