Which of the following tasks does the system perform during reorder point planning? Note: There are 2 correct answers to this question.

  • A. Flag materials that have been subject to an activity relevant to MRP
  • B. Perform backward scheduling to determine the availability dates of purchase requisitions
  • C. Carry out a net requirement calculation for every material included in the planning run
  • D. Carry out a lot-size calculation for every material with net requirements

正解:C、D

解説:
Explanation
During reorder point planning, the system performs a net requirement calculation for every material included in the planning run and carries out a lot-size calculation for every material with net requirements. The system does not flag materials that have been subject to an activity relevant to MRP or perform backward scheduling to determine the availability dates of purchase requisitions2 References: SAP Help Portal - Reorder Point Planning


質問 # 38
You want to create a purchase document for several minor repairs that may occur over a period of time. They should NOT exceed atotalamount in this period. Furlher details are NOT available.
Which type of purchasing document is best suited tor this puroose?

  • A. Blanket purchase order
  • B. Service purchase order
  • C. Release purchase order
  • D. Invoicing plan

正解:A

解説:
Explanation
A blanket purchase order is the best suited type of purchasing document for this purpose. A blanket purchase order is a long-term agreement with a vendor for several minor repairs that may occur over a period of time.
You can specify an overall limit value for the blanket purchase order and enter the account assignment information without specifying any material or quantity details. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4520, Unit 2, Lesson 1.


質問 # 39
What are some advantages of a stock transport order compared to a stock transfer posting between two plants?
Note; There are 3 correct answers to this question.

  • A. You can post goods receipt to consumption.
  • B. You can create stock transport requisitions via MRP.
  • C. You can plan delivery costs.
  • D. You can post goods receipt in consignment.
  • E. You can issue from inspection stock.

正解:A、B、C


質問 # 40
You have several valid purchasing info records for one specific material available in your system. What is the system behavior when you manually create a purchase requisition?

  • A. The system will choose the info record from the last purchase order.
  • B. The system will list all valid records and the user needs to select one.
  • C. The system will choose the info record with the lowest price.
  • D. The system will choose the most recent info record.

正解:B

解説:
Explanation
When you manually create a purchase requisition, the system will list all valid records and the user needs to select one. The system will not choose the most recent info record, the info record with the lowest price, or the info record from the last purchase order.References: [SAP Help Portal - Creating Purchase Requisitions Manually]


質問 # 41
Which of the following procurement proposals can be created during an MRP Live planning externally procured materials? Note: There are 2 correct answers to this question.

  • A. Planned order
  • B. Delivery schedule line
  • C. Purchase requisition
  • D. Purchase order

正解:B、C


質問 # 42
For which of the following business scenarios does a situation template exist in Situation Handling? Note:
There are 2 correct answers to this question.

  • A. A purchase order approval is pending.
  • B. The due date for a blocked invoice has passed.
  • C. A supplier confirmation is pending.
  • D. A contract is ready as a source of supply.

正解:C、D

解説:
Explanation
Situation Handling is a feature that helps users deal with situations that require their attention or action. A situation template is a predefined configuration that defines the rules and actions for a specific type of situation. For the following business scenarios, a situation template exists in Situation Handling:
A supplier confirmation is pending, which means that a vendor has not confirmed a purchase order or has confirmed it with different conditions than expected.
A contract is ready as a source of supply, which means that a contract has been released and can be used as a valid source of supply for purchase requisitions or purchase orders. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4520, Unit 8, Lesson 1.


質問 # 43
Which object is determined using an access sequence in message determination?

  • A. Message schema for a document category
  • B. Output condition record for a message type
  • C. Output device in an output condition record
  • D. Message type in a message schema

正解:B


質問 # 44
You send newly created purchase orders to a supplier via EDI,whereas quantity or price changes are transmitted by e-mail. What prerequisites must be met if you are using the condition technique for message determination? Note: There are 3 correct answers to this question.

  • A. The dispatch time related to the change message needs to be set to 1 (send with periodically m scheduled job).
  • B. The Price and Quantity fields are relevant for printout changes.
  • C. You have configured different message types for the New and Change print options
  • D. The condition record contains the Price and Quantity fields.
  • E. The New Message Determination Process for Change Messages indicator is flagged in Customizing.

正解:A、B、E


質問 # 45
What can you create to plan materials differently within a plant?

  • A. Storage bins
  • B. MRP areas
  • C. Production supply areas
  • D. Vendor consignment info records

正解:B


質問 # 46
For which of the following transactions do you receive an error message if the automatic account determination is set up incorrectly? Note: There are 3 correct answers to this question.

  • A. Stock transfer between company codes
  • B. Material price change
  • C. Stock transfer posting between stock types
  • D. Goods receipt into blocked stock
  • E. Purchasing info record price change

正解:A、C、D

解説:
Explanation
The automatic account determination is used to assign the correct general ledger accounts for the inventory postings. If the account determination is set up incorrectly, the system will issue an error message when posting a transaction that affects the inventory value or quantity. The transactions C, D, and E are examples of such transactions, as they involve stock movements between different valuation areas, stock types, or company codes. The transactions A and B do not affect the inventory value or quantity, as they only change the material master data or the purchasing info record.References: SAP Help Portal, SAP Community


質問 # 47
Your MRP run detects a shortage of 2000 pieces for a material with an active quota arrangement. Each of your two suppliers can only supply 1000 pieces at once. What must you maintain to have MRP generate a procurement proposal for 1000 pieces for each supplier? Note: There are 2 correct answers to this question.

  • A. Set a maximum quota quantity in the quota arrangement item for each supplier
  • B. Set a maximum lot size in the quota arrangement item and activate the lx checkbox
  • C. Assign the indicator for quota splitting to the lot-sizing procedure being used
  • D. Assign a rounding profile in the material master record of the planned material

正解:A、B

解説:
Explanation
To have MRP generate a procurement proposal for 1000 pieces for each supplier, you must maintain the following:
Set a maximum lot size in the quota arrangement item and activate the lx checkbox, which means that MRP will split the total requirement quantity according to the quota allocation and create one procurement proposal per quota arrangement item.
Set a maximum quota quantity in the quota arrangement item for each supplier, which limits the total quantity that can be procured from each supplier within a validity period. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4525, Unit 1, Lesson 1.


質問 # 48
Where does SAP S/4HANA store low-level code? Note:There are 2 correct answers to this question.

  • A. Planning file
  • B. Material Master
  • C. Bill of material
  • D. Production version

正解:A、C

解説:
Explanation
SAP S/4HANA stores low-level code in the following objects:
Bill of material (BOM), which is a structured list of components that make up a product or assembly.
Planning file, which is an internal table that contains information about materials that need to be planned by MRP. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4525, Unit 1, Lesson 1.


質問 # 49
You have agreed on a value contract with a supplier for packaging. The exact materials and their purchase prices are NOT specified until the release orders. Which item category must you use wh creating the contract?

  • A. B (Limit)
  • B. M (Material unknown)
  • C. W (Material group)
  • D. T (Text)

正解:C


質問 # 50
For which of the following docum workflow for purchasing?

  • A. Scheduling agreement
  • B. Purchase requisition
  • C. Purchase order
  • D. Request for quotation

正解:B

解説:
Explanation
You can configure the workflow for purchasing for a purchase requisition. A workflow is a sequence of tasks that are performed by different agents according to predefined rules and conditions. A workflow for purchasing can automate and streamline the approval process for a purchase requisition, which is an internal document that requests the procurement of a material or service. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4520, Unit 1, Lesson 1.


質問 # 51
Which of the following are prerequisites for flexible workflows for purchase order approval? Note: There are
3 correct answers to this question.

  • A. Define the recipients for the flexible workflow in the Manage W orkflows for Purchase Orders SAP Fiori app
  • B. Set up the preconditions for the flexible workflow in the Manage W orkflows for Purchase Orders SAP Fiori app
  • C. Deactivate the classic release procedure for purchase orders in Customizing
  • D. Activate the flexible workflow for purchase orders in Customizing
  • E. Create a class with flexible workflow characteristics for purchase orders

正解:A、B、D


質問 # 52
What are some of the consequences of setting the Delivery Completed indicator in a purchase order (PO) item? Note: There are 2 correct answers to this question.

  • A. The PO item CANNOT be deleted and archived.
  • B. The commitment for the PO item will increase.
  • C. You can still post goods receipts of remaining quantities.
  • D. The PO item is skipped when delivery reminders are generated.

正解:C、D

解説:
Explanation
The Delivery Completed indicator in a purchase order item signals that no more goods receipts are expected for this item. Some consequences of setting this indicator are:
You can still post goods receipts of remaining quantities if you have not received the full ordered quantity yet. However, you cannot post goods receipts that exceed the ordered quantity.
The purchase order item is skipped when delivery reminders are generated by the system. Delivery reminders are messages that are sent to vendors to remind them of overdue deliveries orupcoming delivery dates. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4520, Unit 2, Lesson 1.


質問 # 53
Which of the following can you control with the confirmation control key? Note: There are 2 correct answers to this question.

  • A. Default reminder levels for outstanding confirmations
  • B. The sequence of required confirmations
  • C. The document type for the goods receipt
  • D. Whether a confirmation is a prerequisite for a goods receipt

正解:B、D

解説:
Explanation
The confirmation control key determines the sequence of required confirmations and whether a confirmation is a prerequisite for a goods receipt. It also controls the output type and the transmission medium for the confirmations1 References: SAP Help Portal - Confirmation Control Key


質問 # 54
......

更新されたPDF(2024年最新)実際にあるSAP C_TS452_2022試験問題:https://www.passtest.jp/SAP/C_TS452_2022-shiken.html

検証済みのC_TS452_2022試験問題集PDF[2024年最新] 成功の秘訣はPassTest:https://drive.google.com/open?id=18-XN-_0H03coGIFfpJGft919OrnQrzlc