SAP Certified Application Associate - SAP S/4HANA Asset Management - C_TS413_2020 模擬練習
During the implementation project you need to define the organizational units relevant for Plant Maintenance. Which of the following objects can you directly assign to a maintenance plant? Note: There are 2 correct answers to this question.
正解: A,B
You create a revision for a maintenance event builder (MEB) scenario. Which of the following statements are correct? Note: Thereare 2 correct answers to this question.
正解: A,C
The maintenance technician wants to document the finished work steps for a technical object in a notification. Which catalog-based option in the notification can be used?
正解: A
In which cases are projects (PS) used in the area of SAP S/4HANAAsset Management? Note: There are 2 correct answers to this question.
正解: C,D
Which of the following statements are correct for SAP S/4HANACIoud - Asset Management? Note: There are 2 correct answers to this question.
正解: A,C
How does a performance-based maintenance plan calculate the interval between start date and planned date?
正解: C
Which scheduling parameters are used in a multiple-counter plan? Note: There are 2 correct answers to this question.
正解: A,D
Which operations are possible when you cancel the technical completion of a maintenance order? Note: There are 2 correct answers to this question.
正解: A,D
You want to assign components to an equipment task list. There isno BOM assigned to the equipment. What is the prerequisite for using the free assignment of material?
正解: D