PRINCE2 Project Management Practitioner (Version 7) - PRINCE2-7-Practitioner 模擬練習
PROGRESS
Here are three actions related to the 'progress' practice for the LouisShopping project.
Which role (A-E) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.
Here are three actions related to the 'progress' practice for the LouisShopping project.
Which role (A-E) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.
正解: B,D,E
解説: (PassTest メンバーにのみ表示されます)
During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.
Is this an appropriate use of the 'give ongoing direction' activity, and why?
Is this an appropriate use of the 'give ongoing direction' activity, and why?
正解: C
解説: (PassTest メンバーにのみ表示されます)
The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.
Is this an appropriate application of the quality practice, and why?
Is this an appropriate application of the quality practice, and why?
正解: D
解説: (PassTest メンバーにのみ表示されます)
In stage 4, work is late because the survey and utilities teams have not shared information needed by other teams, and morale is falling. The project manager considers a short weekly coordination forum for questions and information sharing, but rejects it solely because it would take time away from delivery.
Is this an appropriate approach to leading a successful team, and why?
Is this an appropriate approach to leading a successful team, and why?
正解: D
解説: (PassTest メンバーにのみ表示されます)
During stage 3, the foundations team manager tells the project manager that the completed foundations may have changed rainwater flow onto a neighbouring property. The project manager notes the concern in the project log but dismisses it without assessment and instructs the team to continue because the design has planning approval.
Is this an appropriate application of the 'capture issues and risks' activity, and why?
Is this an appropriate application of the 'capture issues and risks' activity, and why?
正解: D
解説: (PassTest メンバーにのみ表示されます)
While preparing the project plan during initiation, the project manager proposes that stage 2 should end at the Council's financial year-end. This would allow the decision on funding for stage 3 to coincide with the Council's annual budget process.
Is this an appropriate application of the 'manage by stages' principle, and why?
Is this an appropriate application of the 'manage by stages' principle, and why?
正解: C