1Z0-1057-23合格させる問題集でOracle24時間で試験合格できます [Q54-Q73]

Share

1Z0-1057-23合格させる問題集でOracle24時間で試験合格できます

最新問題を使おう1Z0-1057-23試験問題と解答でPDFで一年間無料更新

質問 # 54
Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)

  • A. After the creation of Sub Task 1, Project Start Date would remain unchanged as 01-Jul-2016 and Sub Task 2 would be created with 15-Jun-2016.
  • B. After the creation of Sub Task 1, Project Start Date would be changed to 15-Jun-2016 and Sub Task 2 would be created with 15-Jun-2016.
  • C. Project Start Date would remain unchanged as 01-Jul-2016 for both actions but the start dates on both subtasks would remain 15-Jun-2016.
  • D. After the creation and saving of Sub Task 1, Task Start Date would be changed to 01-Jul-2016 and Sub Task 2 would be created with 01-Jul-2016.

正解:B

解説:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjf/manage-project-plan-tasks-and-task-assignments.html#OAPJF75076


質問 # 55
Which two statements are true about the borrowed and lent cross charge method?

  • A. This method creates accounting entries that move an amount equal to the transfer price between the provider and receiver organizations
  • B. Internal Invoice is not generated with this method.
  • C. This method allows you to process cross charge transactions across legal entities.
  • D. You must set up a contract business unit to use this method.

正解:B

解説:
The borrowed and lent cross charge method is a method that allows you to process cross charge transactions between provider and receiver organizations that belong to different legal entities within the same primary ledger. This method does not generate internal invoices or intercompany accounting entries for cross charge transactions. Instead, this method creates accounting entries that move an amount equal to the transfer price between the provider and receiver organizations using borrowed and lent accounts. Two statements that are true about this method are:
Internal Invoice is not generated with this method. This method does not create internal invoices for cross charge transactions, as these transactions are accounted within the same primary ledger using borrowed and lent accounts.
This method allows you to process cross charge transactions across legal entities. This method allows you to process cross charge transactions between provider and receiver organizations that belong to different legal entities within the same primary ledger, as long as they share the same chart of accounts, calendar, currency, and subledger accounting method.


質問 # 56
Your customer accounts revenue based on, product class category. Because all your customer''s projects are funded by private and government institutions, they decide to classify all projects based on their funding source to accurately report on revenue in General Ledger. Accordingly, you create a new class category "Funding Source" and assign it to all projects. However, you notice that the accounting is still happening based on product class category. Identify the reason for this problem. (Choose the best answer.)

  • A. Product class category is not enabled for "available as accounting source".
  • B. Funding source class category is not enabled for "available as accounting source".
  • C. Funding source class category is assigned to all project types.
  • D. Funding source class category is enabled for "available as accounting source".

正解:B

解説:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-foundation-configuration-define-types-and-categorizations.html#OAPFM222700 Topic - Manage Project Class Categories Setting Up Class Categories: Points to Consider Available as Accounting Source This option indicates if the class category is available as an accounting source so that Oracle Fusion Subledger Accounting can use the category to create mapping sets, account rules, journal line rules, and description rules.
Only one class category at a time is available as an accounting source in Oracle Fusion Subledger Accounting. To change the class category that Oracle Fusion Subledger Accounting uses, deactivate the old class category and create a new one with a different date range.


質問 # 57
Identify two correct role templates available on the Oracle Entitlement Server to generate roles for Project Organization Security.

  • A. Project Administrator Template for Project Organization Security
  • B. Project Billing Specialist Template for Project Organization Security
  • C. Project Accountant Template for Project Organization Security
  • D. Project Creator Template for Project Organization Security
  • E. Project Manager Template for Project Organization Security

正解:A

解説:
Reference https://docs.oracle.com/en/cloud/saas/applications-common/r13-update17d/faser/implementing-security-in-oracle-fusion-project-portfolio-management.html#FASER1722595 Ref to "Securing Project Financial Management and Grants Management Applications" Table lists predefined enterprise roles and the type of security that grants the role access to data in a work area or dashboard.
Enterprise Role
Work Area or Dashboard
Data Security Based On
Project Accountant
Asset
Project business unit
Project Accountant
Costs
Project expenditure business unit
Project Accountant
Revenue
Contract business unit
Project Administrator
Project Financial Management
Project business unit
Project organization
Project Billing Specialist
Invoices
Contract business unit
Project Creator
Project Financial Management
Project business unit
Project organization
Project Management Duty
Project Management Infolet Dashboard
Project assignment
Project Management Duty
Project Performance Dashboard
Project assignment
Project Manager
Project Management Infolet Dashboard
Project assignment
Project Manager
Project Performance Dashboard
Project assignment
Project Manager
Project Management
Project assignment
Project Manager
Project Manager Dashboard
Project assignment
Project Team Member
Project Financial Management
Project assignment
Grants Accountant
Invoices
Contract business unit
Grants Accountant
Revenue
Contract business unit
Grants Administrator
Awards
Contract business unit
Grants Administrator
Contracts
Contract business unit
Grants Administrator
Project Financial Management
Project business unit
Principal Investigator
Awards
Award assignment
Principal Investigator
Contracts
Award assignment
Principal Investigator
Project Financial Management
Project assignment


質問 # 58
Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS.
Identify two correct statements about the periodic project labor demand.
Response:

  • A. Labor Demand FTE is calculated as Quaterly Allocation hours divided by Quarterly FTE hours, if a quarter is used as the basis for viewing labor demand.
  • B. Labor Demand FTE is calculated as Yearly Allocation hours divided by Yearly FTE hours, if a year is used as the basis for viewing labor demand.
  • C. Labor Demand FTE is calculated as Monthly Allocation hours divided by Monthly FTE hours, if a period is used as the basis for viewing labor demand.
  • D. Labor Demand FTE is calculated as Project Allocation hours divided by Project FTE hours, if project duration is used as the basis for viewing labor demand.

正解:A、D


質問 # 59
You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and subtasks applicable to each of the phases of the project: Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want to define deliverables for your project requirements that are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect.

  • A. The association of a deliverable with a task is dependent on associating a requirement with a task.
  • B. A deliverable associated with a requirement is automatically associated with the tasks created for that requirement.
  • C. You associate a deliverable with a task, independent of associating a requirement with a task.
  • D. A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.

正解:D

解説:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapem/define-project-deliverables.html#OAPEM1122079 Associate deliverables with one or many tasks or requirements at any level. Associate existing deliverables to tasks or requirements or create deliverables directly for tasks or requirements. You can delete a deliverable in New status if it is not associated with tasks or requirements.
Can deliverables for projects and tasks be inherited from associated requirements?
No. A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.
You associate a deliverable with a task, independent of associating a requirement with a task.


質問 # 60
Your company creates a separate project for infrastructure services, so as to track these costs separately and then allocate to various projects that use the services of the infrastructure team. You want to allocate these costs by first attributing a fixed percentage of the source amount to each project and then spread it across tasks based on the actual labor hours charged to each task.
Which allocation basis method would you use to meet this requirement? (Choose the best answer.)

  • A. spread evenly
  • B. target percentage and prorate
  • C. target percentage and spread evenly
  • D. prorate

正解:B

解説:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjc/allocate-project-costs.html#OAPJC94831 Spread Evenly The allocation rule divides the source pool amount equally among all the chargeable target tasks included in the rule. This is the most simple and direct basis method.
Target Percentage and Spread Evenly
Specify the percentage of the source pool that is required to allocate to each target line. The total specified target percentage must always equal 100 percent. The allocation rule calculates the amount to allocate to the target line, and then spreads the results evenly among the chargeable tasks.
Prorate
The allocation generation uses the attributes defined in the allocation rule to derive the rate at which the source pool amount is apportioned among the target projects and tasks. For this basis method, the allocation rule uses the basis attributes to apportion the source amount among all the tasks defined by the rule. The Prorate basis method provides precise control over how the rule distributes the source pool.
Target Percentage and Prorate
The allocation rule first uses the target percentage to calculate the amount to allocate to the line, and then apportions the results among all the tasks. The Target Percentage and Prorate basis method provides precise control over how the rule distributes the source pool.


質問 # 61
Stigma Consulting wants to implement the program management capability to coordinate and track their strategic programs.
Which three components are required to configure the program options as part of implementing the program management capability? (Choose three.)

  • A. Currencies
  • B. Derivation Methods
  • C. Calendar
  • D. Calculation Methods
  • E. Accounting Methods

正解:C

解説:
Program management is a capability that allows you to coordinate and track multiple related projects and tasks as part of a strategic program. To configure the program options as part of implementing the program management capability, you need to define three components:
Calendar: This component allows you to specify the calendar that is used to calculate the dates and durations for the program and its projects and tasks.
Calculation Methods: This component allows you to specify the methods that are used to calculate the progress, performance, and variance measures for the program and its projects and tasks based on various sources and formulas.
Derivation Methods: This component allows you to specify the methods that are used to derive the attributes and values for the program and its projects and tasks based on various rules and conditions. Currencies and Accounting Methods are not components that are required to configure the program options. Currencies are used to define the currency conversion rates and rules for the program and its projects and tasks. Accounting Methods are used to define the subledger accounting rules and options for the program and its projects and tasks. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-programs.html#OAPFM2356261


質問 # 62
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem.

  • A. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
  • B. Unaccounted transactions have not been swept to the next period.
  • C. The corresponding Oracle Payables Cloud accounting period has not been closed.
  • D. Unaccounted transactions are not imported.
  • E. Pending burden summarization items have not been processed.

正解:A

解説:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record-accounting-for-project-billing.html#OAPJB340382 Topic - Accounting Period and Project Accounting Period Closing: How Validation Works


質問 # 63
Stigma consulting has been hired by a client to implement Project Management Cloud. Which role should they assign to a user for using the rapid implementation feature to set up the Project Financial Management offering by populating and uploading a Microsoft Excel workbook?

  • A. Project Integration Specialist
  • B. Project Executive
  • C. Project Application Administrator
  • D. Project Administrator

正解:A

解説:
The Project Integration Specialist role should be assigned to a user for using the rapid implementation feature to set up the Project Financial Management offering by populating and uploading a Microsoft Excel workbook. This role allows the user to access the Functional Setup Manager and perform the common setups for project costing and billing using predefined templates and spreadsheets. The user can also monitor and validate the setup data using reports and dashboards. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/implement-project-financial-management-applications.html#OAPFM2356151


質問 # 64
Identify two attributes for which you can enter budgets that will be considered for Budgetary Controls in Project Portfolio Management.

  • A. project
  • B. project classification
  • C. expenditure item
  • D. project plan type
  • E. resource

正解:A

解説:
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/OAPJF/OAPJF1121937.htm#OAPJF1121937


質問 # 65
Which setup option is common to both financial and project plan types?

  • A. Enable the entry of plan amounts in currencies other than the project currency.
  • B. Manage the options for creating control budgets in Oracle Fusion Budgetary Control.
  • C. Enable the use of a workflow for managing budget or forecasting status changes.
  • D. Identify whether the plan type is the default selection when you create budget or forecast versions.

正解:A

解説:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-control-configuration-manage-financial-and-project-plan-types.html#OAPFM75315 Financial and Project Plan Setup Options The following table describes the basic budget, forecast, or project plan setup options that determine how a plan type is used in the context of a project. Except for third-party scheduling, you can,t edit these options at the project level.
Option
Location
Description
Planning amounts
Financial plan type
Indicates that the financial plan type supports the creation of versions with the following amounts:
Cost amounts
Revenue amounts
Both cost and revenue amounts
Either cost or revenue amounts
Approved budget or primary forecast
Financial plan type
Determines whether a financial plan type is used for creating approved budget versions or primary forecast versions that are used for plan comparison or project performance reporting.
Default financial plan type
Financial plan type
Determines whether the financial plan type is the default selection when you create budget or forecast versions.
Workflows
Financial plan type
Enables the use of a workflow for managing budget or forecast status changes.
Third-party scheduling software
Project plan type
Indicates whether project planning is performed in Microsoft Project.
If third-party scheduling is disabled in the project plan type, you can use the associated project or project template to create a project in Microsoft Project. However, you can,t export the new project or link it to one created in Oracle Fusion Project Portfolio Management.
Multiple transaction currencies
Financial and project plan type
Enables entry of plan amounts in currencies other than the project currency.
Budgetary control settings
Financial plan type
Manages options for creating control budgets in Oracle Fusion Budgetary Control.


質問 # 66
Which two are the workflows in Project Financial Management?

  • A. Capital Interest Calculation
  • B. Expenditure Item Adjustment
  • C. Burden Cost Recalculation
  • D. Asset Line Generation
  • E. Project Status Change

正解:B

解説:
The workflows in Project Financial Management are business processes that automate the approval and notification tasks for various project transactions and events. Two of the workflows in Project Financial Management are:
Project Status Change: This workflow manages the approval and notification tasks for changing the status of a project or task from one value to another. For example, when a project or task is submitted for approval, this workflow routes the request to the appropriate approvers and notifies them of the action required.
Expenditure Item Adjustment: This workflow manages the approval and notification tasks for adjusting expenditure items that have been charged to a project or task. For example, when an expenditure item is adjusted by a project manager or a cost accountant, this workflow routes the adjustment to the appropriate approvers and notifies them of the action required. Capital Interest Calculation, Burden Cost Recalculation, and Asset Line Generation are not workflows in Project Financial Management, but processes that perform various calculations and transactions for project costs and assets. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-financial-management.html#OAPFM2356161


質問 # 67
After completing setups in a source environment, your customer wants to move the setup data to a target environment.
Identify the two statements related to task list scope, which you must consider before taking a decision based on the customer requirement.
Response:

  • A. Exported setup data can be filtered by specific scope values if the business object has scope enabled for the setup data export.
  • B. Exported setup data cannot be filtered by specific scope values if the business object has scope enabled for the setup data export.
  • C. A scope value is used to assign users who can perform a task within an implementation project.
  • D. A task list can be segmented by a scope value and a task can be performed for each qualifying value of the selected object.

正解:C、D


質問 # 68
Shift is one of the key elements in defining project and resource calendars.
Which two additional key elements are required to define the project and resource calendars?

  • A. Time off
  • B. Accounting Calendar
  • C. Workday Patterns
  • D. Expenditure Type
  • E. Schedule Exceptions

正解:E

解説:
Shift is one of the key elements in defining project and resource calendars. Two additional key elements that are required to define the project and resource calendars are:
Schedule Exceptions: These are dates or periods that override the regular workday patterns and shifts of a calendar. They can be used to define holidays, vacations, or other special events that affect the availability of resources or projects.
Workday Patterns: These are patterns of working and nonworking days that repeat over a period of time. They can be used to define the standard working days and hours for a calendar. Time off, expenditure type, and accounting calendar are not key elements in defining project and resource calendars. Time off is an attribute of a resource assignment that reduces the availability of a resource. Expenditure type is a classification of costs that determines how they are processed and accounted. Accounting calendar is a calendar that defines the accounting periods and dates for transactions. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-resources.html#OAPFM2356131


質問 # 69
You are trying to create a custom infolet but are not able to find the "Create Infolet" option in the Infolet repository window. Which two steps should be completed before you can access the "Create Infolet" option?

  • A. You must activate Page Composer.
  • B. You should be on the Project Custom Objects page.
  • C. You must be in an active sandbox.
  • D. You should enable the "Create Infolet" option from the Personalize Springboard page.

正解:B

解説:
Ref: https://docs.oracle.com/cd/E83857_01/saas/applications-common/18b/oaext/page-modification.html#OAEXT1640891


質問 # 70
Identify the valid approval group type applicable to Oracle Project Financial Management Cloud. (Choose the best answer.)

  • A. Job
  • B. Static
  • C. Position
  • D. Flexfield
  • E. Dynamic

正解:B

解説:
Ref: https://docs.oracle.com/en/cloud/saas/applications-common/19b/facia/define-approval-management.html#FACIA3124477 Topic Approval Groups Each approval group includes a set of users that you configure to act on tasks in a certain pattern. Tasks can be defined to get routed to an approval group instead of an individual user. You can nest approval groups within approval groups.
You have two options for defining the group:
Static: Select the specific users to include in the group.
Dynamic: Provide the logic to use to determine the users in the group.


質問 # 71
Which two privileges are assigned to the Project Plan Management duty in Security Reference Implementation?

  • A. Manage Project Plan Resource Assignment
  • B. View Project Progress
  • C. Allocate Project Expense
  • D. Transfer Project

正解:A

解説:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjm/index.html#_Toc468200732_1_12 Topic - Privileges - This table lists privileges granted to duties of the abstract role Project Management Duty.
Granted Role - Project Plan Management
Privilege - only A and C are listed


質問 # 72
When scheduling the Update Project Performance Data process to run on a periodic basis, which summarization method would you select? (Choose the best answer.)

  • A. Bulk
  • B. Summary
  • C. Detail
  • D. Incremental

正解:D

解説:
Reference https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/define-project-organizations.html#OAPFM177674 Settings That Affect Performance Data Summarization You can summarize performance data for a project unit, business unit, a range of projects, or projects managed by a project manager. When you run the Update Project Performance Data process from the Scheduled Processes page, select one of the summarization methods from the following table:
Summarization Method
Usage
Incremental
Summarizes new transactions that are yet to be summarized
Delete and re-summarize
Correct summary data when the source system data changes outside the regular transaction flow.
Do not use this summarization method when you run the Update Project Performance Data Without Producing Report process unless you are advised to do so.
Resource breakdown structure
Migrate all summary data from one resource breakdown structure version to the next.
If you select this option, you must also specify the resource breakdown structure header.


質問 # 73
......