PMI Risk Management Professional - PMI-RMP 模擬練習

A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

正解: B
解説: (PassTest メンバーにのみ表示されます)
The scope of a large mobile network deployment project includes equipment to be furnished by the customer.
The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.
What should the risk manager do?

正解: D
解説: (PassTest メンバーにのみ表示されます)
A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.
How should the risk manager address this concern?

正解: A
解説: (PassTest メンバーにのみ表示されます)
A project is underway to implement a new customer support software. During testing, the risk manager discovers that the integration with the existing customer relationship management system is more complex than initially planned, potentially delaying the project. The risk manager needs to update project documents to reflect this new information.
Which steps should the risk manager consider when updating relevant project documents?

正解: A
解説: (PassTest メンバーにのみ表示されます)
Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project ' s budget.
What should the project manager do next?

正解: B
解説: (PassTest メンバーにのみ表示されます)
There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders, and this delays the decision-making process.

正解: B
解説: (PassTest メンバーにのみ表示されます)
An organization is embarking on a multi-million-dollar project with numerous identified risks. What should the project risk team do to navigate the risks on this project?

正解: A
解説: (PassTest メンバーにのみ表示されます)
The project team has correctly identified, assessed, and planned responses for a project ' s risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.
What are two options the risk manager should consult for the analysis? (Choose two.)

正解: A,E
解説: (PassTest メンバーにのみ表示されます)
A project ' s design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.
What should the project manager have done differently?

正解: A
解説: (PassTest メンバーにのみ表示されます)
A project team is developing a software system for a financial organization and is conducting a failure modes and effects analysis (FMEA) to identify and evaluate potential failure points. The risk manager must guide the team on how to prioritize risks based on FMEA results for effective risk management.
What should the risk manager do?

正解: C
解説: (PassTest メンバーにのみ表示されます)