質問 # 16
What is the minimum number of quality gates mandated by the SAP Activate methodology?
Please choose the correct answer.
Response:
- A. 0
- B. 1
- C. 2
- D. 3
正解:A
質問 # 17
Which Value Chains does SAP Solution Manager 7.2 deliver? Note:There are 3 correct answers to this question.
- A. Hire-to-Retire
- B. Cash-to-Order
- C. Detect-to-Correct
- D. Request-to-Fulfill
- E. Requirements-to-Deploy
正解:C、D、E
質問 # 18
Which activity helps the project team add user stories to the product backing?
- A. Planning the user acceptance test
- B. Conducting the solution validation workshop
- C. Preparing a project schedule
- D. Assessing project risks
正解:B
質問 # 19
What information does the project team need before they can.
- A. Overall project schedule
- B. Test strategy
- C. Available project resources
- D. Definition of done
正解:D
質問 # 20
Ready-to-use Content in SAP Activate includes which of the following?
There are 2 correct answers to this question.
Response:
- A. Business models from leading companies in each industry sector
- B. Courses delivered by SAP Education
- C. Project Accelerators
- D. SAP Best Practices
正解:C、D
質問 # 21
What Solution Operations Framework can customers use to create a joint Business and IT organization, that will secure transparency and efficiency of SAP implementation, innovation, operation, and quality of business processes and systems?
Please choose the correct answer.
Response:
- A. Business Transformation Management Methodology
- B. SAP Operations Control Center
- C. Customer Center of Expertise
- D. SAP Activate
正解:C
質問 # 22
Which artifacts are part of the solution adoption workstream?
There are 3 correct answers to this question
- A. Project plan
- B. Business transformation review (point of view)
- C. System go live announcement(order)
- D. Detailed design-business process
正解:B、C、D
質問 # 23
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
Please choose the correct answer.
Response:
- A. User Stories are in a Ready state for NO more than the first three Sprints.
- B. Project scope and planning are completed and final.
- C. Timelines of the Sprint may differ due to the workload.
- D. Go-Live scope is fixed on the first of January the following year.
正解:A
質問 # 24
Which of the following belong to the Application Design and Configuration work stream for SAP S/4HANA Cloud in the Explore phase?
There are 2 correct answers to this question.
Response:
- A. Configuration definition
- B. Fit-to-standard workshop
- C. Kick-off workshop
- D. Integration prerequisites confirmation
正解:A、B
質問 # 25
What is the purpose of the Solution Validation activity in the Explore phase?
There are 3 correct answers to this question.
Response:
- A. To educate project participants
- B. To challenge changes to standard
- C. To verify technical installation
- D. To identify gaps
- E. To log additional scope items
正解:B、D、E
質問 # 26
In which phase do you verify that the SAP Best Practice solution scenarios meet the business needs of the customer?
Please choose the correct answer.
Response:
- A. Prepare
- B. Explore
- C. Realize
- D. Deploy
正解:B
質問 # 27
How do you achieve frequent checkpoints with the end user in an Agile delivery approach?
There are 2 correct answers to this question.
- A. Demo the SAP model company
- B. User acceptance test
- C. Solution review for waves
- D. Solution demo for sprints
正解:C、D
質問 # 28
Which of the following scenarios are enabled for the "Selective Data Transition" transition path with the SAP Landscape Transformation tool?
There are 3 correct answers to this question.
Response:
- A. Security Migration
- B. System Consolidation
- C. Consolidation through online data replication
- D. Extraction of Business Units
- E. System Upgrade
正解:B、C、D
質問 # 29
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?
Please choose the correct answer.
Response:
- A. Deploy
- B. Explore
- C. Prepare
- D. Realize
正解:A
質問 # 30
Which new role is introduced in the SAP activate methodology in a full scrum team?
- A. Application consultant
- B. Product owner
- C. Project manager
- D. System administrator
正解:A
質問 # 31
In which phase should you first run the SAP readiness check for SAP S/4HANA In a "selective data transition" transition path, in a system consolidation scenario That includes conversions from SAP ERP?
- A. Prepare
- B. Discover
- C. Explore
- D. Realize
正解:C
質問 # 32
In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project?
Please choose the correct answer.
Response:
- A. Prepare
- B. Explore
- C. Realize
- D. Deploy
正解:B
質問 # 33
......