質問 # 58
Which statement regarding the creation of a new work breakdown structure (WBS element) are true?
Note : there are 3 correct answer for this question.
- A. WBS element can be a planning element, an account assignment element, and a billing element at the same time.
- B. A new work breakdown structure must contain up to 10 levels.
- C. The WBS structure can contain several level 1 WBS element,
- D. You can create several WBS elements per level.
- E. A WBS element of the new project can be assigned to a different project definition.
正解:A、D、E
解説:
You can create several WBS elements per level." According to SAP Help Portal2, "You can assign a WBS element of the new project to a different project definition." According to SAP Help Portal3, "WBS elements can be planning elements, account assignment elements, and billing elements at the same time." Reference: 123
質問 # 59
How can you grant individual authorization for WBS elements and networks?
- A. Activate access control lists (ACL) for the project profile and the network profile
- B. Set the system status to "Lock Master Data".
- C. Define a user status to lock the business transaction Update Project.
- D. Activate access control lists (ACL) for the user master record.
正解:A
解説:
To grant individual authorization for WBS elements and networks, you have to activate access control lists (ACL) for the project profile and the network profile. Access control lists are a feature that allows you to control access to project objects, such as WBS elements and networks, based on user-specific authorization objects. You can use access control lists to define which users can create, change, display, or delete project objects. The project profile is a parameter that defines the basic properties of a project, such as its project type, number range, and budget profile. The network profile is a parameter that defines the basic properties of a network, such as its order type, number range, and scheduling parameters. You have to activate access control lists for both the project profile and the network profile in Customizing in order to use them for WBS elements and networks. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 60
What is the reason for assigning billing plans in customer projects?
- A. Billing plans enable the billing process to be carried out
- B. Billing plans are prerequisites for quotation creation
- C. Billing plans are copied automatically to the sales order item.
- D. Billing plans are used for revenue planning
正解:D
解説:
Billing plans are used for revenue planning in customer projects because they allow you to define billing dates and billing amounts for each project phase or milestone. Billing plans can also be used to create billing requests or invoices automatically based on the billing dates and amounts. Billing plans help you to plan and monitor the cash flow and profitability of your customer projects. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html
質問 # 61
Resources
How can you define external task in your project.
Note : there are 2 correct answers for this question.
- A. Create a service activity in a network.
- B. Assign a purchase order for external processing to the project definition.
- C. Create an external activity in a network.
- D. Create a service milestone.
正解:A、C
質問 # 62
What are the prerequisites for resource-related billing? Note: There are 2 correct answers to this question
- A. A dynamic item processor (DIP) profile with the appropriate settings
- B. A header-account-assigned network that is assigned to a sales order item
- C. An activity-account-assigned network that is assigned to a sales order item
- D. Released WBS elements, activities, and/or activity elements
正解:A、C
解説:
The prerequisites for resource-related billing are a dynamic item processor (DIP) profile with the appropriate settings and an activity-account-assigned network that is assigned to a sales order item. Resource-related billing is a process that allows you to bill customer-specific services based on individual materials, internal activities, and costs. The prerequisites for resource-related billing are:
A dynamic item processor (DIP) profile with the appropriate settings: A DIP profile is a parameter that defines how billing requests are created from project data, such as activities, materials, PRTs, and so on. A DIP profile contains various settings, such as which data sources are used, how prices are determined, how quantities are calculated, and so on. You have to create and maintain DIP profiles in Customizing for Project System under Revenues and Earnings Integration with SD Documents Dynamic Item Processor .
An activity-account-assigned network that is assigned to a sales order item: An activity-account-assigned network is a network that has its activities assigned to different account assignments, such as cost centers, orders, or sales orders. An activity-account-assigned network that is assigned to a sales order item means that some or all of its activities are assigned to an item of an SD document (such as standard order) with controlling object. This enables costs and revenues to be updated in both the SD document and the controlling object.
質問 # 63
You are working with predefined project coding masks to create projects. Which of the following statements apply? Note: There are 2 correct Answers to this question.
- A. You can use an indicator to determine that only coded project numbers may be used within SAP Project System.
- B. You can only use numbers for a project coding mask definition.
- C. You can use the same coding mask for standard projects and operative projects.
- D. You can shorten the project mask even when there are existing projects.
正解:A、C
質問 # 64
Project Structures
Which the following statement regarding networks are correct?.
Note : there are 3 correct answers for this question.
- A. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
- B. Capacity requirements of a network activity are reduced when the activity is confirmed.
- C. You can assign the same work center to more than one activity on the same network.
- D. If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
- E. You can assign more than one activity element to a network activity.
正解:B、C、E
質問 # 65
You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?
- A. Missing reservations for material components
- B. Missing material availability
- C. Missing budget for material components
- D. Missing authorizations to release material components
正解:D
解説:
One possible reason for the error message "Business transaction cannot be carried out" when releasing a network is missing authorizations to release material components. Material components are materials that are required for executing a network activity. To release material components, you need to have the authorization object C_AFKO_ATY with the activity 02 (change) for the order type of the network. Reference: https://answers.sap.com/questions/7530952/the-business-transaction-cannot-be-carried-out-mes.html
質問 # 66
Project Structure
You plan double the work on each internal activity for multiple project. What do you recommend?
- A. Use mass change within the project Builder (CJ20N).
- B. Double the work of each internal activity, one after another, in the project Builder.
- C. Use mass change (CNMASS) in the project system.
- D. Double the capacity in the work center.
正解:C
解説:
Mass change (CNMASS) is a powerful tool that allows you to change multiple fields in multiple objects at once. You can use it to change fields in project definitions, WBS elements, networks, activities, milestones, and PRTs." Reference: 3
質問 # 67
The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element?
- A. Activity allocation
- B. Goods receipt for purchase orders
- C. Creation of purchase orders
- D. Calculation of actual values
正解:C
質問 # 68
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question
- A. Goods receipt into valuated project stock
- B. Goods receipt into unvaluated project stock
- C. Recording of external services in the service entry sheet
- D. Goods receipt of a non-stock item
正解:B、D
解説:
Goods receipt into unvaluated project stock and goods receipt of a non-stock item do not lead to the booking of actual costs to an object. Goods receipt into unvaluated project stock does not affect inventory valuation or accounting documents, therefore no actual costs are posted. Goods receipt of a non-stock item does not affect inventory valuation either, but only updates the purchase order history and statistical delivery costs, therefore no actual costs are posted. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 69
Which of the following statements apply to project versions? Note: There are 2 correct answers to this question
- A. Project versions can be created automatically based on user status
- B. Project versions are mandatory for Milestone Trend Analysis (MTA)
- C. Manually Created project versions always require a project version profile
- D. Project versions can be changed
正解:A、B
解説:
Project versions are copies of projects that allow you to save snapshots of project data at different points in time. Project versions are mandatory for Milestone Trend Analysis (MTA), which is a tool that allows you to monitor and compare the planned and actual dates of milestones in a project over time. Project versions can be created automatically based on user status, which means that you can define rules that trigger the creation of project versions when certain user statuses are set for project objects. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 70
You want to create a reservation for a material component assigned to a network activity.
However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation?
Note: There are 2 correct answers to this question
- A. The material master is set to external procurement
- B. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never"
- C. The availability check for material components indicates missing parts
- D. The material is assigned to the activity as a non-stock material
正解:B、D
質問 # 71
What is the reason for assigning billing plans in customer projects?
- A. Billing plans enable the billing process to be carried out
- B. Billing plans are prerequisites for quotation creation
- C. Billing plans are copied automatically to the sales order item.
- D. Billing plans are used for revenue planning
正解:D
質問 # 72
To which object can you assign a factory calendar?
- A. Milestone
- B. Network header
- C. Relationship
- D. Material component
正解:B
解説:
To assign a factory calendar, you can use the network header. The network header is a structural element of a network that contains general data and settings for a network, such as its order type, number range, scheduling parameters, and so on. The network header also contains the factory calendar field, which allows you to assign a factory calendar to a network. A factory calendar is a parameter that defines the working days and holidays for a plant or a location. A factory calendar is used to determine the dates and durations of activities and networks based on their workdays and non-workdays. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 73
......
SAP C-TS412-2021試験は、SAP S/4HANAプロジェクトシステムモジュールの専門知識を証明したい個人を対象としています。この認定は、SAP S/4HANAプロジェクトシステムを実装、設定、サポートする責任を持つ専門家を対象としています。試験は、候補者のプロジェクト計画、実行、監視プロセスの知識、およびシステムの構成とメンテナンス能力をテストすることに焦点を当てています。
究極なガイド準備C_TS412_2021認定試験SAP Certified Application Associate:https://www.passtest.jp/SAP/C_TS412_2021-shiken.html
リアルC_TS412_2021問題集でSAP明確な解答を試そう:https://drive.google.com/open?id=1rQcZaoZLzCevfkMFDC5yFW1byMIJ-Yxk