NCARB ARE 5.0 Project Management (PjM) - Project-Management 模擬練習
Which four factors will most affect the choice of project delivery method? Check the four that apply.
正解: B,C,D,F
解説: (PassTest メンバーにのみ表示されます)
What is the primary purpose of a punch list?
正解: B
解説: (PassTest メンバーにのみ表示されます)
Construction of a gymnasium is scheduled to be complete 365 days from the date of the notice to proceed. On Friday, day 355 of the schedule, the contractor submits a punch list to the architect for substantial completion.
The architect agrees to review the punch list on-site after the weekend.
On Monday, the architect discovers that a subcontractor left open a skylight over the weekend, allowing heavy rain to fall into the courtyard area and damage the gymnasium floor. It was determined the flooring must be replaced. The lead time for new flooring is 8-10 weeks, and installation will take 14 days. The architect's agreement with the owner is contracted to end 30 days after substantial completion.
Which of the following documents must the architect prepare immediately? Check the two that apply.
The architect agrees to review the punch list on-site after the weekend.
On Monday, the architect discovers that a subcontractor left open a skylight over the weekend, allowing heavy rain to fall into the courtyard area and damage the gymnasium floor. It was determined the flooring must be replaced. The lead time for new flooring is 8-10 weeks, and installation will take 14 days. The architect's agreement with the owner is contracted to end 30 days after substantial completion.
Which of the following documents must the architect prepare immediately? Check the two that apply.
正解: C,D
解説: (PassTest メンバーにのみ表示されます)
During the predesign phase of a project, the architect discovers that the owner's budget is insufficient to meet the program requirements.
Which of the following should the architect do?
Which of the following should the architect do?
正解: C
解説: (PassTest メンバーにのみ表示されます)
Which scheduling method shows the longest path of dependent activities?
正解: D
解説: (PassTest メンバーにのみ表示されます)
Near the end of a routine job site visit, the architect begins to assemble notes. The owner's representative then arrives on site unexpectedly. The architect, owner's representative, and contractor discuss and resolve several outstanding project issues. The architect begins writing correspondence to distribute to the project team when the architect returns to the office.
In addition to a Meeting Record, which of the following documents should the architect create?
In addition to a Meeting Record, which of the following documents should the architect create?
正解: A
解説: (PassTest メンバーにのみ表示されます)

Prior to the project kick-off, the architect requests to add an additional week of review time to the schedule for each design submission for coordination with their consultants. Based on the schedule provided, what is the earliest start date for construction with the additional review periods?
正解: C
解説: (PassTest メンバーにのみ表示されます)
When is a change order required?
正解: D
解説: (PassTest メンバーにのみ表示されます)