質問 43
What do you do during Sprint Execution? Please choose the answer.
- A. Present status of selected user stories in the sprint scope on a scrumboard
- B. Measure the sprint progress with a percentage complete report
- C. Hold a retrospective at the end of each week
- D. End a sprint when the sprint backlog items are all complete
正解: B
質問 44
What is the primary function of the Starter System in the Fit-to-Standard workshops?
- A. To configure and test the solution in a sandbox
- B. To gather the customer's detailed configuration requirements
- C. To provide a secondary sandbox that will be maintained by the customer post go-live
- D. To demonstrate SAP Best Practices
正解: D
質問 45
What are key characteristics of the implementation approach in SAP Activate Methodology? There are 3 answers to this question.
- A. Premium engagement ready
- B. On-premise only
- C. Validate solution
- D. Fixed scope
- E. Start with SAP Best Practices
正解: A,C,E
質問 46
Which of the following personas is one of the key personas of the business process monitoring application?
- A. Chief executive officer
- B. Configuration expert
- C. Operation control center lead
- D. Process manager
正解: D
質問 47
The hypercare period is part of which phase?
- A. Deploy
- B. Explore
- C. Go-Live
- D. Realize
正解: A
質問 48
Which artifacts in the Testing workstream are created within the Realize phase for the "New Implementation of SAP S/4HANA Cloud" transition path? Note: There are 2 correct answers to this question.
- A. Reporting Functional Specifications
- B. Functional Specifications
- C. User Acceptance Test
- D. Functional Test Scenarios
正解: C,D
質問 49
Which types of tests are supported by Test Management in SAP Cloud ALM? Note: There are 2 answers to this question.
- A. Manual testing
- B. Integration of automated testing
- C. System testing
- D. Acceptance testing
正解: A,B
質問 50
What information does the project team need before they can correctly estimate the relative size of backlog user stories?
- A. Definition of Done
- B. Overall project schedule
- C. Test strategy
- D. Available project resources
正解: A
質問 51
What is the term used for workshops, which are intended to set value targets, validate SAP Standard functionality against customer requirements.
And collect delta requirements in the "New Implementation of SAP S/4HANA" transition path?
- A. Fit-to-Standard
- B. Design Thinking
- C. Delta Design
- D. Solution Validation
正解: D
質問 52
Which accelerators support the fit-to-standard workshop in the Explore phase? 2 correct answers
- A. quality gate chaclist
- B. Backlog template
- C. Business-driven configuration questionarie
- D. test strategy
正解: B,D
質問 53
Which activities are part of the Design and Configuration application of the SAP Activate methodology?
There are 2 answers to this question
- A. Confirm Integration prerequisites
- B. Conduct Scope Validation
- C. Perform Fit/Gap Analysis
- D. Schedule kick-off workshop
正解: B,C
質問 54
SAP now offers the ability to deploy and manage solutions in which of the following environments? Please choose the correct answer.
- A. Cloud and On-premise
- B. Cloud
- C. Cloud, on premise & hybrid
- D. On-premise
正解: C
質問 55
What are some of the values of SAP Cloud ALM operations? 3 correct answers
- A. it provides reduced cost of operations
- B. it provides a solution readiness check
- C. it provides improved efficiency and automation
- D. it provides license management capabilities
- E. it provides end-to-end transparency
正解: A,C,E
質問 56
What can be found in the SAP Solution Implementation Roadmaps?
- A. Detailed description of implementation tasks
- B. Accelerators to be used in the Project Library
- C. Value Maps
- D. Deliverables in each Phase
正解: A,B,D
質問 57
What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path? There are 2 answers to this question.
- A. SAP S/4HANA uses the implementation guide (IMG) and the in-app extensibility option for Configuration and development, and SAP S/4HANA Cloud uses SSCUs and the side- by-side Extensibility option
- B. There are different roles in the application design and configuration workstream
- C. Upgrade of SAP S/4HANA cloud are managed by SAP, and upgrades of SAP S/4HANA are managed by the customer
- D. Different sets of workstreams are used for these transition paths
正解: A,C
質問 58
In which SAP Activate methodology phase does the team complete the Integration Validation? Please choose the correct answer.
- A. Explore
- B. Realize
- C. Prepare
- D. Deploy
正解: B
質問 59
What can cloud-centric customers do with SAP Cloud ALM?
- A. Track cloud services
- B. Configure their cloud products
- C. Update cloud releases
- D. Manage the Intelligent Enterprise
正解: D
質問 60
Which new project roles are introduced with the SAP Activate methodology for the Agile delivery approach, compared to waterfall? 2 correct answers
- A. Product owner
- B. Integration lead
- C. Design thinking coach
- D. Scrum master
正解: A,D