質問 # 11
Consider the following examples of risks identified in different software development projects:
[I]. The contrast color ratio for both normal text and large text of a website does not comply with the applicable accessibility guidelines, making itdifficult for many users to read the content on the pages
[II]. A development vendor fails to deliver their software system on time, causing significant delays to system integration testing activities that havebeen planned as part of a development project for a system of systems
[III]. People in the test team do not have sufficient skills to automate tests at the test levels required by the test automation strategy which does notallow production of an effective regression test suite
[IV]. In a web application, data from untrusted sources is not subject to proper input validation, making the applicationvulnerable to several securityattacks Which of the following statements is true?

  • A. [IV] is a product risk; [I]. [II] and [III] are project risks
  • B. [II], [III] and [IV] are product risks; [I] is a project risk
  • C. [I] and [III] are product risks; [II] and [IV] are project risks
  • D. [I] and [IV] are product risks. [II] and [III] are project risks

正解:D

解説:
Explanation
This answer is correct because product risks are risks that affect the quality of the software product, such as defects, failures, or non-compliance with requirements or standards. Project risks are risks that affect the project's schedule, budget, resources, or scope, such as delays, cost overruns, skill gaps, or scope changes. In this case, [I] and [IV] are product risks, as they relate to the accessibility and security of the software product, which are quality attributes. [II] and [III] are project risks, as they relate to the delivery time and the test automation skills of the test team, which are project factors. References: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 2.1.1.1


質問 # 12
The acceptance criteria associated with a user story:

  • A. can be written in different formats and represent an aspect of a user story referred to as confirmation' of the so called "3 C's"
  • B. must be written in one of the two following formats: scenario-oriented or rule-oriented
  • C. are often written in a rule-oriented format using the template referred to as "Given/When/Then"
  • D. are often documented following in rule-oriented format using the following template: "As a [role], I want [feature], so that I can [benefit]"

正解:A

解説:
Explanation
The acceptance criteria associated with a user story are the conditions that must be met for the user story to be considered done and to deliver the expected value to the user. They are often written in different formats, such as rule-oriented, scenario-oriented, or table-oriented, depending on the nature and complexity of the user story.They represent an aspect of a user story referred to as confirmation, which is one of the so called "3 C's" of user stories. The other two aspects are card and conversation. Card refers to the concise and informal description of the user story, usually following the template: "As a [role], I want [feature], so that I can
[benefit]". Conversation refers to the ongoing dialogue between the stakeholders and the team members to clarify and refine the user story and its acceptance criteria. Therefore, option C is the correct answer.
References: ISTQB Certified Tester Foundation Level Syllabus v4.01, Section 3.2.2, page 35-36; ISTQB Glossary v4.02, page 37.


質問 # 13
An alphanumeric password must be between 4 and 7 characters long and must contain at least one numeric character, one capital (uppercase) letter and one lowercase letter of the alphabet.
Which one of the following sets of test cases represents the correct outcome of a two-value boundary value analysis applied to the password length? (Note: test cases are separated by a semicolon)

  • A. 1RhT;rSp53;3N3e10;8sBdby
  • B. 1xA;aB11;Pq1ZZab;7iDD0a1x
  • C. aB11;99rSp:5NnN10;7iDD0a1x
  • D. 1xB: aB11: 99rSp: 5NnN10; 4NnN10T; 44ghWn19

正解:A

解説:
Explanation
The correct outcome of a two-value boundary value analysis applied to the password length is the set of test cases represented by option D. Boundary value analysis is a test design technique that focuses on the values at the boundaries of an equivalence partition, such as the minimum and maximum values, or the values just above and below the boundaries. A two-value boundary value analysis uses two values for each boundary, one representing the valid value and one representing the invalid value. For example, if the valid range of values is from 4 to 7, then the two values for the lower boundary are 3 and 4, and the two values for the upper boundary are 7 and 8. The test cases in option D use these values for the password length, while also satisfying the other requirements of the password, such as containing at least one numeric character, one capital letter, and one lowercase letter. The test cases in option D are:
1RhT: a 4-character password that is valid
rSp53: a 5-character password that is valid
3N3e10: a 6-character password that is valid
8sBdby: an 8-character password that is invalid The test cases in the other options are incorrect, because they either use values that are not at the boundaries of the password length, or they do not meet the other requirements of the password. For example, the test cases in option A are:
1xA: a 3-character password that is invalid, but it does not contain a capital letter aB11: a 4-character password that is valid Pq1ZZab: a 7-character password that is valid
7iDD0a1x: an 8-character password that is invalid References: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.2.1, Black-box Test Design Techniques1 ISTQB Glossary of Testing Terms v4.0, Boundary Value Analysis, Equivalence Partition2


質問 # 14
Which of the following statements about exploratory testing is true?

  • A. When exploratory testing is conducted following a session-based approach, the issues detected by the testers can be documented in session sheets
  • B. Exploratory testing is an experience-based test technique in which testers explore the requirements specification to detect non testable requirements
  • C. In exploratory testing, testers usually produce scripted tests and establish bidirectional traceability between these tests and the items of the test basis
  • D. Exploratory testing is an experience-based test technique used by testers during informal code reviews to find defects by exploring the source code

正解:A

解説:
Exploratory testing is an experience-based test technique in which testers dynamically design and execute tests based on their knowledge, intuition, and learning of the software system, without following predefined test scripts or test cases. Exploratory testing can be conducted following a session-based approach, which is a structured way of managing and measuring exploratory testing. In a session-based approach, the testers perform uninterrupted test sessions, usually lasting between 60 and 120 minutes, with a specific charter or goal, and document the issues detected, the test coverage achieved, and the time spent in session sheets. Session sheets are records of the test activities, results, and observations during a test session, which can be used for reporting, debriefing, and learning purposes. The other statements are false, because:
Exploratory testing is not a test technique in which testers explore the requirements specification to detect non testable requirements, but rather a test technique in which testers explore the software system to detect functional and non-functional defects, as well as to learn new information, risks, or opportunities. Non testable requirements are requirements that are ambiguous, incomplete, inconsistent, or not verifiable, which can affect the quality and effectiveness of the testing process. Non testable requirements can be detected by applying static testing techniques, such as reviews or inspections, to the requirements specification, before the software system is developed or tested.
Exploratory testing is not a test technique used by testers during informal code reviews to find defects by exploring the source code, but rather a test technique used by testers during dynamic testing to find defects by exploring the behavior and performance of the software system, without examining the source code. Informal code reviews are static testing techniques, in which the source code is analyzed by one or more reviewers, without following a formal process or using a checklist, to identify defects, violations, or improvements. Informal code reviews are usually performed by developers or peers, not by testers.
In exploratory testing, testers usually do not produce scripted tests and establish bidirectional traceability between these tests and the items of the test basis, but rather produce unscripted tests and adapt them based on the feedback and the findings of the testing process. Scripted tests are tests that are designed and documented in advance, with predefined inputs, outputs, and expected results, and are executed according to a test plan or a test procedure. Bidirectional traceability is the ability to trace both forward and backward the relationships between the items of the test basis, such as the requirements, the design, the risks, etc., and the test artifacts, such as the test cases, the test results, the defects, etc. Scripted tests and bidirectional traceability are usually associated with more formal and structured testing approaches, such as specification-based or structure-based test techniques, not with exploratory testing. Reference: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.2.3, Experience-based Test Design Techniques1 ISTQB® Glossary of Testing Terms v4.0, Exploratory Testing, Session-based Testing, Session Sheet, Non Testable Requirement, Static Testing, Informal Review, Dynamic Testing, Scripted Testing, Bidirectional Traceability2


質問 # 15
The whole-team approach:

  • A. promotes the idea that all team members should have a thorough understanding of test techniques
  • B. promotes the idea that all team members should be responsible for the quality of the product
  • C. is a consensus-based approach that engages the whole team in estimating the user stories
  • D. is mostly adopted in projects aimed at developing safety-critical systems, as it ensures the highest level of testing independence

正解:B

解説:
This answer is correct because the whole-team approach is a way of working in agile projects where all team members share the responsibility for the quality of the product, and collaborate on delivering value to the customer. The whole-team approach involves testers, developers, business analysts, product owners, and other stakeholders in planning, designing, developing, testing, and delivering the product. The whole-team approach fosters communication, feedback, learning, and continuous improvement within the team. Reference: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 3.1.1.1


質問 # 16
Which of the following coverage criteria results in the highest coverage for state transition based test cases?

  • A. Can't be determined
  • B. Covering only start and end states
  • C. Covering all transitions at least once
  • D. Covering all states at least once

正解:C

解説:
Covering all transitions at least once is the highest coverage criterion for state transition based test cases, because it ensures that every possible change of state is tested at least once. This means that all the events that trigger the transitions, as well as the actions and outputs that result from the transitions, are verified. Covering all transitions at least once also implies covering all states at least once, but not vice versa. Therefore, option D is not the highest coverage criterion. Option C is the lowest coverage criterion, because it only tests the initial and final states of the system or component, without checking the intermediate states or transitions. Option A is incorrect, because the coverage criteria for state transition based test cases can be determined and compared based on the number of transitions and states covered. Reference = CTFL 4.0 Syllabus, Section 4.2.3, page 49-50.


質問 # 17
Which of the following are the phases of the ISTQB fundamental test process?

  • A. Test planning, Test analysis and design. Test implementation and control. Checking test coverage and reporting, Test closure activities
  • B. Test planning and control, Test specification and design. Test implementation and execution, Evaluating test coverage and reporting, Retesting and regression testing, Test closure activities
  • C. Test planning. Test specification and design. Test implementation and execution. Evaluating exit criteria and reporting. Retesting and test closure activities
  • D. Test planning and control, Test analysis and design, Test implementation and execution, Evaluating ex t criteria and reporting. Test closure activities

正解:D

解説:
The ISTQB fundamental test process consists of five main phases, as described in the ISTQB Foundation Level Syllabus, Version 4.0, 2018, Section 2.2, page 15:
Test planning and control: This phase involves defining the test objectives, scope, strategy, resources, schedule, risks, and metrics, as well as monitoring and controlling the test activities and results throughout the test process.
Test analysis and design: This phase involves analyzing the test basis (such as requirements, specifications, or user stories) to identify test conditions (such as features, functions, or scenarios) that need to be tested, and designing test cases and test procedures (such as inputs, expected outcomes, and execution steps) to cover the test conditions. This phase also involves evaluating the testability of the test basis and the test items (such as software or system components), and selecting and implementing test techniques (such as equivalence partitioning, boundary value analysis, or state transition testing) to achieve the test objectives and optimize the test coverage and efficiency.
Test implementation and execution: This phase involves preparing the test environment (such as hardware, software, data, or tools) and testware (such as test cases, test procedures, test data, or test scripts) for test execution, and executing the test procedures or scripts according to the test plan and schedule. This phase also involves logging the outcome of test execution, comparing the actual results with the expected results, and reporting any discrepancies as incidents (such as defects, errors, or failures).
Evaluating exit criteria and reporting: This phase involves checking if the planned test activities have been completed and the exit criteria (such as quality, coverage, or risk levels) have been met, and reporting the test results and outcomes to the stakeholders. This phase also involves making recommendations for the release or acceptance decision based on the test results and outcomes, and identifying any residual risks (such as known defects or untested areas) that need to be addressed or mitigated.
Test closure activities: This phase involves finalizing and archiving the testware and test environment for future reuse, and evaluating the test process and the test project against the test objectives and the test plan. This phase also involves identifying any lessons learned and best practices, and communicating the findings and suggestions for improvement to the relevant parties.
Reference = ISTQB Certified Tester Foundation Level Syllabus, Version 4.0, 2018, Section 2.2, page 15; ISTQB Glossary of Testing Terms, Version 4.0, 2018, pages 37-38; ISTQB CTFL 4.0 - Sample Exam - Answers, Version 1.1, 2023, Question 88, page 32.


質問 # 18
In which of the following test documents would you expect to find test exit criteria described9

  • A. Test plan
  • B. Project plan
  • C. Test design specification
  • D. Requirements specification

正解:A

解説:
Test exit criteria are the conditions that must be fulfilled before concluding a particular testing phase. These criteria act as a checkpoint to assess whether we have achieved the testing objectives and are done with testing1. Test exit criteria are typically defined in the test plan document, which is one of the outputs of the test planning phase. The test plan document describes the scope, approach, resources, and schedule of the testing activities. It also identifies the test items, the features to be tested, the testing tasks, the risks, and the test deliverables2. According to the ISTQB® Certified Tester Foundation Level Syllabus v4.0, the test plan document should include the following information related to the test exit criteria3:
The criteria for evaluating test completion, such as the percentage of test cases executed, the percentage of test coverage achieved, the number and severity of defects found and fixed, the quality and reliability of the software product, and the stakeholder satisfaction.
The criteria for evaluating test process improvement, such as the adherence to the test strategy, the efficiency and effectiveness of the testing activities, the lessons learned and best practices identified, and the recommendations for future improvements.
Therefore, the test plan document is the most appropriate test document to find the test exit criteria described. The other options, such as test design specification, project plan, and requirements specification, are not directly related to the test exit criteria. The test design specification describes the test cases and test procedures for a specific test level or test type3. The project plan describes the overall objectives, scope, assumptions, risks, and deliverables of the software project4. The requirements specification describes the functional and non-functional requirements of the software product5. None of these documents specify the conditions for ending the testing process or evaluating the testing outcomes. Reference = ISTQB® Certified Tester Foundation Level Syllabus v4.0, Entry and Exit Criteria in Software Testing | Baeldung on Computer Science, Entry And Exit Criteria In Software Testing - Rishabh Software, Entry and Exit Criteria in Software Testing Life Cycle - STLC [2022 Updated] - Testsigma Blog, ISTQB® releases Certified Tester Foundation Level v4.0 (CTFL).


質問 # 19
Consider the following user story about the authentication functionality of an e-commerce website:
"As a logged-in user, I want to change my current password with a new one, so that I can make my account safer".
The following are some of the acceptance criteria defined for the user story:
[a] After the logged-in user has successfully changed his password, an email confirming the change must be sent to him
[b] To successfully change the password, the logged-in user must enter the current password, enter a new valid password, and finally confirm by pressing the 'Change Password' button
[c] To be valid, the new password entered by the logged-in user is not only required to meet the criteria related to the length and type of characters, but must also be different form the last 5 passwords of that user
[d] A dedicated error message must be presented to the logged-in user when he enters a wrong current password
[e] A dedicated error message must be presented to the logged-in user when he enters the correct current password, but enters an invalid password Based only on the given information, which of the following ATDD tests is most likely to be written first?

  • A. The logged-in user enters the correct current password, enters an invalid password, and finally views the dedicated error
  • B. The logged-in user enters the correct current password, enters a valid new password (different from the last 5 passwords), presses the Change Password' button, and finally receives the e-mail confirming that the password has been successfully changed
  • C. The logged-in user submits a purchase order containing ten items, selects to pay with a Visa credit card, enters credit card information of a valid card, presses the 'Confirm' button, and finally views the dedicated message confirming that the purchase has been successful
  • D. The logged-in user enters a wrong current password and views the dedicated error message

正解:B

解説:
Explanation
ATDD stands for Acceptance Test-Driven Development, which is a collaborative approach to software development and testing, in which the acceptance criteria of a user story are defined and automated as executable tests before the implementation of the software system. ATDD tests are usually written in a Given-When-Then format, which describes the preconditions, the actions, and the expected outcomes of a test scenario. ATDD tests are intended to verify that the software system meets the expectations and the needs of the users and the stakeholders, as well as to provide feedback and guidance for the developers and the testers.
Based on the given information, the ATDD test that is most likely to be written first is the one that corresponds to option B, which is:
Given the logged-in user is on the Change Password page When the user enters the correct current password, enters a valid new password (different from the last 5passwords), and presses the Change Password button Then the user receives an email confirming that the password has been successfully changed This ATDD test is most likely to be written first, because it covers the main functionality and the happy path of the user story, as well as the most important acceptance criterion [a]. It also verifies that the user can change the password with a valid new password that meets the criteria related to the length, the type of characters, and the history of the passwords, as specified in the acceptance criterion [c]. The other options are not likely to be written first, because they either cover less critical or less frequent scenarios, such as entering a wrong current password [d] or an invalid new password [e], or they are not related to the user story or the acceptance criteria at all, such as submitting a purchase order [d]. References: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 1.3.1, Testing in Software Development Lifecycles1 ISTQB Glossary of Testing Terms v4.0, Acceptance Test-Driven Development, User Story, Acceptance Criterion, Given-When-Then2


質問 # 20
The four test levels used in ISTQB syllabus are:
1. Component (unit) testing
2. Integration testing
3. System testing
4. Acceptance testing
An organization wants to do away with integration testing but otherwise follow V-model. Which of the following statements is correct?

  • A. It is allowed as organizations can decide on men test levels to do depending on the context of the system under test
  • B. It is not allowed because integration testing is a very important test level and ignoring i: means definite poor product quality
  • C. It is not allowed as organizations can't change the test levels as these are chosen on the basis of the SDLC (software development life cycle) model
  • D. It is allowed because integration testing is not an important test level arc! can be dispensed with.

正解:C

解説:
The V-model is a software development life cycle model that defines four test levels that correspond to four development phases: component (unit) testing with component design, integration testing with architectural design, system testing with system requirements, and acceptance testing with user requirements. The V-model emphasizes the importance of verifying and validating each phase of development with a corresponding level of testing, and ensuring that the test objectives, test basis, and test artifacts are aligned and consistent across the test levels. Therefore, an organization that wants to follow the V-model cannot do away with integration testing, as it would break the symmetry and completeness of the V-model, and compromise the quality and reliability of the software or system under test. Integration testing is a test level that aims to test the interactions and interfaces between components or subsystems, and to detect any defects or inconsistencies that may arise from the integration of different parts of the software or system. Integration testing is essential for ensuring the functionality, performance, and compatibility of the software or system as a whole, and for identifying and resolving any integration issues early in the development process. Skipping integration testing would increase the risk of finding serious defects later in the test process, or worse, in the production environment, which would be more costly and difficult to fix, and could damage the reputation and credibility of the organization. Therefore, the correct answer is D.
The other options are incorrect because:
A) It is not allowed as organizations can decide on the test levels to do depending on the context of the system under test. While it is true that the choice and scope of test levels may vary depending on the context of the system under test, such as the size, complexity, criticality, and risk level of the system, the organization cannot simply ignore or skip a test level that is defined and required by the chosen software development life cycle model. The organization must follow the principles and guidelines of the software development life cycle model, and ensure that the test levels are consistent and coherent with the development phases. If the organization wants to have more flexibility and adaptability in choosing the test levels, it should consider using a different software development life cycle model, such as an agile or iterative model, that allows for more dynamic and incremental testing approaches.
B) It is not allowed because integration testing is not an important test level and can be dispensed with. This statement is false and misleading, as integration testing is a very important test level that cannot be dispensed with. Integration testing is vital for testing the interactions and interfaces between components or subsystems, and for ensuring the functionality, performance, and compatibility of the software or system as a whole. Integration testing can reveal defects or inconsistencies that may not be detected by component (unit) testing alone, such as interface errors, data flow errors, integration logic errors, or performance degradation. Integration testing can also help to verify and validate the architectural design and the integration strategy of the software or system, and to ensure that the software or system meets the specified and expected quality attributes, such as reliability, usability, security, and maintainability. Integration testing can also provide feedback and confidence to the developers and stakeholders about the progress and quality of the software or system development. Therefore, integration testing is a crucial and indispensable test level that should not be skipped or omitted.
C) It is not allowed because integration testing is a very important test level and ignoring it means definite poor product quality. This statement is partially true, as integration testing is a very important test level that should not be ignored, and skipping it could result in poor product quality. However, this statement is too strong and absolute, as it implies that integration testing is the only factor that determines the product quality, and that ignoring it would guarantee a poor product quality. This is not necessarily the case, as there may be other factors that affect the product quality, such as the quality of the requirements, design, code, and other test levels, the effectiveness and efficiency of the test techniques and tools, the competence and experience of the developers and testers, the availability and adequacy of the resources and environment, the management and communication of the project, and the expectations and satisfaction of the customers and users. Therefore, while integration testing is a very important test level that should not be skipped, it is not the only test level that matters, and skipping it does not necessarily mean definite poor product quality, but rather a higher risk and likelihood of poor product quality.
Reference = ISTQB Certified Tester Foundation Level Syllabus, Version 4.0, 2018, Section 2.3, pages 16-18; ISTQB Glossary of Testing Terms, Version 4.0, 2018, pages 38-39; ISTQB CTFL 4.0 - Sample Exam - Answers, Version 1.1, 2023, Question 104, page 36.


質問 # 21
Consider a given test plan which, among others, contains the following three sections: "Test Scope", "Testing Communication", and "Stakeholders". The features of the test object to be tested and those excluded from the testing represent information that is:

  • A. not usually included in a test plan, and therefore in the given test plan it should not be specified neither within the three sections mentioned, nor within the others
  • B. usually included in a test plan and, in the given test plan, it is more likely to be specified within "Testing Communication" rather than in the other two sections mentioned
  • C. usually included in a test plan and, in the given test plan, it is more likely to be specified within "Stakeholders" rather than in the other two sections mentioned
  • D. usually included in a test plan and, in the given test plan, it is more likely to be specified within "Test Scope" rather than in the other two sections mentioned

正解:D

解説:
The features of the test object to be tested and those excluded from the testing represent information that is usually included in a test plan and, in the given test plan, it is more likely to be specified within "Test Scope" rather than in the other two sections mentioned. The test scope defines the boundaries and limitations of the testing activities, such as the test items, the features to be tested, the features not to be tested, the test objectives, the test environment, the test resources, the test assumptions, the test risks, etc. The test scope helps to establish a common understanding of what is included and excluded from the testing, and to avoid ambiguity, confusion, or misunderstanding among the stakeholders. The other two sections, "Testing Communication" and "Stakeholders", are also important parts of a test plan, but they do not directly address the features of the test object. The testing communication describes the methods, frequency, and responsibilities for the communication and reporting of the testing progress, status, issues, and results. The stakeholders identify the roles and responsibilities of the people involved in or affected by the testing activities, such as the test manager, the test team, the project manager, the developers, the customers, the users, etc. Reference: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.1, Test Planning1 ISTQB® Glossary of Testing Terms v4.0, Test Plan, Test Scope2


質問 # 22
Who of the following has the best knowledge to decide what tests in a test project should be automated?

  • A. The customer
  • B. The development manager
  • C. The developer
  • D. The test leader

正解:D

解説:
The test leader is the person who is responsible for planning, monitoring, and controlling the test activities and resources in a test project. The test leader should have the best knowledge of the test objectives, scope, risks, resources, schedule, and quality criteria. The test leader should also be aware of the test automation criteria, such as the execution frequency, the test support, the team education, the roles and responsibilities, and the devs and testers collaboration1. Based on these factors, the test leader can decide which tests are suitable for automation and which are not, and prioritize them accordingly. The test leader can also coordinate with the test automation engineers, the developers, and the stakeholders to ensure the alignment of the test automation strategy with the test project goals and expectations. Reference = ISTQB Certified Tester Foundation Level (CTFL) v4.0 Syllabus, Chapter 2, Section 2.3.1, Page 152; ISTQB Glossary of Testing Terms v4.0, Page 403; ISTQB Certified Tester Foundation Level (CTFL) v4.0 Syllabus, Chapter 6, Section 6.1.1, Page 514; Top 8 Test Automation Criteria You Need To Fulfill - QAMIND1


質問 # 23
A typical objective of testing is to ensure that:

  • A. testing is used to drive the development of a software
  • B. a software has been tested using a combination of test techniques
  • C. a software has been properly covered
  • D. there are no defects in a software that is about to be released

正解:B

解説:
Explanation
This answer is correct because a typical objective of testing is to ensure that a software has been tested using a combination of test techniques, such as black-box, white-box, or experience-based techniques, that are appropriate for the test objectives, test levels, and test types. Testing using a combination of test techniques can increase the effectiveness and efficiency of testing, as different techniques can target different aspects of the software quality, such as functionality, usability, performance, security, reliability, etc. Testing using a combination of test techniques can also reduce the risk of missing defects that could be detected by one technique but not by another. References: ISTQB Foundation Level Syllabus v4.0, Section 2.3.1.1, Section
2.3.2


質問 # 24
The fact that defects are usually not evenly distributed among the various modules that make up a software application, but rather their distribution tend to reflect the Pareto principle:

  • A. is expressed by the testing principle referred to as 'Bug prediction'
  • B. is expressed by the testing principle referred to as 'Defects cluster together'
  • C. is a false myth
  • D. is expressed by the testing principle referred to as Tests wear out'

正解:B

解説:
Explanation
The fact that defects are usually not evenly distributed among the various modules that make up a software application, but rather their distribution tend to reflect the Pareto principle, is expressed by the testing principle referred to as 'Defects cluster together'. This principle states that a small number of modules contain most of the defects detected, or that a small number of causes are responsible for most of the defects. This principle can be used to guide the test analysis and design activities, by prioritizing the testing of the most critical or risky modules, or by applying more rigorous test techniques to them. Therefore, option C is the correct answer.
References: ISTQB Certified Tester Foundation Level Syllabus v4.01, Section 1.2.1, page 11; ISTQB Glossary v4.02, page 16.


質問 # 25
Which of the following is a test-first approach, where tests that express a shared understanding from stakeholders of how the application is expected to work, are first written in business-readable language (following the Given/When/Then format), and then made executable to drive development?

  • A. Test-Driven Development (TDD)
  • B. Acceptance Test-Driven Development (ATDD)
  • C. Behavior-Driven Development (BDD)
  • D. Domain-Driven Design (DDD)

正解:C

解説:
This answer is correct because Behavior-Driven Development (BDD) is a test-first approach, where tests that express a shared understanding from stakeholders of how the application is expected to work, are first written in business-readable language (following the Given/When/Then format), and then made executable to drive development. BDD is a collaborative approach that involves testers, developers, business analysts, product owners, and other stakeholders in defining the expected behavior of the application using scenarios that describe the preconditions, actions, and outcomes of the application. BDD scenarios are written using a domain-specific language (DSL) that can be translated into executable test cases using tools such as Cucumber or SpecFlow. BDD aims to improve communication, collaboration, and feedback among the team members, and to deliver software that meets the customer's needs and expectations. Reference: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 3.1.1.4


質問 # 26
The acceptance criteria associated with a user story:

  • A. can be written in different formats and represent an aspect of a user story referred to as confirmation' of the so called "3 C's"
  • B. must be written in one of the two following formats: scenario-oriented or rule-oriented
  • C. are often written in a rule-oriented format using the template referred to as "Given/When/Then"
  • D. are often documented following in rule-oriented format using the following template: "As a [role], I want [feature], so that I can [benefit]"

正解:A

解説:
The acceptance criteria associated with a user story are the conditions that must be met for the user story to be considered done and to deliver the expected value to the user. They are often written in different formats, such as rule-oriented, scenario-oriented, or table-oriented, depending on the nature and complexity of the user story. They represent an aspect of a user story referred to as confirmation, which is one of the so called "3 C's" of user stories. The other two aspects are card and conversation. Card refers to the concise and informal description of the user story, usually following the template: "As a [role], I want [feature], so that I can [benefit]". Conversation refers to the ongoing dialogue between the stakeholders and the team members to clarify and refine the user story and its acceptance criteria. Therefore, option C is the correct answer.


質問 # 27
Which of the following statements about branch coverage is true?

  • A. The minimum number of test cases needed to achieve full branch coverage, is usually lower than that needed to achieve full statement coverage
  • B. If full branch coverage has been achieved, then all unconditional branches within the code have surely been exercised
  • C. If full branch coverage has been achieved, then all combinations of conditions in a decision table have surely been exercised
  • D. Exercising at least one of the decision outcomes for all decisions within the code, ensures achieving full branch coverage

正解:D

解説:
Explanation
Exercising at least one of the decision outcomes for all decisions within the code, ensures achieving full branch coverage, which is a test coverage criterion that requires that all branches in the control flow of the code are executed at least once by the test cases. A branch is a basic block of code that has a single entry point and a single exit point, and a decision is a point in the code where the control flow can take more than one direction, such as an if-then-else statement, a switch-case statement, a loop statement, etc. The decision outcomes are the possible paths that can be taken from a decision, such as the then branch or the else branch, the case branch or the default branch, the loop body or the loop exit, etc. The other statements are false, because:
The minimum number of test cases needed to achieve full branch coverage, is usually higher than that needed to achieve full statement coverage, which is a test coverage criterion that requires that all executable statements in the code are executed at least once by the test cases. This is because branch coverage is a stronger criterion than statement coverage, as it implies statement coverage, but not vice versa. For example, a single test case can achieve full statement coverage for an if-then-else statement, but two test cases are needed to achieve full branch coverage, as both the then branch and the else branch need to be exercised.
If full branch coverage has been achieved, then all unconditional branches within the code have not necessarily been exercised, as unconditional branches are branches that do not depend on any decision, and are always executed, such as a goto statement, a break statement, a return statement, etc.
Unconditional branches are not part of the branch coverage criterion, as they do not represent different paths in the control flow of the code. However, they are part of the statement coverage criterion, as they are executable statements in the code.
If full branch coverage has been achieved, then all combinations of conditions in a decision table have not necessarily been exercised, as a decision table is a test design technique that represents the logical relationships between multiple conditions and their corresponding actions, in a tabular format. A decision table can have more combinations of conditions than the number of decisionoutcomes in the code, as each condition can have two or more possible values, such as true or false, yes or no, etc. For example, a decision table with four conditions can have 16 combinations of conditions, but the corresponding code may have only two decision outcomes, such as pass or fail. To exercise all combinations of conditions in a decision table, a stronger test coverage criterion is needed, such as condition combination coverage, which requires that all possible combinations of condition outcomes in the code are executed at least once by the test cases. References: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.3.1, Test Coverage Criteria Based on the Structure of the Software ISTQB Glossary of Testing Terms v4.0, Branch Coverage, Statement Coverage, Branch, Decision, Decision Outcome, Unconditional Branch, Decision Table, Condition Combination Coverage


質問 # 28
A system has a self-diagnostics module that starts executing after the system is reset. The diagnostics are running 12 different tests on the systems memory hardware. The following is one of the requirements set for the diagnostics module:
'The time taking the diagnostics tests to execute shall be less than 2 seconds' Which of the following is a failure related to the specified requirement?

  • A. The diagnostic tests that measure the speed of the memory, fail
  • B. The diagnostic tests fail due to incorrect implementation of the test code
  • C. The diagnostic tests fail to start after a system reset
  • D. The diagnostic tests take too much time to execute

正解:D

解説:
A failure is an event in which a component or system does not perform a required function within specified limits1. A requirement is a condition or capability needed by a user to solve a problem or achieve an objective2. In this case, the requirement is that the diagnostics tests should execute in less than 2 seconds. Therefore, any event that violates this requirement is a failure. The only option that clearly violates this requirement is B. The diagnostic tests take too much time to execute. If the diagnostic tests take more than 2 seconds to complete, then they do not meet the specified limit and thus fail. The other options are not necessarily failures related to the specified requirement. Option A. The diagnostic tests fail to start after a system reset is a failure, but not related to the time limit. It is related to the functionality of the self-diagnostics module. Option C. The diagnostic tests that measure the speed of the memory, fail is also a failure, but not related to the time limit. It is related to the accuracy of the memory tests. Option D. The diagnostic tests fail due to incorrect implementation of the test code is also a failure, but not related to the time limit. It is related to the quality of the test code. Reference = ISTQB® Certified Tester Foundation Level Syllabus v4.0, Requirements Engineering Fundamentals.


質問 # 29
Consider the following simplified version of a state transition diagram that specifies the behavior of a video poker game:

What Is the minimum number of test cases needed to cover every unique sequence of up to 3 states/2 transitions starting In the "Start" state and ending In the "End" state?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

正解:C

解説:
The minimum number of test cases needed to cover every unique sequence of up to 3 states/2 transitions starting in the "Start" state and ending in the "End" state is 4. This is because there are 4 unique sequences of up to 3 states/2 transitions starting in the "Start" state and ending in the "End" state:
Start -> Bet -> End
Start -> Deal -> End
Start -> 1st Deal -> End
Start -> 2nd Deal -> End Reference: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents.


質問 # 30
The following rules determine the annual bonus to be paid to a salesman of a company based on the total annual amount of the sales made (referred to as TAS).
If the TAS is between 50k€ and 80k€, the bonus is 10%. If the TAS exceeds 80k€ by a value not greater than 40k€, the bonus is 15%. Finally, if the TAS exceeds the maximum threshold which entitles to a 15% bonus, the bonus is 22%.
Consider applying equivalence partitioning to the TAS (Note: 1k€ = 1000 euros).
Which one of the following answers contain only test cases that belong to the same equivalence partition?

  • A. TC1 = 40k€; TC2= 46k€; TC3=51k€; TC4=53k€
  • B. TC1 = 79k€; TC2= 80k€; TC3=81k€; TC4=82k€
  • C. TC1 = 90k€; TC2= 110k€; TC3=125k€: TC4=140k€
  • D. TC1 = 81 k€; TC2= 97k€; TC3=111k€; TC4=118k€

正解:D

解説:
This answer is correct because equivalence partitioning is a test design technique that divides the input domain of a system or component into partitions of equivalent data, such that each partition is expected to produce the same output or behavior. Equivalence partitioning aims to reduce the number of test cases by selecting one representative value from each partition. In this case, the input domain of the TAS can be divided into four partitions based on the bonus rules: less than 50k€, between 50k€ and 80k€, between 80k€ and 120k€, and more than 120k€. The test cases in the answer belong to the same partition, which is between 80k€ and 120k€, and they are expected to produce the same output, which is a bonus of 15%. Reference: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 2.3.2.1


質問 # 31
Which of the following statements about branch coverage is true?

  • A. The minimum number of test cases needed to achieve full branch coverage, is usually lower than that needed to achieve full statement coverage
  • B. If full branch coverage has been achieved, then all unconditional branches within the code have surely been exercised
  • C. If full branch coverage has been achieved, then all combinations of conditions in a decision table have surely been exercised
  • D. Exercising at least one of the decision outcomes for all decisions within the code, ensures achieving full branch coverage

正解:D

解説:
Exercising at least one of the decision outcomes for all decisions within the code, ensures achieving full branch coverage, which is a test coverage criterion that requires that all branches in the control flow of the code are executed at least once by the test cases. A branch is a basic block of code that has a single entry point and a single exit point, and a decision is a point in the code where the control flow can take more than one direction, such as an if-then-else statement, a switch-case statement, a loop statement, etc. The decision outcomes are the possible paths that can be taken from a decision, such as the then branch or the else branch, the case branch or the default branch, the loop body or the loop exit, etc. The other statements are false, because:
The minimum number of test cases needed to achieve full branch coverage, is usually higher than that needed to achieve full statement coverage, which is a test coverage criterion that requires that all executable statements in the code are executed at least once by the test cases. This is because branch coverage is a stronger criterion than statement coverage, as it implies statement coverage, but not vice versa. For example, a single test case can achieve full statement coverage for an if-then-else statement, but two test cases are needed to achieve full branch coverage, as both the then branch and the else branch need to be exercised.
If full branch coverage has been achieved, then all unconditional branches within the code have not necessarily been exercised, as unconditional branches are branches that do not depend on any decision, and are always executed, such as a goto statement, a break statement, a return statement, etc. Unconditional branches are not part of the branch coverage criterion, as they do not represent different paths in the control flow of the code. However, they are part of the statement coverage criterion, as they are executable statements in the code.
If full branch coverage has been achieved, then all combinations of conditions in a decision table have not necessarily been exercised, as a decision table is a test design technique that represents the logical relationships between multiple conditions and their corresponding actions, in a tabular format. A decision table can have more combinations of conditions than the number of decision outcomes in the code, as each condition can have two or more possible values, such as true or false, yes or no, etc. For example, a decision table with four conditions can have 16 combinations of conditions, but the corresponding code may have only two decision outcomes, such as pass or fail. To exercise all combinations of conditions in a decision table, a stronger test coverage criterion is needed, such as condition combination coverage, which requires that all possible combinations of condition outcomes in the code are executed at least once by the test cases. Reference: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.3.1, Test Coverage Criteria Based on the Structure of the Software ISTQB® Glossary of Testing Terms v4.0, Branch Coverage, Statement Coverage, Branch, Decision, Decision Outcome, Unconditional Branch, Decision Table, Condition Combination Coverage


質問 # 32
Which of the following statements refers to good testing practice to be applied regardless of the chosen software development model?

  • A. Tests should be written in executable format before the code is written and should act as executable specifications that drive coding
  • B. Test objectives should be the same for all test levels, although the number of tests designed at various levels can vary significantly
  • C. Test levels should be defined such that the exit criteria of one level are part of the entry criteria for the next level
  • D. Involvement of testers in work product reviews should occur as early as possible to take advantage of the early testing principle

正解:D

解説:
The statement that refers to good testing practice to be applied regardless of the chosen software development model is option D, which says that involvement of testers in work product reviews should occur as early as possible to take advantage of the early testing principle. Work product reviews are static testing techniques, in which the work products of the software development process, such as the requirements, the design, the code, the test cases, etc., are examined by one or more reviewers, with or without the author, to identify defects, violations, or improvements. Involvement of testers in work product reviews can provide various benefits for the testing process, such as improving the test quality, the test efficiency, and the test communication. The early testing principle states that testing activities should start as early as possible in the software development lifecycle, and should be performed iteratively and continuously throughout the lifecycle. Applying the early testing principle can help to prevent, detect, and remove defects at an early stage, when they are easier, cheaper, and faster to fix, as well as to reduce the risk, the cost, and the time of the testing process. The other options are not good testing practices to be applied regardless of the chosen software development model, but rather specific testing practices that may or may not be applicable or beneficial for testing, depending on the context and the objectives of the testing activities, such as:
Tests should be written in executable format before the code is written and should act as executable specifications that drive coding: This is a specific testing practice that is associated with test-driven development, which is an approach to software development and testing, in which the developers write automated unit tests before writing the source code, and then refactor the code until the tests pass. Test-driven development can help to improve the quality, the design, and the maintainability of the code, as well as to provide fast feedback and guidance for the developers. However, test-driven development is not a good testing practice to be applied regardless of the chosen software development model, as it may not be feasible, suitable, or effective for testing in some contexts or situations, such as when the requirements are unclear, unstable, or complex, when the test automation tools or skills are not available or adequate, when the testing objectives or levels are not aligned with the unit testing, etc.
Test levels should be defined such that the exit criteria of one level are part of the entry criteria for the next level: This is a specific testing practice that is associated with sequential software development models, such as the waterfall model, the V-model, or the W-model, in which the software development and testing activities are performed in a linear and sequential order, with well-defined phases, deliverables, and dependencies. Test levels are the stages of testing that correspond to the levels of integration of the software system, such as component testing, integration testing, system testing, and acceptance testing. Test levels should have clear and measurable entry criteria and exit criteria, which are the conditions that must be met before starting or finishing a test level. In sequential software development models, the exit criteria of one test level are usually part of the entry criteria for the next test level, to ensure that the software system is ready and stable for the next level of testing. However, this is not a good testing practice to be applied regardless of the chosen software development model, as it may not be relevant, flexible, or efficient for testing in some contexts or situations, such as when the software development and testing activities are performed in an iterative and incremental order, with frequent changes, feedback, and adaptations, as in agile software development models, such as Scrum, Kanban, or XP, when the test levels are not clearly defined or distinguished, or when the test levels are performed in parallel or concurrently, etc.
Test objectives should be the same for all test levels, although the number of tests designed at various levels can vary significantly: This is a specific testing practice that is associated with uniform software development models, such as the spiral model, the incremental model, or the prototyping model, in which the software development and testing activities are performed in a cyclical and repetitive manner, with similar phases, deliverables, and processes. Test objectives are the goals or the purposes of testing, which can vary depending on the test level, the test type, the test technique, the test environment, the test stakeholder, etc. Test objectives can be defined in terms of the test basis, the test coverage, the test quality, the test risk, the test cost, the test time, etc. Test objectives should be specific, measurable, achievable, relevant, and time-bound, and they should be aligned with the project objectives and the quality characteristics. In uniform software development models, the test objectives may be the same for all test levels, as the testing process is repeated for each cycle or iteration, with similar focus, scope, and perspective of testing. However, this is not a good testing practice to be applied regardless of the chosen software development model, as it may not be appropriate, realistic, or effective for testing in some contexts or situations, such as when the software development and testing activities are performed in a hierarchical and modular manner, with different phases, deliverables, and dependencies, as in sequential software development models, such as the waterfall model, the V-model, or the W-model, when the test objectives vary according to the test levels, such as component testing, integration testing, system testing, and acceptance testing, or when the test objectives change according to the feedback, the learning, or the adaptation of the testing process, as in agile software development models, such as Scrum, Kanban, or XP, etc. Reference: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 1.1.1, Testing and the Software Development Lifecycle1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 1.2.1, Testing Principles1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 1.2.2, Testing Policies, Strategies, and Test Approaches1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 1.3.1, Testing in Software Development Lifecycles1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.1, Test Planning1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.2, Test Monitoring and Control1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.3, Test Analysis and Design1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.4, Test Implementation1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.5, Test Execution1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.6, Test Closure1 ISTQB® Glossary of Testing Terms v4.0, Work Product Review, Static Testing, Early Testing, Test-driven Development, Test Level, Entry Criterion, Exit Criterion, Test Objective, Test Basis, Test Coverage, Test Quality, Test Risk, Test Cost, Test Time2


質問 # 33
A new web app aims at offering a rich user experience. As a functional tester, you have run some functional tests to verify that, before releasing the app, such app works correctly on several mobile devices, all of which are listed as supported devices within the requirements specification. These tests were performed on stable and isolated test environments where you were the only user interacting with the application. All tests passed, but in some of those tests you observed the following issue: on some mobile devices only, the response time for two web pages containing images was extremely slow.
Based only on the given information, which of the following recommendation would you follow?

  • A. You should not open any defect report as the problem is most likely due to poor hardware equipment on the devices where you observed the issue
  • B. You should open a defect report providing detailed information on which devices and by running which tests you observed the issue
  • C. The issue is related to performance efficiency, not functionality. Thus, as a functional tester, you should not open any defect report as all the functional tests passed
  • D. You should not open any defect report and inform the test manager that the devices on which you observed the issue should no longer be supported so that they will be removed from the requirements specification

正解:B

解説:
As a functional tester, you should open a defect report providing detailed information on which devices and by running which tests you observed the issue. A defect report is a document that records the occurrence, nature, and status of a defect detected during testing, and provides information for further investigation and resolution. A defect report should include relevant information such as the defect summary, the defect description, the defect severity, the defect priority, the defect status, the defect origin, the defect category, the defect reproduction steps, the defect screenshots, the defect attachments, etc. Opening a defect report is a good practice for any tester who finds a defect in the software system, regardless of the type or level of testing performed. The other options are not recommended, because:
The issue is related to performance efficiency, not functionality, but that does not mean that as a functional tester, you should not open any defect report as all the functional tests passed. Performance efficiency is a quality characteristic that measures how well the software system performs its functions under stated conditions, such as the response time, the resource utilization, the throughput, etc. Performance efficiency is an important aspect of the user experience, especially for web applications that run on different devices and networks. Even if the functional tests passed, meaning that the software system met the functional requirements, the performance issue observed on some devices could still affect the user satisfaction, the usability, the reliability, and the security of the software system. Therefore, as a functional tester, you have the responsibility to report the performance issue as a defect, and provide as much information as possible to help the developers or the performance testers to investigate and resolve it.


質問 # 34
A company runs a pilot project for evaluation of a test automation tool. Which of the following is NOT a valid object of this pilot project?

  • A. Decide upon standards for tool implementation
  • B. Get familiar with the functionality and options of the tool
  • C. Check haw the tool fits to the existing test processes
  • D. Train all testers on using the tool

正解:D

解説:
A pilot project is a small-scale experiment or trial that is conducted to evaluate the feasibility, effectiveness, and suitability of a test automation tool before implementing it on a larger scale1.
The objectives of a pilot project may vary depending on the context and scope of the test automation initiative, but some common ones are2:
To get familiar with the functionality and options of the tool
To check how the tool fits to the existing test processes and environment To assess the benefits and challenges of using the tool To decide upon standards and guidelines for tool implementation and usage To estimate the costs and resources required for tool deployment and maintenance Therefore, option C is not a valid objective of a pilot project, as it is not necessary to train all testers on using the tool at this stage. Training all testers on using the tool would be more appropriate after the tool has been selected and approved for full-scale implementation, and after the standards and guidelines have been established. Training all testers on using the tool during the pilot project would be inefficient, costly, and premature, as the tool may not be suitable or effective for the intended purpose, or may be replaced by another tool later.
Reference:
1: ISTQB Certified Tester Foundation Level Syllabus 2018, Version 4.0, p. 82
2: ISTQB Certified Tester Foundation Level Syllabus 2018, Version 4.0, p. 83
3: ISTQB Certified Tester Foundation Level Syllabus 2018, Version 4.0, p. 84
4: ISTQB Certified Tester Foundation Level Syllabus 2018, Version 4.0, p. 85


質問 # 35
Which of the following statements refers to good testing practice to be applied regardless of the chosen software development model?

  • A. Tests should be written in executable format before the code is written and should act as executable specifications that drive coding
  • B. Test objectives should be the same for all test levels, although the number of tests designed at various levels can vary significantly
  • C. Test levels should be defined such that the exit criteria of one level are part of the entry criteria for the next level
  • D. Involvement of testers in work product reviews should occur as early as possible to take advantage of the early testing principle

正解:D

解説:
Explanation
The statement that refers to good testing practice to be applied regardless of the chosen software development model is option D, which says that involvement of testers in work product reviews should occur as early as possible to take advantage of the early testing principle. Work product reviews are static testing techniques, in which the work products of the software development process, such as the requirements, the design, the code, the test cases, etc., are examined by one or more reviewers, with or without the author, to identify defects, violations, or improvements. Involvement of testers in work product reviews can provide various benefits for the testing process, such as improving the test quality, the test efficiency, and the test communication. The early testing principle states that testing activities should start as early as possible in the software development lifecycle, and should be performed iteratively and continuously throughout the lifecycle. Applying the early testing principle can help to prevent, detect, and remove defects at an early stage, when they are easier, cheaper, and faster to fix, as well as to reduce the risk, the cost, and the time of the testing process. The other options are not good testing practices to be applied regardless of the chosen software development model, but rather specific testing practices that may or may not be applicable or beneficial for testing, depending on the context and the objectives of the testing activities, such as:
Tests should be written in executable format before the code is written and should act as executable specifications that drive coding: This is a specific testing practice that is associated with test-driven development, which is an approach to software development and testing, in which the developers write automated unit tests before writing the source code, and then refactor the code until the tests pass.
Test-driven development can help to improve the quality, the design, and the maintainability of the code, as well as to provide fast feedback and guidance for the developers. However, test-driven development is not a good testing practice to be applied regardless of the chosen software development model, as it may not be feasible, suitable, or effective for testing in some contexts or situations, such as when the requirements are unclear, unstable, or complex, when the test automation tools or skills are not available or adequate, when the testing objectives or levels are not aligned with the unit testing, etc.
Test levels should be defined such that the exit criteria of one level are part of the entry criteria for the next level: This is a specific testing practice that isassociated with sequential software development models, such as the waterfall model, the V-model, or the W-model, in which the software development and testing activities are performed in a linear and sequential order, with well-defined phases, deliverables, and dependencies. Test levels are the stages of testing that correspond to the levels of integration of the software system, such as component testing, integration testing, system testing, and acceptance testing. Test levels should have clear and measurable entry criteria and exit criteria, which are the conditions that must be met before starting or finishing a test level. In sequential software development models, the exit criteria of one test level are usually part of the entry criteria for the next test level, to ensure that the software system is ready and stable for the next level of testing. However, this is not a good testing practice to be applied regardless of the chosen software development model, as it may not be relevant, flexible, or efficient for testing in some contexts or situations, such as when the software development and testing activities are performed in an iterative and incremental order, with frequent changes, feedback, and adaptations, as in agile software development models, such as Scrum, Kanban, or XP, when the test levels are not clearly defined or distinguished, or when the test levels are performed in parallel or concurrently, etc.
Test objectives should be the same for all test levels, although the number of tests designed at various levels can vary significantly: This is a specific testing practice that is associated with uniform software development models, such as the spiral model, the incremental model, or the prototyping model, in which the software development and testing activities are performed in a cyclical and repetitive manner, with similar phases, deliverables, and processes. Test objectives are the goals or the purposes of testing, which can vary depending on the test level, the test type, the test technique, the test environment, the test stakeholder, etc. Test objectives can be defined in terms of the test basis, the test coverage, the test quality, the test risk, the test cost, the test time, etc. Test objectives should be specific, measurable, achievable, relevant, and time-bound, and they should be aligned with the project objectives and the quality characteristics. In uniform software development models, the test objectives may be the same for all test levels, as the testing process is repeated for each cycle or iteration, with similar focus, scope, and perspective of testing. However, this is not a good testing practice to be applied regardless of the chosen software development model, as it may not be appropriate, realistic, or effective for testing in some contexts or situations, such as when the software development and testing activities are performed in a hierarchical and modular manner, with different phases, deliverables, and dependencies, as in sequential software development models, such as the waterfall model, the V-model, or the W-model, when the test objectives vary according to the test levels, such ascomponent testing, integration testing, system testing, and acceptance testing, or when the test objectives change according to the feedback, the learning, or the adaptation of the testing process, as in agile software development models, such as Scrum, Kanban, or XP, etc.References: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 1.1.1, Testing and the Software Development Lifecycle1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 1.2.1, Testing Principles1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 1.2.2, Testing Policies, Strategies, and Test Approaches1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 1.3.1, Testing in Software Development Lifecycles1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.1, Test Planning1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.2, Test Monitoring and Control1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.3, Test Analysis and Design1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.4, Test Implementation1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.5, Test Execution1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.6, Test Closure1 ISTQB Glossary of Testing Terms v4.0, Work Product Review, Static Testing, Early Testing, Test-driven Development, Test Level, Entry Criterion, Exit Criterion, Test Objective, Test Basis, Test Coverage, Test Quality, Test Risk, Test Cost, Test Time2


質問 # 36
......

認定問題集でISTQB Foundation Level CTFL_Syll_4.0ガイドで100%有効な:https://www.passtest.jp/ISQI/CTFL_Syll_4.0-shiken.html

100%必ず合格させるCTFL_Syll_4.0一発合格はこれ:https://drive.google.com/open?id=1GFxMPk2xpCITet9vtLGDaFpgpwMvqyDo