質問 # 28
What is the objective of a sprint retrospective meeting?

  • A. Improve the Scrum process.
  • B. Review and prioritize the backlog.
  • C. Provide formal feedback to the Project Manager.
  • D. Define the stakeholder management approach

正解:A

解説:
* A is correct because improving the Scrum process is the objective of a sprint retrospective meeting. The sprint retrospective meeting is a time for the Scrum Team to reflect on how they worked together in the last sprint and identify ways to enhance their effectiveness and efficiency. Verified References:
* : What is a Sprint Retrospective? | Scrum.org


質問 # 29
What is preferred when a customer wants to keep most of their original processes and migrate to SAP S/4HANA Cloud, private edition?

  • A. System Conversion
  • B. Shell Conversion
  • C. Selective Data Transition
  • D. Mix and Match

正解:B

解説:
* Shell Conversion is preferred when a customer wants to keep most of their original processes and migrate to SAP S/4HANA Cloud, private edition. It involves creating a shell system that contains the configuration and master data of the source system, and then migrating the transactional data to the target system. Verified References:
* : SAP Activate Project Management Certification Guide, page 128


質問 # 30
You are transitioning to SAP S/4HANA.In which phase do you adjust custom code?

  • A. Discover
  • B. Realize
  • C. Explore
  • D. Deploy

正解:B

解説:
* A is correct because in the Realize phase, you adjust custom code when transitioning to SAP S/4HANA.
Custom code is the code that was developed by the customer or a partner to extend or modify the standard SAP functionality. Custom code needs to be adjusted to ensure compatibility and performance with SAP S/4HANA, as well as compliance with the simplification items and coding guidelines.
Verified References:
* : [SAP Activate Methodology for SAP S/4HANA On Premise], page 22


質問 # 31
When conducting an upgrade of an SAP S/4HANA Cloud, public edition three system landscape, in which phase are the Business Roles updated?

  • A. Discover
  • B. Deploy
  • C. Explore
  • D. Realize

正解:C

解説:
* A is correct because in the Explore phase, the Business Roles are updated when conducting an upgrade of an SAP S/4HANA Cloud, public edition three system landscape. The Business Roles are the roles that define the access rights and authorizations for the users in the system. The Business Roles are updated to reflect the changes and enhancements that are introduced by the upgrade, such as new apps, features, or functions. Verified References:
* : SAP S/4HANA Cloud Upgrade Guide, page 11


質問 # 32
Which of the following is a key characteristic of the Agile project approach?

  • A. Formal and detailed documentation
  • B. Frequent quality gates
  • C. Iterative build with frequent inspections
  • D. Frequent and detailed project scheduling

正解:C

解説:
D is correct because Iterative build with frequent inspections is a key characteristic of the Agile project approach. The Agile project approach follows an iterative and incremental development process, where the solution is built and delivered in small increments called sprints. Each sprint consists of planning, designing, building, testing, and reviewing activities, where the team inspects the solution and adapts to changing requirements and feedback


質問 # 33
Your customer is using a non-SAP ERP system and decides to implement SAP S/4HANA. Which of the following options are available to your customer?Note: There are 3 correct answers to this question.

  • A. System Conversion SAP S/4HANA Cloud, private edition
  • B. System Conversion SAP S/4HANA
  • C. New Implementation SAP S/4HANA Cloud, public edition
  • D. New Implementation SAP S/4HANA
  • E. New Implementation SAP S/4HANA Cloud, private edition

正解:C、D、E

解説:
* B is correct because New Implementation SAP S/4HANA Cloud, public edition is one of the options that are available to a customer who is using a non-SAP ERP system and decides to implement SAP S/4HANA. It involves setting up a new SAP S/4HANA Cloud system with predefined configuration and data migration from the legacy system.
* D is correct because New Implementation SAP S/4HANA Cloud, private edition is one of the options that are available to a customer who is using a non-SAP ERP system and decides to implement SAP S/4HANA. It involves setting up a new SAP S/4HANA Cloud system with customized configuration and data migration from the legacy system.
* E is correct because New Implementation SAP S/4HANA is one of the options that are available to a customer who is using a non-SAP ERP system and decides to implement SAP S/4HANA. It involves setting up a new SAP S/4HANA on-premise system with tailored configuration and data migration from the legacy system. Verified References:
* : SAP Activate Project Management Certification Guide, page 126


質問 # 34
What criterion does the product owner use to sequence the product backlog?

  • A. Relative effort
  • B. Business priority
  • C. Complexity
  • D. Resource availability

正解:B

解説:
* A is correct because the product owner is responsible for prioritizing the product backlog based on the business value and urgency of each user story3. Verified References:
* 3: SAP Activate Project Management Certification Guide, page 112


質問 # 35
What technique helps a Scrum team to prioritize a large, flat backlog?

  • A. Planning poker
  • B. Fit-gap analysis
  • C. Retrospective
  • D. User story mapping

正解:D

解説:
* C is correct because user story mapping is a technique that helps a Scrum team to prioritize a large, flat backlog. User story mapping is a process of creating a visual representation of the user stories, grouped by themes, epics, and features, and ordered by value and dependency. It helps the team to understand the big picture and focus on the most important user stories for each sprint. Verified References:
* : User Story Mapping


質問 # 36
Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud, public edition" transition path?

  • A. Solution Validation and Delta Design
  • B. Simplification and Custom Code Impact Analysis
  • C. Fit-to-standard
  • D. Setup and Enablement

正解:C

解説:
* B is correct because Fit-to-standard is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud, public edition" transition path. Fit-to-standard is a process where the customer validates the fit of their business processes to the standard SAP S/4HANA Cloud solution and identifies any gaps or extensions that need to be addressed. Fit-to-standard is performed using a series of workshops where the customer reviews the best practice processes and scenarios provided by SAP and compares them with their own requirements. Verified References:
* : SAP Activate Methodology for SAP S/4HANA Cloud, page 18
* : SAP Activate - Explore Phase: Use Fit-to-Standard to Confirm Business Process Fit and Identify Gaps in Your SAP S/4HANA Cloud Implementation


質問 # 37
What is Scrum of Scrums?

  • A. Integration meeting among the various Scrum teams
  • B. Mechanism for gathering and validating requirements
  • C. Alternative to regular Scrum process for smaller teams
  • D. Frequent inspection of code and configuration prior to quality gates

正解:A

解説:
* B is correct because Scrum of Scrums is an integration meeting among the various Scrum teams that are working on a large-scale project. It helps to coordinate and synchronize the work across teams, resolve dependencies and issues, and share best practices and learnings. Verified References:
* : SAP Activate Project Management Certification Guide, page 115


質問 # 38
Which accelerators support the fit-to-standard workshop in the Explore phase? Note: There are 2 correct answers to this question.

  • A. Requirements feature in SAP Cloud ALM
  • B. Quality gate checklist and quality gate guide
  • C. Test strategy document
  • D. Business-Driven Configuration questionnaire

正解:A、D

解説:
* B is correct because the requirements feature in SAP Cloud ALM is an accelerator that supports the fit-to-standard workshop in the Explore phase. It allows the project team to capture and manage the user stories that are identified during the workshop, as well as link them to the relevant scope items and test cases.
* D is correct because the Business-Driven Configuration questionnaire is an accelerator that supports the fit-to-standard workshop in the Explore phase. It provides a set of questions that help the project team to understand and document the customer's business requirements and configuration settings for each scope item. Verified References:
* : SAP Cloud ALM
* : Business Driven Configuration Questionnaire


質問 # 39
Which of the following are Selective Data Transition scenarios? Note: There are 3 correct answers to this question

  • A. Migration of business units
  • B. Migration of open items
  • C. Migration of selected applications
  • D. Migration of transactional data
  • E. Consolidation

正解:A、D、E

解説:
* A is correct because migration of business units is one of the Selective Data Transition scenarios. It allows the customer to move specific business units or company codes from their source system to SAP S/4HANA, while keeping the rest of the system unchanged.
* B is correct because consolidation is one of the Selective Data Transition scenarios. It allows the customer to merge multiple source systems into one SAP S/4HANA system, while harmonizing and simplifying the data and processes.
* E is correct because migration of transactional data is one of the Selective Data Transition scenarios. It allows the customer to move selected transactional data (such as open items, balances, and documents) from their source system to SAP S/4HANA, while preserving the historical data in the source system.
SAP Activate Project Management Certification Guide, page 128


質問 # 40
According to the Definition of Done, which activity must be completed for each Sprint?

  • A. The solution must be built and configured in the development system (DEV)
  • B. End-user training must be delivered
  • C. Functionality must be released to the business
  • D. Functionality must be tested in the production system (PROD)

正解:A

解説:
* B is correct because according to the Definition of Done, the solution must be built and configured in the development system (DEV) for each Sprint. This means that all user stories in the Sprint backlog must be completed, tested, and accepted by the product owner in the DEV system before moving to the next Sprint. Verified References:
* : SAP Activate Project Management Certification Guide, page 114


質問 # 41
Which tool do you use to configure SAP S/4HANA Cloud, public edition?

  • A. IMG (Implementation Guide)
  • B. SAP Central Business Configuration
  • C. SAP Cloud ALM
  • D. SAP Solution Manager

正解:B

解説:
* C is correct because SAP Central Business Configuration is the tool that you use to configure SAP S/4HANA Cloud, public edition. It provides a guided configuration process that helps you to activate your system, enter configuration data, and validate your settings. Verified References:
* : Central Business Configuration Overview


質問 # 42
What accelerator can help you document the configuration definition in the Explore phase?

  • A. Backlog template
  • B. Test strategy
  • C. Change request template
  • D. Data definition

正解:A

解説:
* D is correct because the backlog template is an accelerator that can help you document the configuration definition in the Explore phase. The backlog template is a document that contains the user stories that describe the configuration requirements and gaps for each scope item. It also includes the acceptance criteria, priority, effort estimation, and dependencies for each user story. Verified References:
* : SAP Activate Project Management Certification Guide, page 123


質問 # 43
What is the primary purpose of the SAP Activate methodology?

  • A. To manage solution documentation
  • B. To expedite all deployment options for SAP products
  • C. To enable access to the SAP ecosystem
  • D. To provide end-to-end application lifecycle management

正解:B

解説:
C is correct because expediting all deployment options for SAP products is the primary purpose of the SAP Activate methodology. The SAP Activate methodology is a framework that provides guidance and best practices for implementing SAP solutions in different scenarios, such as cloud, on-premise, or hybrid. The SAP Activate methodology aims to accelerate and simplify the deployment process by combining ready-to-run business processes, proven implementation practices, and guided configuration tools.


質問 # 44
Which of the following is the customer's responsibility in both on-premise and private cloud scenarios?

  • A. Middleware
  • B. Servers
  • C. Database
  • D. Operating system

正解:B

解説:
* D is correct because servers are the customer's responsibility in both on-premise and private cloud scenarios. Servers are the hardware devices that host the SAP system and its components. The customer has to provide, maintain, and secure their own servers in both scenarios, as they have full control over their infrastructure. Verified References:
* : [SAP S/4HANA Cloud Editions]


質問 # 45
Which systems are part of the private cloud edition landscape?Note. There are 2 correct answers to this question.

  • A. Sandbox
  • B. Production
  • C. Evaluation
  • D. Starter

正解:A、B

解説:
* A is correct because Production is one of the systems that are part of the private cloud edition landscape.
The Production system is the system where the solution is deployed and operated for the end users. It contains the live data and processes of the customer's business.
* B is correct because Sandbox is one of the systems that are part of the private cloud edition landscape.
The Sandbox system is an optional system that can be used for testing, prototyping, or training purposes.
It is a copy of the Production system that can be refreshed on demand.


質問 # 46
Which of the following tools can support you in managing requirements and software development for implementation projects? Note: There are 2 correct answers to this question

  • A. Focused Insights for SAP Solution Manager
  • B. SAP Cloud ALM
  • C. Focused Build for SAP Solution Manager
  • D. SAP Focused Run

正解:B、C

解説:
* B is correct because Focused Build for SAP Solution Manager is a tool that supports the management of requirements and software development for implementation projects. It provides features such as requirements-to-deploy process, collaboration platform, quality gate management, and test management.
* D is correct because SAP Cloud ALM is a tool that supports the management of requirements and software development for implementation projects. It provides features such as project task management, solution documentation, change request management, and test management. Verified References:
* : Focused Build for SAP Solution Manager
* : SAP Cloud ALM


質問 # 47
Which collaboration features are available in the SAP Community? Note: There are 2 correct answers to this question.

  • A. Ask questions
  • B. Comment on Key Deliverables
  • C. Update Key Deliverable wikis
  • D. Tweet questions

正解:A、B

解説:
* B is correct because asking questions is one of the collaboration features that are available in the SAP Community. The SAP Community allows users to post questions on various topics and get answers from other users, experts, or moderators.
* C is correct because commenting on key deliverables is one of the collaboration features that are available in the SAP Community. The SAP Community allows users to comment on the key deliverables that are published by SAP or other users, such as blog posts, articles, videos, podcasts, or webinars. Verified References:
* : SAP Community Home


質問 # 48
Which task should you include in your procedure while preparing for a fit-to-standard analysis in an SAP Data Warehouse Cloud project?Note: There are 2 correct answers to this question.

  • A. Review all the necessary Implementation Design Principles (IDPs).
  • B. Review all the necessary leading practice process diagrams.
  • C. Review SAP S/4HANA best practices availability for your country.
  • D. Review available SAP S/4HANA accelerators for the Data Management workstream

正解:A、B

解説:
* B is correct because Implementation Design Principles (IDPs) are documents that provide guidance on how to configure and extend SAP Data Warehouse Cloud to meet customer-specific requirements1.
* D is correct because leading practice process diagrams are graphical representations of the business processes that are supported by SAP Data Warehouse Cloud and can be used as a reference for the fit-to-standard analysis2. Verified References:
* 1: SAP Data Warehouse Cloud Implementation Design Principles
* 2: SAP Data Warehouse Cloud Best Practices


質問 # 49
Which of the following are workshop design principles/guidelines?Note: There are 2 correct answers to this question.

  • A. Best Practices enablement
  • B. Fit-to-standard
  • C. Expert configuration definitions
  • D. Active participation

正解:B、D

解説:
* A is correct because active participation is a key principle for designing effective workshops, as it ensures that all stakeholders are engaged and contribute to the workshop outcomes.
* B is correct because fit-to-standard is a workshop design guideline that aims to minimize customizations
* and leverage the standard SAP functionality as much as possible. Verified References:
* : SAP Activate Project Management Certification Guide, page 123
* : SAP Activate Methodology for SAP S/4HANA Cloud, page 40


質問 # 50
Which additional scope option does the strategic advisory service for cloud analytics offer?Note: There are 2 correct answers to this question

  • A. SAP Activate methodology for the Intelligent Enterprise
  • B. SAP S/4HANA for central finance
  • C. Extended package
  • D. Baseline package

正解:C、D

解説:
* A is correct because the extended package is an additional scope option that the strategic advisory service for cloud analytics offers. It provides a deeper analysis of the customer's current analytics landscape and a more detailed roadmap for the cloud analytics transformation.
* C is correct because the baseline package is an additional scope option that the strategic advisory service for cloud analytics offers. It provides a high-level assessment of the customer's current analytics landscape and a general roadmap for the cloud analytics transformation. Verified References:
* : Strategic Advisory Service for Cloud Analytics


質問 # 51
When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?

  • A. During the user acceptance test
  • B. During the daily Scrum meeting
  • C. During the sprint review
  • D. During the sprint retrospective

正解:C

解説:
* D is correct because the sprint review is the event where the Scrum team receives formal confirmation that the user stories are completed to the satisfaction of the product owner. The sprint review is a meeting where the Scrum team demonstrates the functionality that they have built and configured in the sprint, and the product owner provides feedback and acceptance. Verified References:
* : [What is a Sprint Review? | Scrum.org]


質問 # 52
......