質問 # 13
At what level do you create the structure of the operating concern?

  • A. Client level
  • B. Company code level
  • C. Controlling area level
  • D. Sales organization level

正解:A


質問 # 14
Which of the following values can be calculated using result analysis? Note: There are 3 correct answers to this question.

  • A. Cost of goods manufactured
  • B. Gross margin
  • C. Reserves for unrealized costs
  • D. Work in progress
  • E. Cost of sales

正解:C、D、E


質問 # 15
You want to use budget availability control for your projects and internal orders. What can you check using budget availability control? Note: There are 2 correct answers to this question.

  • A. The availability of funds on period level
  • B. The availability of funds according to tolerance limits
  • C. The availability of funds using overall plan value
  • D. The availability of funds in object currency

正解:B、D


質問 # 16
You create a new profit center. Which company code(s) is it assigned to by default?

  • A. All company codes maintained in your authorization profile.
  • B. All company codes to which the profit center standard hierarchy is assigned to.
  • C. All company codes within the controlling area.
  • D. All company codes where profit center accounting is activated.

正解:C


質問 # 17
You are creating new activity type and want to maintain plan prices for a cost center. Which attribute must you configure in the activity type master record? Note: There are 3 correct answers to this question.

  • A. Activity type category
  • B. Price indicator
  • C. Company code
  • D. CO version
  • E. Valid cost center categories

正解:A、B、E


質問 # 18
You are considering using commitment management with internal orders. What do you need to do in the configuration?

  • A. Activate commitment management in the controlling area, the order type, and in individual internal order master data.
  • B. Activate commitment management only in the controlling area.
  • C. Activate commitment management in both the controlling area and the order type.
  • D. Activate commitment management in both the version and the order type.

正解:C


質問 # 19
What are some of the characteristics of planning for internal orders? Note: There are 2 correct answers to this question.

  • A. You can enter costs and revenues.
  • B. Availability control can check against plan values.
  • C. You can define tolerance limits for plan overspend.
  • D. You can plan multiple versions.

正解:A、D


質問 # 20
You want to create a new standard cost estimate based on the quantity structure of the existing standard cost estimate. Which object do you use?

  • A. Costing type
  • B. Transfer control
  • C. Reference variant
  • D. Costing version

正解:B


質問 # 21
How do you define the relationship between an operating concern and a controlling area?

  • A. One-to-one (1:1)
  • B. Many-to-one (N:1)
  • C. Many-to-many (N:M)
  • D. One-to-many (1:N)

正解:D


質問 # 22
How does SAP S/4HANA capture costs? Note: There are 2 correct answers to this question.

  • A. Secondary costs are captured as secondary cost element, and not as general ledger accounts.
  • B. Only primary costs are captured in general ledger accounts.
  • C. Primary and secondary costs are captured in general ledger accounts.
  • D. All primary and secondary costs are captured by creating them as cost elements.

正解:C、D


質問 # 23
How can you define the overhead rate in a costing sheet? Note: There are 2 correct answers to this question.

  • A. As equivalence number
  • B. As lot-based surcharge
  • C. As quantity-based surcharge
  • D. As percentage rate

正解:C、D


質問 # 24
For which objects can you enter statistical key figures? Note: There are 3 correct answers to this question.

  • A. Functional areas
  • B. Cost elements
  • C. Internal orders
  • D. Profit centers
  • E. Cost centers

正解:C、D、E


質問 # 25
You have implemented Product Cost by Sales Oder in conjunction with revenue-based results analysis in your organization.
For a particular sales order item, you have the following:
Plan revenue = 3000; Plan costs = 2000
Actual revenue = 1200; Actual costs = 1000
What data does the system calculate during results analysis?

  • A. Revenue = 1200; Cost of sales = 800; Reserve = 200
  • B. Revenue = 1200; Cost of sales = 1000; Reserve = 200
  • C. Revenue = 1200; Cost of sales = 800; WIP = 200
  • D. Revenue = 1200; Cost of sales = 1000; WIP = 200

正解:C


質問 # 26
You want to create cost centers for your company. What is the prerequisite to build an organizational structure for overhead cost controlling?

  • A. Person responsible
  • B. Profit center
  • C. Standard hierarchy top node
  • D. Cost center categories

正解:C


質問 # 27
You want to understand why cost are collected on sales order item level. What do you need to in the configuration? Note: There are 3 correct answers to this question.

  • A. Requirements class
  • B. Valuation variant
  • C. Costing type
  • D. Requirement type
  • E. Account assignment category

正解:A、D、E


質問 # 28
Why would you use manual cost allocation in Controlling? Note: There are 2 correct answers to this question.

  • A. To run simple allocations of plan data
  • B. To run simple allocations of actual data
  • C. To correct secondary postings
  • D. To allocate costs using an allocation cycle

正解:B、C


質問 # 29
Which of the following statements best describe Product Cost by Order? Note: There are 2 correct answers to this question.

  • A. It is used when you perform repetitive manufacturing.
  • B. It is recommended for products with a long production time.
  • C. It is used when controlling by individual production lots or discrete quantities is needed.
  • D. It is used when full cost traceability is needed.

正解:C、D


質問 # 30
In SAP S/4HANA, you have decided to activate only account-based profitability analysis for your organization. You want to settle costs and revenue of a sales order item to a profitability segment. What do you need to configure?

  • A. Cost component structure
  • B. PA transfer structure
  • C. Allocation structure
  • D. Source structure

正解:B


質問 # 31
......

最新(2024)SAP C_TS4CO_2021試験問題集:https://www.passtest.jp/SAP/C_TS4CO_2021-shiken.html