When connecting the refrigerant pipe, to prevent the pipe from being oxidized, it is necessary to introduce a small amount of nitrogen gas during welding.

正解: A
The FusionModule1000B series solution can meet the Tier4 power supply requirements when using the 2N power supply and distribution system.

正解: B
When the NetCol5000-A removes the air conditioning humidifier, the steps to maintain the electrode humidifier include (). (Multiple choice)

正解: A,B,C,D
After the air conditioner is commissioned, the indoor temperature is in a reasonable state, and the suction pressure is not lower than ( ).

正解: D
The NetCol5000-C requires manual adjustment of the water valve to a minimum when it is filled with water.

正解: B
The Fusion Module2000 is an outdoor prefabricated integrated data center solution.

正解: B
The following statement about the integration UP5000-E-120K-HASBS, which is wrong?

正解: C
Which of the following are the characteristics of Huawei NetCol5000-A row-level precision air conditioner cooling capacity adjustment?

正解: A,D
UPS2000-G-(6-20kVA) battery is not connected and does not affect the normal power supply of the system, but the UPS loses the backup power supply capability.

正解: A
When the NetCol5000-A air conditioner was commissioned, Which statement about the possible cause of the "exhaust high pressure alarm" was wrong?

正解: B