質問 # 33
Which of the following is not an example of a typical content of a test completion report for a test project?

  • A. The additional effort spent on test execution compared to what was planned
  • B. The test procedures of all test cases that have been executed
  • C. The residual risk level if a risk-based test approach was adopted
  • D. The unexpected test environment downtime that resulted in slower test execution

正解:B

解説:
This answer is correct because the test procedures of all test cases that have been executed are not a typical content of a test completion report for a test project. A test completion report is a document that summarizes the test activities and results at the end of a test project. It usually includes information such as the test objectives, scope, approach, resources, schedule, results, deviations, issues, risks, lessons learned, and recommendations for improvement. The test procedures of all test cases that have been executed are part of the test documentation, but they are not relevant for the test completion report, as they do not provide a high-level overview of the test project outcomes and performance. Reference: ISTQB Foundation Level Syllabus v4.0, Section 2.5.3.2


質問 # 34
A typical objective of testing is to ensure that:

  • A. there are no defects in a software that is about to be released
  • B. a software has been properly covered
  • C. testing is used to drive the development of a software
  • D. a software has been tested using a combination of test techniques

正解:D

解説:
Explanation
This answer is correct because a typical objective of testing is to ensure that a software has been tested using a combination of test techniques, such as black-box, white-box, or experience-based techniques, that are appropriate for the test objectives, test levels, and test types. Testing using a combination of test techniques can increase the effectiveness and efficiency of testing, as different techniques can target different aspects of the software quality, such as functionality, usability, performance, security, reliability, etc. Testing using a combination of test techniques can also reduce the risk of missing defects that could be detected by one technique but not by another. References: ISTQB Foundation Level Syllabus v4.0, Section 2.3.1.1, Section
2.3.2


質問 # 35
The following rules determine the annual bonus to be paid to a salesman of a company based on the total annual amount of the sales made (referred to as TAS).
If the TAS is between 50k€ and 80k€, the bonus is 10%. If the TAS exceeds 80k€ by a value not greater than 40k€, the bonus is 15%. Finally, if the TAS exceeds the maximum threshold which entitles to a 15% bonus, the bonus is 22%.
Consider applying equivalence partitioning to the TAS (Note: 1k€ = 1000 euros).
Which one of the following answers contain only test cases that belong to the same equivalence partition?

  • A. TC1 = 79k€; TC2= 80k€; TC3=81k€; TC4=82k€
  • B. TC1 = 90k€; TC2= 110k€; TC3=125k€: TC4=140k€
  • C. TC1 = 81 k€; TC2= 97k€; TC3=111k€; TC4=118k€
  • D. TC1 = 40k€; TC2= 46k€; TC3=51k€; TC4=53k€

正解:C

解説:
This answer is correct because equivalence partitioning is a test design technique that divides the input domain of a system or component into partitions of equivalent data, such that each partition is expected to produce the same output or behavior. Equivalence partitioning aims to reduce the number of test cases by selecting one representative value from each partition. In this case, the input domain of the TAS can be divided into four partitions based on the bonus rules: less than 50k€, between 50k€ and 80k€, between 80k€ and 120k€, and more than 120k€. The test cases in the answer belong to the same partition, which is between 80k€ and 120k€, and they are expected to produce the same output, which is a bonus of 15%. Reference: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 2.3.2.1


質問 # 36
Which of the following statements is true?

  • A. Sequential development models impose the use of systematic test techniques and do not allow the use of experience-based test techniques
  • B. In Agile software development, work product documentation tends to be lightweight and manual tests tend to be often unscripted as they are often produced using experience-based test techniques
  • C. Both in Agile software development and in sequential development models, such as the V-model, test levels tend to overlap since they do not usually have defined entry and exit criteria
  • D. In Agile software development, the first iterations are exclusively dedicated to testing activities, as testing will be used to drive development, which will be performed in the subsequent iterations

正解:B

解説:
This answer is correct because in Agile software development, work product documentation, such as user stories, acceptance criteria, or test cases, tends to be lightweight and concise, as the focus is on working software and frequent communication rather than comprehensive documentation. Manual tests tend to be often unscripted, as they are often produced using experience-based test techniques, such as error guessing or exploratory testing, which rely on the tester's skills, knowledge, and creativity to find defects and provide feedback. Reference: ISTQB Foundation Level Syllabus v4.0, Section 3.1.1.2, Section 3.2.1.2


質問 # 37
You are testing a room upgrade system for a hotel. The system accepts three differed types of room (increasing order of luxury): Platinum. Silver and Gold Luxury. ONLY a Preferred Guest Card holder s eligible for an upgrade.
Below you can find the decision table defining the upgrade eligibility:

What is the expected result for each of the following test cases?
Customer A: Preference Guest Card holder, holding a Silver room
Customer B: Non Preferred Guest Card holder, holding a Platinum room

  • A. Customer A: offers upgrade to Silver room; Customer B: offers upgrade to Silver room.
  • B. Customer A: offers upgrade to Gold Luxury room; Customer B: doesn't offer any upgrade
  • C. Customer A; doesn't offer any upgrade; Customer B: offers upgrade to Gold luxury room
  • D. Customer A: doesn't offer any upgrade; Customer B: doesn't offer any upgrade.

正解:B

解説:
According to the decision table in the image, a Preferred Guest Card holder with a Silver room is eligible for an upgrade to Gold Luxury (YES), while a non-Preferred Guest Card holder, regardless of room type, is not eligible for any upgrade (NO). Therefore, Customer A (a Preferred Guest Card holder with a Silver room) would be offered an upgrade to Gold Luxury, and Customer B (a non-Preferred Guest Card holder with a Platinum room) would not be offered any upgrade. Reference = The answer is derived directly from the decision table provided in the image; specific ISTQB Certified Tester Foundation Level (CTFL) v4.0 documents are not referenced.


質問 # 38
Which of the following statements about static testing and dynamic testing is true?

  • A. Both static testing and dynamic testing can be used to highlight issues associated with non-functional characteristics
  • B. Unlike dynamic testing, which focuses on detecting potential defects, static testing focuses on detecting failures which may be due to actual defects
  • C. Unlike dynamic testing, which can be also performed manually, static testing cannot be performed without specialized tools
  • D. Static testing is usually much less cost-effective than dynamic testing

正解:A

解説:
This answer is correct because static testing and dynamic testing are both types of testing that can be used to highlight issues associated with non-functional characteristics, such as usability, performance, security, reliability, etc. Static testing is a type of testing that involves the analysis of software work products, such as requirements, design, code, or test cases, without executing them. Dynamic testing is a type of testing that involves the execution of software work products, such as code or test cases, using inputs and verifying outputs. Both static testing and dynamic testing can be applied to different test levels and test types, and can use different test techniques and tools, to evaluate the non-functional characteristics of the software product. Reference: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 2.2.1.1, Section 2.2.1.2


質問 # 39
Consider the following examples of risks identified in different software development projects:
[I]. The contrast color ratio for both normal text and large text of a website does not comply with the applicable accessibility guidelines, making it difficult for many users to read the content on the pages
[II]. A development vendor fails to deliver their software system on time, causing significant delays to system integration testing activities that have been planned as part of a development project for a system of systems
[III]. People in the test team do not have sufficient skills to automate tests at the test levels required by the test automation strategy which does not allow production of an effective regression test suite
[IV]. In a web application, data from untrusted sources is not subject to proper input validation, making the application vulnerable to several security attacks Which of the following statements is true?

  • A. [II], [III] and [IV] are product risks; [I] is a project risk
  • B. [IV] is a product risk; [I]. [II] and [III] are project risks
  • C. [I] and [IV] are product risks. [II] and [III] are project risks
  • D. [I] and [III] are product risks; [II] and [IV] are project risks

正解:C

解説:
This answer is correct because product risks are risks that affect the quality of the software product, such as defects, failures, or non-compliance with requirements or standards. Project risks are risks that affect the project's schedule, budget, resources, or scope, such as delays, cost overruns, skill gaps, or scope changes. In this case, [I] and [IV] are product risks, as they relate to the accessibility and security of the software product, which are quality attributes. [II] and [III] are project risks, as they relate to the delivery time and the test automation skills of the test team, which are project factors. Reference: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 2.1.1.1


質問 # 40
What is test oracle?

  • A. The source for the actual results
  • B. The source of expected results
  • C. The source of lest objectives
  • D. The source of input conditions

正解:B

解説:
A test oracle is a mechanism or principle that can be used to determine whether the observed behavior or output of a system under test is correct or not1. A test oracle can be based on various sources of expected results, such as specifications, user expectations, previous versions, comparable systems, etc2. Reference: ISTQB Certified Tester Foundation Level (CTFL) v4.0 Syllabus, Section 1.2.1, Page 91; ISTQB Glossary of Testing Terms, Version 4.0, Page 332.


質問 # 41
Which of the following statements refers to good testing practice to be applied regardless of the chosen software development model?

  • A. Test levels should be defined such that the exit criteria of one level are part of the entry criteria for the next level
  • B. Tests should be written in executable format before the code is written and should act as executable specifications that drive coding
  • C. Involvement of testers in work product reviews should occur as early as possible to take advantage of the early testing principle
  • D. Test objectives should be the same for all test levels, although the number of tests designed at various levels can vary significantly

正解:C

解説:
Explanation
The statement that refers to good testing practice to be applied regardless of the chosen software development model is option D, which says that involvement of testers in work product reviews should occur as early as possible to take advantage of the early testing principle. Work product reviews are static testing techniques, in which the work products of the software development process, such as the requirements, the design, the code, the test cases, etc., are examined by one or more reviewers, with or without the author, to identify defects, violations, or improvements. Involvement of testers in work product reviews can provide various benefits for the testing process, such as improving the test quality, the test efficiency, and the test communication. The early testing principle states that testing activities should start as early as possible in the software development lifecycle, and should be performed iteratively and continuously throughout the lifecycle. Applying the early testing principle can help to prevent, detect, and remove defects at an early stage, when they are easier, cheaper, and faster to fix, as well as to reduce the risk, the cost, and the time of the testing process. The other options are not good testing practices to be applied regardless of the chosen software development model, but rather specific testing practices that may or may not be applicable or beneficial for testing, depending on the context and the objectives of the testing activities, such as:
Tests should be written in executable format before the code is written and should act as executable specifications that drive coding: This is a specific testing practice that is associated with test-driven development, which is an approach to software development and testing, in which the developers write automated unit tests before writing the source code, and then refactor the code until the tests pass.
Test-driven development can help to improve the quality, the design, and the maintainability of the code, as well as to provide fast feedback and guidance for the developers. However, test-driven development is not a good testing practice to be applied regardless of the chosen software development model, as it may not be feasible, suitable, or effective for testing in some contexts or situations, such as when the requirements are unclear, unstable, or complex, when the test automation tools or skills are not available or adequate, when the testing objectives or levels are not aligned with the unit testing, etc.
Test levels should be defined such that the exit criteria of one level are part of the entry criteria for the next level: This is a specific testing practice that isassociated with sequential software development models, such as the waterfall model, the V-model, or the W-model, in which the software development and testing activities are performed in a linear and sequential order, with well-defined phases, deliverables, and dependencies. Test levels are the stages of testing that correspond to the levels of integration of the software system, such as component testing, integration testing, system testing, and acceptance testing. Test levels should have clear and measurable entry criteria and exit criteria, which are the conditions that must be met before starting or finishing a test level. In sequential software development models, the exit criteria of one test level are usually part of the entry criteria for the next test level, to ensure that the software system is ready and stable for the next level of testing. However, this is not a good testing practice to be applied regardless of the chosen software development model, as it may not be relevant, flexible, or efficient for testing in some contexts or situations, such as when the software development and testing activities are performed in an iterative and incremental order, with frequent changes, feedback, and adaptations, as in agile software development models, such as Scrum, Kanban, or XP, when the test levels are not clearly defined or distinguished, or when the test levels are performed in parallel or concurrently, etc.
Test objectives should be the same for all test levels, although the number of tests designed at various levels can vary significantly: This is a specific testing practice that is associated with uniform software development models, such as the spiral model, the incremental model, or the prototyping model, in which the software development and testing activities are performed in a cyclical and repetitive manner, with similar phases, deliverables, and processes. Test objectives are the goals or the purposes of testing, which can vary depending on the test level, the test type, the test technique, the test environment, the test stakeholder, etc. Test objectives can be defined in terms of the test basis, the test coverage, the test quality, the test risk, the test cost, the test time, etc. Test objectives should be specific, measurable, achievable, relevant, and time-bound, and they should be aligned with the project objectives and the quality characteristics. In uniform software development models, the test objectives may be the same for all test levels, as the testing process is repeated for each cycle or iteration, with similar focus, scope, and perspective of testing. However, this is not a good testing practice to be applied regardless of the chosen software development model, as it may not be appropriate, realistic, or effective for testing in some contexts or situations, such as when the software development and testing activities are performed in a hierarchical and modular manner, with different phases, deliverables, and dependencies, as in sequential software development models, such as the waterfall model, the V-model, or the W-model, when the test objectives vary according to the test levels, such ascomponent testing, integration testing, system testing, and acceptance testing, or when the test objectives change according to the feedback, the learning, or the adaptation of the testing process, as in agile software development models, such as Scrum, Kanban, or XP, etc.References: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 1.1.1, Testing and the Software Development Lifecycle1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 1.2.1, Testing Principles1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 1.2.2, Testing Policies, Strategies, and Test Approaches1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 1.3.1, Testing in Software Development Lifecycles1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.1, Test Planning1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.2, Test Monitoring and Control1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.3, Test Analysis and Design1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.4, Test Implementation1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.5, Test Execution1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.6, Test Closure1 ISTQB Glossary of Testing Terms v4.0, Work Product Review, Static Testing, Early Testing, Test-driven Development, Test Level, Entry Criterion, Exit Criterion, Test Objective, Test Basis, Test Coverage, Test Quality, Test Risk, Test Cost, Test Time2


質問 # 42
A calculator software is used to calculate the result for 5+6.
The user noticed that the result given is 6.
This is an example of;

  • A. Error
  • B. Failure
  • C. Fault
  • D. Mistake

正解:B

解説:
According to the ISTQB Glossary of Testing Terms, Version 4.0, 2018, page 18, a failure is "an event in which a component or system does not perform a required function within specified limits". In this case, the calculator software does not perform the required function of calculating the correct result for 5+6 within the specified limits of accuracy and precision. Therefore, this is an example of a failure.
The other options are incorrect because:
A mistake is "a human action that produces an incorrect result" (page 25). A mistake is not an event, but an action, and it may or may not lead to a failure. For example, a mistake could be a typo in the code, a wrong assumption in the design, or a misunderstanding of the requirement.
A fault is "a defect in a component or system that can cause the component or system to fail to perform its required function" (page 16). A fault is not an event, but a defect, and it may or may not cause a failure. For example, a fault could be a logical error in the code, a missing specification in the design, or a contradiction in the requirement.
An error is "the difference between a computed, observed, or measured value or condition and the true, specified, or theoretically correct value or condition" (page 15). An error is not an event, but a difference, and it may or may not result in a failure. For example, an error could be a rounding error in the calculation, a measurement error in the observation, or a deviation error in the condition.
Reference = ISTQB Glossary of Testing Terms, Version 4.0, 2018, pages 15-18, 25; ISTQB CTFL 4.0 - Sample Exam - Answers, Version 1.1, 2023, Question 96, page 34.


質問 # 43
Consider a review for a high-level architectural document written by a software architect. The architect does most of the review preparation work, including distributing the document to reviewers before the review meeting. However, reviewers are not required to analyze the document in advance, and during the review meeting the software architect explains the document step by step. The only goal of this review is to establish a common understanding of the software architecture that will be used in a software development project.
Which of the following review types does this review refer to?

  • A. Audit
  • B. Inspection
  • C. Walkthrough
  • D. Informal review

正解:C

解説:
Explanation
This answer is correct because a walkthrough is a type of review where the author of the work product leads the review process and explains the work product to the reviewers. The reviewers are not required to prepare for the review in advance, and the main objective of the walkthrough is to establish a common understanding of the work product and to identify any major defects or issues. A walkthrough is usually informal and does not follow a defined process or roles. In this case, the review for a high-level architectural document written by a software architect matches the characteristics of a walkthrough. References: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 2.4.2.2


質問 # 44
A Test Manager conducts risk assessment for a project. One of the identified risks is: The sub-contractor may fail to meet his commitment". If this risk materializes. it will lead to delay in completion of testing required for the current cycle.
Which of the following sentences correctly describes the risk?

  • A. It is a product risk since any risk associated with development timeline is a product risk.
  • B. It is no longer a risk for the Test Manager since an independent party (the sub-contractor) is now managing it
  • C. It is a object risk since successful completion of the object depends on successful and timely completion of the tests
  • D. It is a product risk since default on part of the sub-contractor may lead to delay in release of the product

正解:D

解説:
A product risk is a risk that affects the quality or timeliness of the software product being developed or tested1. Product risks are related to the requirements, design, implementation, verification, and maintenance of the software product2.
The risk of the sub-contractor failing to meet his commitment is a product risk, as it could cause a delay in the completion of the testing required for the current cycle, which in turn could affect the release date of the product. The release date is an important aspect of the product quality, as it reflects the customer satisfaction and the market competitiveness of the product3.
The other options are not correct because:
A) It is not true that any risk associated with development timeline is a product risk. Some risks could be project risks, which are risks that affect the management or control of the software project, such as budget, resources, schedule, or communication1. For example, a risk of losing a key project stakeholder is a project risk, not a product risk.
B) It is not true that the risk is no longer a risk for the Test Manager since an independent party is managing it. The Test Manager is still responsible for ensuring that the testing activities are completed according to the test plan and the quality objectives4. The Test Manager should monitor and control the sub-contractor's performance and communicate with him regularly to identify and mitigate any potential issues or deviations5.
C) It is not clear what is meant by "object" in this option, but it could be interpreted as the software system under test or the test object6. In any case, the risk is not an object risk, as it does not affect the successful completion of the object, but rather the successful completion of the testing of the object. An object risk could be a risk that affects the functionality, reliability, usability, efficiency, maintainability, or portability of the software system under test2. For example, a risk of the software system having a high complexity or a low testability is an object risk, not a product risk.
Reference =
1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 97
2 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 98
3 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 99
4 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 100
5 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 101
6 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 102


質問 # 45
Which of the following statements best describes how configuration management supports testing?

  • A. Configuration management is an administrative discipline that includes change control, which is the process of controlling the changes to identified items referred to as Configuration Items'
  • B. Configuration management is an approach to interoperability testing where tests are executed in the cloud, as the cloud can provide cost-effective access to multiple configurations of the test environments
  • C. Configuration management helps ensure that all relevant project documentation and software items are uniquely identified in all their versions and therefore can be unambiguously referenced in test documentation
  • D. Configuration management helps reduce testing effort by identifying a manageable number of test environment configurations in which to test the software, out of all possible configurations of the environment in which the software will be released

正解:C

解説:
Explanation
This answer is correct because configuration management is a process of establishing and maintaining consistency of a product's performance, functional, and physical attributes with its requirements, design, and operational information throughout its life. Configuration management helps ensure that all relevant project documentation and software items are uniquely identified in all their versions and therefore can be unambiguously referenced in test documentation. This supports testing by providing traceability, consistency, and control over the test artifacts and the software under test. References: : ISTQB Glossary of Testing Terms v4.0, : ISTQB Foundation Level Syllabus v4.0, Section 2.2.2.2


質問 # 46
The whole-team approach:

  • A. promotes the idea that all team members should have a thorough understanding of test techniques
  • B. promotes the idea that all team members should be responsible for the quality of the product
  • C. is a consensus-based approach that engages the whole team in estimating the user stories
  • D. is mostly adopted in projects aimed at developing safety-critical systems, as it ensures the highest level of testing independence

正解:B

解説:
This answer is correct because the whole-team approach is a way of working in agile projects where all team members share the responsibility for the quality of the product, and collaborate on delivering value to the customer. The whole-team approach involves testers, developers, business analysts, product owners, and other stakeholders in planning, designing, developing, testing, and delivering the product. The whole-team approach fosters communication, feedback, learning, and continuous improvement within the team. Reference: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 3.1.1.1


質問 # 47
Which of the following is a test-first approach, where tests that express a shared understanding from stakeholders of how the application is expected to work, are first written in business-readable language (following the Given/When/Then format), and then made executable to drive development?

  • A. Domain-Driven Design (DDD)
  • B. Behavior-Driven Development (BDD)
  • C. Acceptance Test-Driven Development (ATDD)
  • D. Test-Driven Development (TDD)

正解:B

解説:
Explanation
This answer is correct because Behavior-Driven Development (BDD) is a test-first approach, where tests that express a shared understanding from stakeholders of how the application is expected to work, are first written in business-readable language (following the Given/When/Then format), and then made executable to drive development. BDD is a collaborative approach that involves testers, developers, business analysts, product owners, and other stakeholders in defining the expected behavior of the application using scenarios that describe the preconditions, actions, and outcomes of the application. BDD scenarios are written using a domain-specific language (DSL) that can be translated into executable test cases using tools such as Cucumber or SpecFlow. BDD aims to improve communication, collaboration, and feedback among the team members, and to deliver software that meets the customer's needsand expectations. References: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 3.1.1.4


質問 # 48
Can "cost" be regarded as Exit criteria?

  • A. Yes. Going by cost as an exit criterion constrains the testing project which will hello achieve the desired quality level defined for the project
  • B. Yes. Spending too much money on test ng will result in an unprofitable product, and having cost as an exit criterion helps avoid this
  • C. No The cost of testing cannot be measured effectively, so it is incorrect to use cost as an exit criterion
  • D. No. The financial value of product quality cannot be estimated, so it is incorrect to use cost as an exit criterion

正解:B

解説:
Cost can be regarded as an exit criterion for testing, because it is a factor that affects the profitability and feasibility of the software product. Testing is an investment that aims to improve the quality and reliability of the software product, but it also consumes resources, such as time, money, and human effort. Therefore, testing should be planned and executed in a way that balances the cost and benefit of testing activities. Having cost as an exit criterion helps to avoid spending too much money on testing, which may result in an unprofitable product or a loss of competitive advantage. Cost can also help to prioritize and focus the testing efforts on the most critical and valuable features and functions of the software product. However, cost should not be the only exit criterion for testing, as it may not reflect the true quality and risk level of the software product. Other exit criteria, such as defect rate, test coverage, user satisfaction, etc., should also be considered and defined in the test plan.
The other options are incorrect, because they either deny the importance of cost as an exit criterion, or they make false or unrealistic assumptions about the cost of testing. Option B is incorrect, because the financial value of product quality can be estimated, for example, by using cost-benefit analysis, return on investment, or cost of quality models. Option C is incorrect, because going by cost as an exit criterion does not necessarily constrain the testing project or help achieve the desired quality level. Cost is a relative and variable factor that depends on the scope, complexity, and context of the software product and the testing project. Option D is incorrect, because the cost of testing can be measured effectively, for example, by using metrics, such as test effort, test resources, test tools, test environment, etc.


質問 # 49
Which of the following applications will be the MOST suitable for testing by Use Cases

  • A. The ability of an Anti virus package to detect and quarantine a new threat
  • B. Accuracy and usability of a new Navigation system compared with previous system
  • C. Suitability and performance of a Multi media (audio video based) system to a new operating system
  • D. A billing system used to calculate monthly charge based or large number of subscribers parameters

正解:B


質問 # 50
A program is used to control a manufacturing line (turn machines on and off. start and stop conveyer belts, add raw materials to the flow. etc.). Not all actions are possible at all times. For example, there are certain manufacturing stages that cannot be stopped - unless there is an emergency. A tester attempts to evaluate if all such cases (where a specific action is not allowed) are covered by the tests.
Which coverage metric will provide the needed information for this analysis?

  • A. Code coverage
  • B. Statement coverage
  • C. Data flow coverage
  • D. Branch Coverage

正解:D

解説:
Branch coverage is a type of structural coverage metric that measures the percentage of branches or decision outcomes that are executed by the test cases. A branch is a point in the code where the control flow can take two or more alternative paths based on a condition. For example, an if-else statement is a branch that can execute either the if-block or the else-block depending on the evaluation of the condition. Branch coverage ensures that each branch is taken at least once by the test cases, and thus reveals the behavior of the software under different scenarios. Branch coverage is also known as decision coverage or all-edges coverage.
Branch coverage is suitable for testing the cases where a specific action is not allowed, because it can verify that the test cases cover all the possible outcomes of the conditions that determine the action. For example, if the program has a condition that checks if the manufacturing stage can be stopped, then branch coverage can ensure that the test cases cover both the cases where the stage can be stopped and where it cannot be stopped. This way, branch coverage can help identify any missing or incorrect branches that may lead to undesired or unsafe actions.
The other options are not correct because they are not suitable for testing the cases where a specific action is not allowed. Code coverage is a general term that encompasses various types of coverage metrics, such as statement coverage, branch coverage, data flow coverage, etc. Code coverage does not specify which type of coverage metric is used for the analysis. Data flow coverage is a type of structural coverage metric that measures the percentage of data flow paths that are executed by the test cases. A data flow path is a sequence of statements that define, use, or kill a variable. Data flow coverage is useful for testing the correctness and completeness of the data manipulation in the software, but not for testing the conditions that determine the actions. Statement coverage is a type of structural coverage metric that measures the percentage of statements or lines of code that are executed by the test cases. Statement coverage ensures that each statement is executed at least once by the test cases, but it does not reveal the behavior of the software under different scenarios. Statement coverage is a weaker criterion than branch coverage, because it does not account for the branches or decision outcomes in the code. Reference = ISTQB Certified Tester Foundation Level (CTFL) v4.0 syllabus, Chapter 4: Test Techniques, Section 4.3: Structural Testing Techniques, Pages 51-54.


質問 # 51
Following a risk-based testing approach you have designed 10 tests to cover a product risk with a high-risk level. You want to estimate, adopting the three-point test estimation technique, the test effort required to reduce the risk level to zero by executing those 10 tests. You made the following three initial estimates:
* most optimistic = 6 person hours
* most likely = 30 person hours
* most pessimistic = 54 person hours
Based only on the given information, which of the following answers about the three-point test estimation technique applied to this problem is true?

  • A. The final estimate is between 6 person hours and 54 person hours
  • B. The final estimate is between 22 person hours and 38 person hours
  • C. The final estimate is exactly 30 person hours because the technique uses the initial most likely estimate as the final estimate
  • D. The final estimate is exactly 30 person hours because the technique uses the arithmetic mean of the three initial estimates as the final estimate

正解:B

解説:
The three-point test estimation technique is a method of estimating the test effort based on three initial estimates: the most optimistic, the most likely, and the most pessimistic. The technique uses a weighted average of these three estimates to calculate the final estimate, which is also known as the expected value. The formula for the expected value is:
Expected value = (most optimistic + 4 * most likely + most pessimistic) / 6 Using the given values, the expected value is:
Expected value = (6 + 4 * 30 + 54) / 6 Expected value = 30 person hours However, the expected value is not the only factor to consider when estimating the test effort. The technique also calculates the standard deviation, which is a measure of the variability or uncertainty of the estimates. The formula for the standard deviation is:
Standard deviation = (most pessimistic - most optimistic) / 6
Using the given values, the standard deviation is:
Standard deviation = (54 - 6) / 6 Standard deviation = 8 person hours
The standard deviation can be used to determine a range of possible values for the test effort, based on a certain level of confidence. For example, using a 68% confidence level, the range is:
Expected value ± standard deviation
Using the calculated values, the range is:
30 ± 8 person hours
Therefore, the final estimate is between 22 person hours and 38 person hours, which is option A.


質問 # 52
Which of the following statements is true?

  • A. Experience-based test techniques are often useful to detect hidden defects that have not been targeted by black-box test techniques
  • B. The primary goal of experience-based test techniques is to design test cases that can be easily automated using a GUI-based test automation tool
  • C. Some of the most common test basis used by white-box test techniques include user stories, use cases and business processes
  • D. Experience-based test techniques rely on the experience of testers to identify the root causes of defects found by black-box test techniques

正解:A

解説:
Experience-based test techniques are test design techniques that rely on the experience, knowledge, intuition, and creativity of the testers to identify and execute test cases that are likely to find defects in the software system. Experience-based test techniques are often useful to detect hidden defects that have not been targeted by black-box test techniques, which are test design techniques that use the external behavior and specifications of the software system as the test basis, without considering its internal structure or implementation. Experience-based test techniques can complement black-box test techniques by covering aspects that are not explicitly specified, such as usability, security, reliability, performance, etc. The other statements are false, because:
Experience-based test techniques do not rely on the experience of testers to identify the root causes of defects found by black-box test techniques, but rather to identify the potential sources of defects based on their own insights, heuristics, or exploratory testing. The root causes of defects are usually identified by debugging or root cause analysis, which are activities that involve examining the code or the development process to find and fix the errors that led to the defects.
Some of the most common test basis used by white-box test techniques include the source code, the design documents, the architecture diagrams, and the control flow graphs of the software system. White-box test techniques are test design techniques that use the internal structure and implementation of the software system as the test basis, and aim to achieve a certain level of test coverage based on the code elements, such as statements, branches, paths, etc. User stories, use cases, and business processes are examples of test basis used by black-box test techniques, as they describe the functional and non-functional requirements of the software system from the perspective of the users or the stakeholders.
The primary goal of experience-based test techniques is not to design test cases that can be easily automated using a GUI-based test automation tool, but rather to design test cases that can reveal defects that are not easily detected by other test techniques, such as boundary value analysis, equivalence partitioning, state transition testing, etc. Test automation is the use of software tools to execute test cases and compare actual results with expected results, without human intervention. Test automation can be applied to different types of test techniques, depending on the test objectives, the test levels, the test tools, and the test resources. However, test automation is not always feasible or beneficial, especially for test cases that require human judgment, creativity, or exploration, such as those designed by experience-based test techniques. Reference: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.2.1, Black-box Test Design Techniques ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.2.2, White-box Test Design Techniques ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.2.3, Experience-based Test Design Techniques ISTQB® Glossary of Testing Terms v4.0, Experience-based Test Technique, Black-box Test Technique, White-box Test Technique, Test Basis, Test Coverage, Test Automation


質問 # 53
Which of the following lists factors That contribute to PROJECT risks?

  • A. skill and staff shortages; problems in defining the right requirements, contractual issues.
  • B. skill and staff shortages; software does not perform its intended functions; problems in defining the right requirements.
  • C. problems in defining the right requirements; contractual issues; poor software quality characteristics.
  • D. poor software quality characteristics; software does not perform its intended functions.

正解:A

解説:
Project risks are the uncertainties or threats that may affect the project objectives, such as scope, schedule, cost, and quality. According to the ISTQB Certified Tester Foundation Level (CTFL) v4.0 syllabus, some of the factors that contribute to project risks are:
Skill and staff shortages: This factor refers to the lack of adequate or qualified human resources to perform the project tasks. This may result in delays, errors, rework, or low productivity.
Problems in defining the right requirements: This factor refers to the difficulties or ambiguities in eliciting, analyzing, specifying, validating, or managing the requirements of the project. This may result in misalignment, inconsistencies, gaps, or changes in the requirements, affecting the project scope and quality.
Contractual issues: This factor refers to the challenges or disputes that may arise from the contractual agreements between the project parties, such as clients, suppliers, vendors, or subcontractors. This may result in legal, financial, or ethical risks, affecting the project delivery and satisfaction.
The other options are not correct because they list factors that contribute to PRODUCT risks, not project risks. Product risks are the uncertainties or threats that may affect the quality or functionality of the software product or system. Some of the factors that contribute to product risks are:
Poor software quality characteristics: This factor refers to the lack of adherence or compliance to the quality attributes or criteria of the software product or system, such as reliability, usability, security, performance, or maintainability. This may result in defects, failures, or dissatisfaction of the users or stakeholders.
Software does not perform its intended functions: This factor refers to the deviation or discrepancy between the expected and actual behavior or output of the software product or system. This may result in errors, faults, or malfunctions of the software product or system.
Reference = ISTQB Certified Tester Foundation Level (CTFL) v4.0 syllabus, Chapter 1: Fundamentals of Testing, Section 1.5: Risks and Testing, Pages 14-16.


質問 # 54
Consider a given test plan which, among others, contains the following three sections: "Test Scope", "Testing Communication", and "Stakeholders". The features of the test object to be tested and those excluded from the testing represent information that is:

  • A. usually included in a test plan and, in the given test plan, it is more likely to be specified within "Testing Communication" rather than in the other two sections mentioned
  • B. usually included in a test plan and, in the given test plan, it is more likely to be specified within "Stakeholders" rather than in the other two sections mentioned
  • C. usually included in a test plan and, in the given test plan, it is more likely to be specified within "Test Scope" rather than in the other two sections mentioned
  • D. not usually included in a test plan, and therefore in the given test plan it should not be specified neither within the three sections mentioned, nor within the others

正解:C

解説:
The features of the test object to be tested and those excluded from the testing represent information that is usually included in a test plan and, in the given test plan, it is more likely to be specified within "Test Scope" rather than in the other two sections mentioned. The test scope defines the boundaries and limitations of the testing activities, such as the test items, the features to be tested, the features not to be tested, the test objectives, the test environment, the test resources, the test assumptions, the test risks, etc. The test scope helps to establish a common understanding of what is included and excluded from the testing, and to avoid ambiguity, confusion, or misunderstanding among the stakeholders. The other two sections, "Testing Communication" and "Stakeholders", are also important parts of a test plan, but they do not directly address the features of the test object. The testing communication describes the methods, frequency, and responsibilities for the communication and reporting of the testing progress, status, issues, and results. The stakeholders identify the roles and responsibilities of the people involved in or affected by the testing activities, such as the test manager, the test team, the project manager, the developers, the customers, the users, etc. Reference: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.1, Test Planning1 ISTQB® Glossary of Testing Terms v4.0, Test Plan, Test Scope2


質問 # 55
The fact that defects are usually not evenly distributed among the various modules that make up a software application, but rather their distribution tend to reflect the Pareto principle:

  • A. is expressed by the testing principle referred to as 'Defects cluster together'
  • B. is expressed by the testing principle referred to as 'Bug prediction'
  • C. is a false myth
  • D. is expressed by the testing principle referred to as Tests wear out'

正解:A

解説:
The fact that defects are usually not evenly distributed among the various modules that make up a software application, but rather their distribution tend to reflect the Pareto principle, is expressed by the testing principle referred to as 'Defects cluster together'. This principle states that a small number of modules contain most of the defects detected, or that a small number of causes are responsible for most of the defects. This principle can be used to guide the test analysis and design activities, by prioritizing the testing of the most critical or risky modules, or by applying more rigorous test techniques to them. Therefore, option C is the correct answer.


質問 # 56
Which of the following statements is true?

  • A. Sequential development models impose the use of systematic test techniques and do not allow the use of experience-based test techniques
  • B. In Agile software development, work product documentation tends to be lightweight and manual tests tend to be often unscripted as they are often produced using experience-based test techniques
  • C. Both in Agile software development and in sequential development models, such as the V-model, test levels tend to overlap since they do not usually have defined entry and exit criteria
  • D. In Agile software development, the first iterations are exclusively dedicated to testing activities, as testing will be used to drive development, which will be performed in the subsequent iterations

正解:B

解説:
Explanation
This answer is correct because in Agile software development, work product documentation, such as user stories, acceptance criteria, or test cases, tends to be lightweight and concise, as the focus is on working software and frequent communication rather than comprehensive documentation. Manual tests tend to be often unscripted, as they are often produced using experience-based test techniques, such as error guessing or exploratory testing, which rely onthe tester's skills, knowledge, and creativity to find defects and provide feedback. References: ISTQB Foundation Level Syllabus v4.0, Section 3.1.1.2, Section 3.2.1.2


質問 # 57
......