2025年最新のPMI-CP問題集の無料PDFゲットせよ!最近更新された問題
PMI-CP認定試験問題集には360練習テスト問題
質問 # 114
During the contract performance phase, what is the primary focus of contract administration?
Response:
- A. To create a detailed project schedule
- B. To escalate disputes
- C. To ensure that both parties fulfill their obligations
- D. To track project expenses
正解:C
質問 # 115
In construction project management, what does the term "float" refer to?
Response:
- A. The amount of time an activity can be delayed without impacting the project schedule
- B. The duration of critical path activities
- C. The time it takes for a project to be completed
- D. The total time a project is allowed to be delayed without penalties
正解:A
質問 # 116
What is the primary goal of setting up scope governance structures and practices on built environment projects?
Response:
- A. To ensure that the project,s scope is effectively defined, managed, and controlled
- B. To escalate conflicts
- C. To track project expenses
- D. To eliminate project risks
正解:A
質問 # 117
Which of the following documents outlines the roles, responsibilities, and relationships of the project stakeholders, including the project manager, team members, and other involved parties?
Response:
- A. Stakeholder Management Plan
- B. Project Management Plan
- C. Project Charter
- D. Project Scope Statement
正解:A
質問 # 118
During the scope development process, what is the role of a scope baseline?
Response:
- A. To allocate project resources
- B. To escalate conflicts
- C. To eliminate project risks
- D. To provide a reference point for comparing actual project performance against planned performance
正解:D
質問 # 119
During strategy and scope management, what is the role of a Scope Baseline?
Response:
- A. To allocate project resources
- B. To escalate conflicts
- C. To eliminate project risks
- D. To provide a reference point for comparing actual project performance against planned performance
正解:D
質問 # 120
During the scope management process, what is the role of a scope baseline?
Response:
- A. To initiate contract termination
- B. To escalate conflicts
- C. To track project expenses
- D. To provide a reference point for comparing actual project performance against planned performance
正解:D
質問 # 121
In the context of scope management, what is the primary focus of scope definition?
Response:
- A. To allocate project resources
- B. To escalate conflicts
- C. To eliminate project risks
- D. To clearly and precisely describe the project,s deliverables and requirements
正解:D
質問 # 122
What term is used to describe the process of evaluating the potential impacts of changes to the project scope on other project aspects?
Response:
- A. Risk Management
- B. Change Verification
- C. Stakeholder Engagement
- D. Change Impact Analysis
正解:D
質問 # 123
What term is used to describe the process of ensuring that the project's scope is well-defined, complete, and accurate?
Response:
- A. Scope Verification
- B. Scope Definition
- C. Risk Management
- D. Scope Audit
正解:B
質問 # 124
What term is used to describe the process of defining the specific steps, tasks, and resources needed to achieve project objectives?
Response:
- A. Project Execution Plan
- B. Risk Management
- C. Stakeholder Engagement
- D. Work Breakdown Structure (WBS)
正解:A
質問 # 125
During the contracts management process, what is the role of a Contract Closeout process?
Response:
- A. To allocate project resources
- B. To formally close out the contract and ensure that all obligations have been fulfilled
- C. To escalate conflicts
- D. To eliminate project risks
正解:B
質問 # 126
During stakeholder engagement, what is the role of a Stakeholder Engagement Feedback Loop?
Response:
- A. To allocate project resources
- B. To escalate conflicts
- C. To continuously gather feedback, assess stakeholder satisfaction, and make improvements
- D. To eliminate project risks
正解:C
質問 # 127
During the contracts management process, what is the role of a Statement of Work (SOW)?
Response:
- A. To allocate project resources
- B. To outline the project,s scope, objectives, deliverables, and requirements
- C. To escalate conflicts
- D. To eliminate project risks
正解:B
質問 # 128
What is the primary goal of the procurement execution process in construction projects?
Response:
- A. To allocate project resources
- B. To ensure that purchased goods and services are delivered as planned
- C. To track project expenses
- D. To eliminate project risks
正解:B
質問 # 129
In the context of the change order process, what is the primary role of a change control board?
Response:
- A. To allocate project resources
- B. To review and make decisions about proposed changes to the project
- C. To escalate conflicts
- D. To eliminate project risks
正解:B
質問 # 130
......