Which of the following is NOT input data to the construction planning process?

正解: B
解説: (PassTest メンバーにのみ表示されます)
Which activity is drawn in the incorrect position?

正解: A
解説: (PassTest メンバーにのみ表示されます)
Why does activity 11001 not show successor activities?

正解: A
解説: (PassTest メンバーにのみ表示されます)
What is accurate about Activity 7001 in the precedence diagram?

正解: C
解説: (PassTest メンバーにのみ表示されます)
At the end of month one, did the delay to the parking structure foundation delay the project?

正解: C
解説: (PassTest メンバーにのみ表示されます)
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

正解: B
解説: (PassTest メンバーにのみ表示されます)
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

正解: B
解説: (PassTest メンバーにのみ表示されます)
At a minimum, periodic reporting must be done at what interval?

正解: D
解説: (PassTest メンバーにのみ表示されます)
Which of the following is the most important scheduling consideration for the BILCO contractual scope?

正解: C
The EBS is established by:

正解: D
Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?

正解: B
解説: (PassTest メンバーにのみ表示されます)
If Activity E's duration changes to 4 months, what is the overall duration of the project.

正解: B
解説: (PassTest メンバーにのみ表示されます)
Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

正解: D
解説: (PassTest メンバーにのみ表示されます)
Which of the following are NOT normally included in the project scope statement, either directly or by reference?

正解: C
解説: (PassTest メンバーにのみ表示されます)
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

正解: C
解説: (PassTest メンバーにのみ表示されます)