Where can you maintain consumption mode and consumption periods for planning strategies?
There are 2 correct answers to this question.
Response:

正解: C,D
What are main innovations in manufacturing in SAP S/4HANA?
There are 3 correct answers to this question.
Response:

正解: A,B,C
A planner updated a production order status from partially confirmed "PCNF" to technically completed
"TECO" by mistake.
What impact would this have to other users for this specific production order?
Please choose the correct answer.
Response:

正解: B
On which of the following levels can you influence the availability check for the components of production orders?
There are 2 correct answers to this question.
Response:

正解: B,D
In the Manage Shortage view of the new SAP Fiori app "Monitor Material Coverage", what do the stars indicate?
Please choose the correct answer.
Response:

正解: C
Which functional capabilities does the Detailed Scheduling Board have?
There are 2 correct answers to this question.
Response:

正解: A,C
What new technology is used in SAP S/4HANA Embedded Analytics?
Please choose the correct answer.
Response:

正解: B
For which data objects do you have to set up CIF integration models in S/4HANA to use them in advanced planning?
There are 2 correct answers to this question.
Response:

正解: C,D
During planning you are facing an overload situation on a resource. Which activities do you consider to create a feasible production plan?
There are 3 correct answers to this question.
Response:

正解: A,B,E
What are drawbacks of the separation of OLTP and OLAP?
There are 4 correct answers to this question.
Response: