EXIN PRINCE2 Foundation - - EX0-002 模擬練習
Which is a responsibility of a risk owner?
正解: A
What is the definition of a project outcome?
正解: B
Which product identifies the management stages and timescales of a project?
正解: D
Which is a benefit of using PRINCE2?
正解: A
Which is a purpose of a Project Product Description?
正解: B
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.
正解: B
Which is a purpose of a Configuration Management Strategy?
正解: D
What do acceptance criteria identify?
正解: D
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
正解: D
Which process provides the Project Board with the information it requires in order to commit
resources to the project?
resources to the project?
正解: C