質問 # 21
Which date type should an assignee update to change the completion date of a task?
- A. Projected Start Date
- B. Planned Completion Date
- C. Actual Completion Date
- D. Commit Date
正解:B
解説:
In Workfront, to update the planned completion of a task, the assignee should modify the "Planned Completion Date." This date is used for scheduling and planning purposes to track when the task is expected to be finished. Changing the "Planned Completion Date" adjusts the task's projected timeline and allows for a recalculation of project dependencies.
質問 # 22
A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.
Which action should the stakeholder take to log the risk?
- A. Log an issue on the project and explain that the completion date is at risk.
- B. Create a task in the project and set the Planned Completion Date for 2 weeks.
- C. Log a risk as part of the project business case and identify it as a "schedule" risk.
正解:C
解説:
In Adobe Workfront, risks associated with a project should be logged as part of the project business case. The "Risk" section within the business case allows stakeholders to document any potential threats to the project timeline, scope, or resources. Identifying this risk as a "schedule" risk helps communicate the potential delay to the project stakeholders and allows it to be tracked and mitigated effectively.
質問 # 23
A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?
- A. Visit the Reports page and create a task report and an issue report. In the filter tab for each report, update the "Pending Approval" filter to "true," and update the Project Owner ID field with the project manager's name. In the grouping tab for each report, add a grouping for project name. Add both reports to a new dashboard.
- B. Visit the Reports page and create a Pending Approvals report. In the filter tab, update the Project Owner ID field with the project manager's name and update the Object ID field to "tasks" and "issues." In the grouping tab, add a grouping for project name.
- C. Visit the Project page and create a new filter. Update the "Pending Approval" filter to "true" and update the Project Owner ID field to the project manager's name. In the grouping tab, add a grouping for project name.
正解:A
解説:
The most comprehensive approach is to create two separate reports-one for tasks and one for issues-with filters set for "Pending Approval." Grouping the results by project name ensures that the project manager can see all relevant tasks and issues organized per project. Adding these reports to a dashboard consolidates the information into a single view, providing easy access for tracking pending approvals.
質問 # 24
A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.
How should the project manager keep these team members apprised of updates?
- A. Subscribe the team members to the request.
- B. Make the team members all primary contacts on the request.
- C. Ask the team members to add the request to their favorites.
正解:A
解説:
In Adobe Workfront, team members can be subscribed to a request so that they receive updates whenever changes or comments are made. This ensures they stay informed of any progress or issues. Adding a request to favorites only bookmarks it for easy access, but does not trigger automatic notifications. Making multiple primary contacts is not an efficient way to handle notifications.
質問 # 25
A video designer is spending an excessive number of hours on a project that involves editing a TV commercial. The tasks are keeping the designer from completing other assigned work. After discussing the matter with the designer, the project manager determines that the additional hours for this project are necessary and suspects that the number of hours budgeted for the video designer's time on this project was too low in comparison to the actual need. The project manager will need data to illustrate the problem and potentially request more resources for this project so that the designer can still meet commitments on other assigned work.
Which native Project tool is designed to illustrate data on how the Planned Hours for the video designer on this project vary from the Actual Hours spent on the project?
- A. Workload Balancer
- B. Utilization
- C. Hours
正解:A
解説:
The Workload Balancer in Workfront is used to compare planned hours against actual hours worked, providing a clear view of resource allocation and over-utilization. In this case, the project manager can use the Workload Balancer to demonstrate how the video designer's planned hours for the project differ from the actual hours spent. This helps the project manager make data-driven decisions about resource adjustments.
質問 # 26
What item, when shared with a user, can never give that user inherited permission to a project?
- A. Portfolio
- B. Report
- C. Task
正解:B
解説:
Adobe Workfront, permissions can be inherited through various objects like projects, portfolios, or tasks when shared with users. However, when sharing a report, the permissions do not cascade to related items like projects or tasks within that report. This is because reports are generated views and do not directly control object-level permissions. A report can be shared to allow a user to see data within the report, but it will not grant them inherited permissions to the underlying projects or tasks displayed in that report.
質問 # 27
An organization has created unique data fields relevant to their projects. Starting by navigating from a project's landing page, where is this data found?
- A. Project Details > Overview
- B. Project Details > Custom Forms
- C. Business Case > Project Info
正解:C
解説:
In Workfront, custom data fields created for projects are typically found within the "Business Case" section, specifically under "Project Info." This area houses key project information and unique custom fields that are relevant to the project's setup. The "Project Details" section is more focused on task-related information and the overall summary of the project.
質問 # 28
What are two characteristics of a Group in Workfront? (Choose two.)
- A. A Group can be tagged in an Update thread communication.
- B. A user can be assigned as Group Administrator of a Group.
- C. A Group can be associated with a Company or a Project.
- D. A Group assignment is not required for a user.
正解:B、C
解説:
Groups in Adobe Workfront serve as organizational entities that can be associated with specific Companies or Projects to manage workflows or permissions more effectively. Additionally, each Group can have a Group Administrator assigned, who is responsible for managing the group's settings, permissions, and workflows. These roles and associations help in structuring how work and permissions are allocated across different teams or departments.
質問 # 29
Which project elements can be used to measure a project's adherence to its original schedule?
- A. Project baselines, planned completion dates, and actual completion dates
- B. Workload balancer data, planned completion dates, and expenses
- C. Number of tasks, actual completion dates, and project status
正解:A
解説:
To measure a project's adherence to its original schedule, the most critical elements are Project Baselines, Planned Completion Dates, and Actual Completion Dates. The baseline captures the original planned schedule, while the planned and actual completion dates provide the data to compare the project's progress against the initial schedule. This comparison helps project managers identify any deviations from the original plan and assess the project's performance.
質問 # 30
A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.
What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?
- A. Create projects but leave the roles in place without assigning users.
- B. Load the project template once the team has bandwidth to start on the project.
- C. Create a custom status for Backlog to use prior to using the Planning status.
正解:C
解説:
In Workfront, creating a custom status specifically for "Backlog" allows the team to differentiate between work that is pending capacity and work that is actively being planned. This prevents confusion and allows for better project tracking, ensuring that tasks move smoothly from backlog to the planning phase when appropriate.
質問 # 31
Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.
What may have caused the planned start date of Task 2 to remain the same?
- A. The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.
- B. The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.
- C. The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.
- D. The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.
正解:D
解説:
In this scenario, the fact that Task 2's start date did not shift automatically despite its dependency on Task 1 suggests that a manual override was applied, resulting in a Task Constraint of "Must Start On." This type of constraint locks a task to a specific date, preventing it from dynamically adjusting based on changes to its predecessor. The other options either do not explain why the start date remained static or involve user-specific scheduling conflicts, which would not affect the system-driven date adjustment.
質問 # 32
The art director is reviewing and approving a proof and has requested that they only get email notifications for a new proof or version. What Email alert option should be assigned to them on the workflow?
- A. Decisions and Notify recipients about this proof is not selected
- B. Disabled and Notify recipients about this proof is selected
- C. Decisions and Notify recipients about this proof is selected
- D. Disabled and Notify recipients about this proof is not selected
正解:B
解説:
For the art director to only receive email notifications about new proofs or versions, the option "Disabled and Notify recipients about this proof is selected" is the correct choice. This ensures that they are not inundated with notifications about every comment or decision made but are alerted when a new proof or version is uploaded for review.
This approach optimizes the notification settings based on the user's request, providing a more focused and less overwhelming email experience, which is often crucial for roles such as creative directors who manage multiple proofs and versions.
質問 # 33
Which project Condition is set when the Progress Status of the project is Behind or At Risk?
- A. Late
- B. In Trouble
- C. At Risk
正解:C
解説:
In Adobe Workfront, when a project's progress status is marked as Behind or At Risk, the project condition is set to At Risk. This indicates that the project may not meet its deadline or performance metrics, signaling to the project team and stakeholders that corrective action may be necessary. The "In Trouble" status is reserved for more severe cases, and "Late" is generally used for tasks or projects that have passed their planned completion dates without being finished.
The At Risk status allows proactive intervention to address potential issues before they escalate into bigger problems.
質問 # 34
A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.
What task setting needs to change to allow 4 users to complete this in less than 3 days?
- A. Change the Task Duration Type to Effort Driven
- B. Change the Task Duration Type to Calculated Work
- C. Change the Task Constraint to Fixed Dates
- D. Change the Task Constraint to As Soon As Possible
正解:B
解説:
When reducing the task duration and distributing the work among multiple users, changing the Task Duration Type to "Calculated Work" allows Workfront to automatically adjust the duration based on the number of assignees (in this case, 4 users). This will enable the task to be completed within the new shorter timeframe without adjusting the total planned hours.
質問 # 35
What parent object can have child objects?
- A. Project
- B. Portfolio
- C. Issue
正解:B
解説:
In Workfront, a "Portfolio" is a parent object that can contain multiple programs and projects. Each Portfolio can have a hierarchy of child objects such as programs, which further break down into projects. A project, while it contains tasks and issues, is considered a child within the larger hierarchy of a portfolio. Issues, on the other hand, are typically linked to tasks or projects but are not used as parent objects. This hierarchy enables Workfront users to organize and manage their work across various levels.
質問 # 36
The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.
Which report grants the executive team this visibility?
- A. A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.
- B. A project report showing active projects grouped by portfolio showing project condition, project priority, and custom data aligning the project initiative to business goals.
- C. A portfolio report showing all projects grouped by team showing project condition, the alignment score, and custom data aligning the project initiative to business goals.
正解:A
解説:
For executive-level reporting, a program report grouped by department provides a holistic view of ongoing initiatives. This includes the health of programs, urgency, and alignment with business goals. This type of report is essential for leadership teams to assess overall performance and make informed decisions that align with the company's strategic objectives.
質問 # 37
......