質問 # 27
Which tool can the Release Train Engineer use to visualize the flow of value?
- A. Velocity trend charts
- B. Team burn-down charts
- C. Weighted shorted job first
- D. Kanban systems
正解:D
質問 # 28
Scrum Masters are effective by using scrum methods, supporting SAFe principles and practices, and what else?
- A. Supporting delivery using Agile practices
- B. Writing stories and enablers
- C. Managing architectural runway
- D. Serving as a customer proxy
正解:A
質問 # 29
Which statement is true about the SAFe backlog model?
- A. Capabilities are in the Program Backlog
- B. Stories are in the Solution Backlog
- C. Features are in the Program Backlog
正解:B
質問 # 30
How often should a system demo occur?
- A. After every release
- B. After every other iteration
- C. After every iteration
- D. After the end of each program increment (Pl)
正解:C
質問 # 31
Which two actions must the Release Train Engineer (RTE) take when facilitating the Pro-gram Increment (PI) Planning event? (Choose two.)
- A. Wear the RTE visor
- B. Purchase sugary snacks
- C. Ensure the facilities are set up appropriately
- D. Distribute the PI Planning agenda to the Agile Teams
- E. Prioritize the Features
正解:C、D
質問 # 32
What is the primary purpose of PO sync?
- A. To align with the scrum of scrums participants on the status of the Program Increment
- B. To assess progress of the Program Increment and adjust scope and priority as needed
- C. To build objectives for the Program Increment
正解:B
質問 # 33
What are two responsibilities of the Release Train Engineer during Program Increment (PI) execution? (Choose two.)
- A. To facilitate the System Demo
- B. To escalate and track impediments
- C. To make decisions on resource issues for critical bottlenecks
- D. To direct the management of the communities of practice
- E. To formulate and direct decisions on risks
正解:A
質問 # 34
What might an RTE do to embrace relentless improvement and a growth mindset as an individual?
- A. Establish personal KPIs to be able to quantify progress
- B. Frequently execute the SAFe individual self-assessment
- C. Use personal gemba to find useful improvements
- D. Identify personal challenges and create personal actions to be taken
正解:D
質問 # 35
Which tool is typically not used during the problem solving workshop?
- A. Pareto analysis
- B. Fishbone diagram
- C. Dot voting
- D. Modified Fibonacci
正解:B
質問 # 36
Which SAFe tool might the RTE use to identify areas for an ART to improve how its Con-tinuous Delivery Pipeline (CDP) functions?
- A. Conduct empathy interviews with system architects/engineers
- B. Agile Product Delivery core competency assessment
- C. Facilitate a CDP sync every iteration
- D. Architectural runway program backlog enablers
正解:B
質問 # 37
What are two anti-patterns for the IP Iteration? (Choose two.)
- A. To plan work for the IP lteration during P Planning
- B. To ensure all Stories and teams' Pl plans are completed prior to the IP Iteration
- C. To wait for the IP Iteration to fix defects
- D. To minimize lost capacity when people are on vacation or holidays
- E. To allow for sufficient capacity in the Program Roadmap
正解:A、C
質問 # 38
During Program Increment (PI) execution, the System Team is unclear about how to test some of the larger Features. What should a Release Train Engineer do?
- A. Direct Product Management to define the use cases for the Features
- B. Escalate the problem to senior management to get the required action
- C. Allow the problem to reach a critical point knowing that a minor failure is a tech-nique for learning
- D. Encourage the System Team and Product Management to meet and collaborate on a solution
正解:D
質問 # 39
What are two benefits of having a well-executed Innovation and Planning (IP) Iteration? (Choose two.)
- A. Occasional buffer time to deliver more predictably
- B. Shorter lead times before Feature delivery
- C. Improved dependency management between teams
- D. Higher flow of program-level business value
- E. Time for teams to plan, demo and improve together
正解:B、E
質問 # 40
What are two outputs of Iteration Planning? (Choose two.)
- A. PI Objectives
- B. Iteration backlog
- C. Team Backlog
- D. Program Backlog
- E. Iteration goals
正解:B、E
質問 # 41
What is the only true objective measure of an Agile Release Train?
- A. Scrum of scrums
- B. Cumulative flow diagram
- C. Team status report
- D. System Demo
正解:D
質問 # 42
Some teams are having difficulty identifying where they might make process improve-ments. How might the RTE support them?
- A. Encourage the team to perform regular self-assessments and discuss findings
- B. Conduct a survey to identify the worst problems the team is having
- C. Run longer I&A meetings to brainstorm improvement items
- D. Observe the team's ceremonies and share observations
正解:A
質問 # 43
What is a primary responsibility of Business Owners in Program Increment (Pl) Planning?
- A. To ensure that team members plan all of their priorities
- B. To establish the Pl budget
- C. To set the business context
正解:C
質問 # 44
......