EXIN PRINCE2 7 Foundation written - PR2F 模擬練習
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
正解: A
解説: (PassTest メンバーにのみ表示されます)
Which characteristic distinguishes a project from regular business operations?
正解: D
解説: (PassTest メンバーにのみ表示されます)
The project manager needs to know what modifications have been proposed to an approved product during the stage. Which management product should the project manager review?
正解: B
解説: (PassTest メンバーにのみ表示されます)
Which is a description of a purpose of the communication management approach?
正解: B
解説: (PassTest メンバーにのみ表示されます)
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
正解: B
解説: (PassTest メンバーにのみ表示されます)
Which is a definition of management?
正解: C
解説: (PassTest メンバーにのみ表示されます)
What is a goal of the 'implement' step within the recommended risk management procedure?
正解: D
解説: (PassTest メンバーにのみ表示されます)
Who should act as the communication channel between a project and corporate or programme management?
正解: A
解説: (PassTest メンバーにのみ表示されます)
Which document should record the agreed amount of risk budget for a project?
正解: B
解説: (PassTest メンバーにのみ表示されます)
Which product defines how the project board should approve the management products produced during the
'initiating a project' process?
'initiating a project' process?
正解: C
解説: (PassTest メンバーにのみ表示されます)