質問 # 19
You are implementing SAP S/4HANA Cloud, public edition for your customer.How are your customer systems activated?
- A. Via the SAP Contact Center
- B. Via the SAP Business Technology Platform
- C. Via the Central Business Configuration System
- D. Via the SAP Cloud ALM
正解:C
解説:
* C is correct because the Central Business Configuration System (CBC) is a tool that enables customers to activate their SAP S/4HANA Cloud, public edition systems by following guided steps and entering configuration data. Verified References:
* : Central Business Configuration Overview
質問 # 20
What criteria does the product owner use to sequence the backlog?Note: There are 2 correct answers to this question.
- A. Technical dependencies
- B. Release planning schedule
- C. Complexity of the story
- D. Business priority
正解:A、D
解説:
* A is correct because technical dependencies are one of the criteria that the product owner uses to sequence the backlog. Technical dependencies are the relationships between user stories that affect their order of implementation. For example, some user stories may require other user stories to be completed first, or some user stories may have a common prerequisite or constraint.
* C is correct because business priority are one of the criteria that the product owner uses to sequence the backlog. Business priority is the measure of how important and valuable a user story is for the customer and the stakeholders. The product owner decides which user stories are more urgent and beneficial, and places them higher in the backlog. Verified References:
* : Product Backlog
質問 # 21
Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?
- A. Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity
- B. Detailed bottom-up effort estimate by the product owner that breaks up each story into short ^ tasks
- C. Project Manager's relative effort estimate that will be needed to implement and test the user ^ story
- D. Relative effort estimate in Ideal Person Days that reflects the best estimate by the project ^ team
正解:A
解説:
* A is correct because Planning poker is an estimation technique that you can use in an Agile delivery approach to size the user stories during sprint planning. Planning poker is a game where each team member uses a set of cards with numbers that represent the relative effort of a user story. The team members reveal their cards simultaneously and discuss their estimates until they reach a consensus. This technique is based on the concept of story points, which are units of measure for expressing the overall effort required to fully implement a user story. Story points are assigned to user stories based on their complexity, risk, and uncertainty. Verified References:
* : Planning Poker
質問 # 22
Which of the following are capabilities of the test automation tool for SAP S/4HANA Cloud, public edition?Note: There are 2 correct answers to this question.
- A. Captures test results with screenshots
- B. Supports recording of transaction-based processes
- C. Supports the creation of custom test automates
- D. Raises test defects automatically
正解:B、C
解説:
* B is correct because the test automation tool for SAP S/4HANA Cloud, public edition supports recording of transaction-based processes. This means that the tool can capture the user actions and inputs during a transaction and generate a test script that can be replayed later.
* D is correct because the test automation tool for SAP S/4HANA Cloud, public edition supports the creation of custom test automates. This means that the tool allows the user to modify the existing test scripts or create new ones from scratch, using a graphical user interface or a scripting language. Verified References:
* : Test Automation Tool for SAP S/4HANA Cloud, Public Edition - A Game Changer in the 3-System Landscape
* : SAP S/4HANA Cloud Test Automation Tool - Our Approach to Test Automation
質問 # 23
Which collaboration features are available in the SAP Community? Note: There are 2 correct answers to this question.
- A. Comment on Key Deliverables
- B. Update Key Deliverable wikis
- C. Ask questions
- D. Tweet questions
正解:A、C
解説:
* B is correct because asking questions is one of the collaboration features that are available in the SAP Community. The SAP Community allows users to post questions on various topics and get answers from other users, experts, or moderators.
* C is correct because commenting on key deliverables is one of the collaboration features that are available in the SAP Community. The SAP Community allows users to comment on the key deliverables that are published by SAP or other users, such as blog posts, articles, videos, podcasts, or webinars. Verified References:
* : SAP Community Home
質問 # 24
In which of the following do you use a work item in Focused Build?
- A. Epics
- B. Waves
- C. Sprints
- D. Releases
正解:C
解説:
* C is correct because in Focused Build, you use a work item in sprints. A work item is a document that describes a configuration requirement or gap for a scope item. A work item is assigned to a sprint, which is a time-boxed iteration where the work item is implemented and tested by the Scrum team. Verified References:
* : Managing Work Items
質問 # 25
How do you set up Scrum teams?Note: There are 2 correct answers to this question.
- A. As a cross-functional team covering multiple functions, like configuration, data loads, and v u testing
- B. Based on end-to-end processes like order-to-cash
- C. By type of work, like configuration Scrum, documentation Scrum, and testing Scrum
- D. Based on group size, but a minimum of 12 people
正解:A、B
解説:
* A is correct because based on end-to-end processes like order-to-cash is one of the ways to set up Scrum teams. This way, the Scrum teams are organized around the business value streams that they support, and they have a clear understanding of the customer needs and expectations. This also helps to reduce dependencies and handovers between teams, and to optimize the flow of work.
* C is correct because as a cross-functional team covering multiple functions, like configuration, data loads, and testing is one of the ways to set up Scrum teams. This way, the Scrum teams have all the skills and competencies that they need to deliver a complete and working product increment in each Sprint. This also helps to increase collaboration and communication within the team, and to foster a sense of ownership and accountability.
質問 # 26
What transition scenarios are possible when adopting RISE with SAP? Note; There are 3 correct answers to this question.
- A. New Implementation
- B. Shell Conversion
- C. Mix and Match
- D. System Conversion
- E. Lift and Shift
正解:A、D、E
解説:
* B is correct because Lift and Shift is one of the transition scenarios that are possible when adopting RISE with SAP. Lift and Shift is a scenario where the customer moves their existing SAP system to the cloud without changing the code or configuration. It is suitable for customers who want to reduce their infrastructure costs and complexity, and prepare for future innovation.
* C is correct because New Implementation is one of the transition scenarios that are possible when adopting RISE with SAP. New Implementation is a scenario where the customer sets up a new SAP S/4HANA system in the cloud with predefined configuration and data migration from their legacy system. It is suitable for customers who want to adopt the latest SAP innovations and best practices, and simplify their business processes.
* E is correct because System Conversion is one of the transition scenarios that are possible when adopting RISE with SAP. System Conversion is a scenario where the customer converts their existing SAP ERP system to SAP S/4HANA in the cloud, while preserving their data and customizations. It is suitable for customers who want to leverage the benefits of SAP S/4HANA, such as improved performance, user experience, and analytics, and retain their existing business processes. Verified References:
* : RISE with SAP - Business Transformation as a Service
* : RISE with SAP - Transition Scenarios
質問 # 27
In which workshop do you validate SAP standard functionality and collect delta requirements?
- A. Design thinking
- B. Fit-to-standard
- C. Fit-to-gap
- D. Solution validation
正解:B
解説:
* D is correct because Fit-to-standard is the workshop where you validate SAP standard functionality and collect delta requirements. Fit-to-standard is a process where the customer validates the fit of their
* business processes to the standard SAP solution and identifies any gaps or extensions that need to be addressed. Fit-to-standard is performed using a series of workshops where the customer reviews the best practice processes and scenarios provided by SAP and compares them with their own requirements.
Verified References:
* : [SAP Activate Methodology for SAP S/4HANA Cloud], page 18
* : [SAP Activate - Explore Phase: Use Fit-to-Standard to Confirm Business Process Fit and Identify Gaps in Your SAP S/4HANA Cloud Implementation]
質問 # 28
According to the Definition of Done, which activity must be completed for each Sprint?
- A. Functionality must be released to the business
- B. Functionality must be tested in the production system (PROD)
- C. The solution must be built and configured in the development system (DEV)
- D. End-user training must be delivered
正解:C
解説:
* B is correct because according to the Definition of Done, the solution must be built and configured in the development system (DEV) for each Sprint. This means that all user stories in the Sprint backlog must be completed, tested, and accepted by the product owner in the DEV system before moving to the next Sprint. Verified References:
* : SAP Activate Project Management Certification Guide, page 114
質問 # 29
Which of the following tools facilitate secure communication between SAP cloud solutions and protected on-premise networks that CANNOT be accessed directly from the Internet?
- A. SAP Connectivity service
- B. SAP Business Technology Platform
- C. Identity Authentication service
- D. Cloud Integration Automation service
正解:A
解説:
* A is correct because SAP Connectivity service is one of the tools that facilitate secure communication between SAP cloud solutions and protected on-premise networks that cannot be accessed directly from the Internet. The SAP Connectivity service allows SAP cloud applications to access remote services that run on the Internet or on-premise via a secure tunnel established by the Cloud Connector. The Cloud Connector acts as a reverse proxy that connects to the SAP Connectivity service and exposes the on-premise systems to the cloud applications. Verified References:
* : Connectivity Service
* : SAP Cloud Platform Service: Connectivity
質問 # 30
Which of the following are cornerstones of SAP's security strategy? Note: There are 3 correct answers to this question
- A. Secure Company
- B. Secure Infrastructure
- C. Secure Products
- D. Secure Operations
- E. Secure Projects
正解:A、C、D
解説:
* A is correct because Secure Company is one of the cornerstones of SAP's security strategy. It means that SAP ensures that its own organization, employees, and processes comply with the highest security standards and regulations.
* C is correct because Secure Operations is one of the cornerstones of SAP's security strategy. It means that SAP ensures that its cloud services are operated securely and reliably, with measures such as data protection, encryption, backup, monitoring, and incident response.
* E is correct because Secure Products is one of the cornerstones of SAP's security strategy. It means that SAP ensures that its software products are developed securely and follow best practices such as secure coding, testing, and patching.
質問 # 31
What can you find in the SAP Fiori apps reference library? Note: There are 3 correct answers to this question.
- A. Shortcut to the Maintenance Planner tool to establish the technical update path
- B. Shortcut to the Quicksizer tool to estimate hardware requirements
- C. Related app recommendations based on your usage profile
- D. Installation and configuration requirements for selected apps
- E. Related app-specific SAP Fiori design guidelines
正解:C、D、E
解説:
* B is correct because installation and configuration requirements for selected apps are one of the things that you can find in the SAP Fiori apps reference library. The SAP Fiori apps reference library provides information on how to install and configure each app, such as required software components, backend configuration steps, and frontend configuration steps.
* C is correct because related app-specific SAP Fiori design guidelines are one of the things that you can find in the SAP Fiori apps reference library. The SAP Fiori apps reference library provides links to the app-specific design guidelines that describe the user interface and interaction patterns of each app, such as layout, navigation, controls, and dialogs.
* E is correct because related app recommendations based on your usage profile are one of the things that you can find in the SAP Fiori apps reference library. The SAP Fiori apps reference library provides suggestions on other apps that might be relevant or useful for you based on your role, industry, or business area.
質問 # 32
What activity do you perform during the daily stand-up meeting?
- A. Report showstoppers.
- B. Negotiate acceptance criteria
- C. Provide end users with a demo of the new features
- D. Re-baseline the release plan
正解:A
解説:
* C is correct because reporting showstoppers is one of the activities that you perform during the daily stand-up meeting. A showstopper is an issue or impediment that prevents the team from completing their sprint goal or user story. The scrum master is responsible for resolving or escalating the showstoppers as soon as possible. Verified References:
* : SAP Activate Project Management Certification Guide, page 115
質問 # 33
In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps?
- A. Deploy
- B. Prepare
- C. Realize
- D. Explore
正解:D
解説:
* C is correct because in the Explore phase, you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps. This is done through a fit-to-standard workshop, where you compare the customer's business requirements with the standard SAP functionality, and document any gaps or deviations as user stories. Verified References:
* : SAP Activate Project Management Certification Guide, page 122
質問 # 34
......