試験問題解答ブレーン問題集でAgilePM-Foundation試験問題集PDF問題
無料ダウンロードAPMG-International AgilePM-Foundationリアル試験問題
質問 # 18
How is contingency typically managed in a DSDM project?
- A. Managed by varying the features to be delivered.
- B. Not needed in a DSDM project.
- C. Allowed adding a percentage to the high-level estimates.
- D. Managed by varying time and cost
正解:A
解説:
In a DSDM project, contingency is typically managed by varying the features to be delivered6. This approach aligns with the DSDM principle of delivering the most critical work first and using the MoSCoW prioritization to adjust the scope of delivery as needed.
質問 # 19
Which responsibility relates to the role of the Business Ambassador?
- A. Provide day-to-day detail of the requirements during timeboxes
- B. Provide the team with strategic direction.
- C. Responsible for the Business Case and project budget.
- D. Resolve business issues and make financial decisions
正解:A
解説:
The responsibility of the Business Ambassador in AgilePM is to provide day-to-day detail of the requirements during Timeboxes. This role involves representing the interests of the business within the project team, ensuring that the evolving product meets the business needs. The Business Ambassador works closely with the development team to clarify requirements, provide feedback, and make decisions promptly to keep the project on track.
References:
* AgilePM Foundation Handbook
* "Agile Project Management for Dummies" by Mark C. Layton
質問 # 20
What DSDM product describes how the benefits have actually accrued following a period in live operation?
- A. Project Review Report
- B. Delivery Plan
- C. Prioritized Requirement List
- D. Benefits Assessment
正解:D
質問 # 21
How are the business roles critical to the success of a DSDM project?
- A. Lead Solution Developer demonstrations
- B. Provide formal progress reporting
- C. Guide the evolution of the solution at the detailed level
- D. Make all decisions
正解:C
質問 # 22
Which statement about DSDM roles is true?
- A. In DSDM, one person must hold several roles
- B. DSDM roles should NOT be split between two people
- C. All DSDM roles should be shared
- D. One DSDM roles does NOT necessarily mean one person
正解:D
質問 # 23
Which statement about change is correct for DSDM?
- A. Change is inevitable and males estimating very difficult
- B. Change is a symptom of an inability to define requirements properly
- C. Project operate with a changing world
- D. Avoid change whenever possible
正解:C
解説:
DSDM acknowledges that change is inevitable and that projects operate within a changing world5. The methodology is designed to embrace change and harness its benefits, rather than resist it.
質問 # 24
Which technique allows for testing the achievailability of objectives?
- A. MoSCoW
- B. Facilitated Workshop
- C. Modeling
- D. Timeboxing
正解:D
解説:
Timeboxing is the technique that allows for testing the achievability of objectives. This approach involves setting a fixed period (the Timebox) during which specific tasks or objectives must be completed. By focusing on what can be achieved within the set time frame, Timeboxing helps teams test and validate whether their objectives are realistic and attainable. This iterative approach ensures continuous assessment and adaptation, promoting efficient project management.
References:
* AgilePM Foundation Handbook
* "Agile Project Management with Scrum" by Ken Schwaber
質問 # 25
How does the Post-Project phase add value to a project?
- A. Checks how well the expected business benefits have been met
- B. Brigs a baseline of the Evolving Solution into operational use
- C. Define how the operation of the solution will be managed
- D. Iteratively explores the low- level detail of the requirements
正解:A
質問 # 26
Which phase in the DSDM process aims to understand the scope of work and, in broad terms, how it will carried out, by whom, when and where?
- A. Foundations
- B. Pre-Project
- C. Evolutionary Development
- D. Feasibility
正解:A
質問 # 27
Which of the following are recognized DSDM styles of Timebox?
1. Unstructured
2. Consolidated
- A. Only 1 is true
- B. Only 2 is true
- C. Neither 1 or 2 is true
- D. Both 1 and 2 are true
正解:D
解説:
DSDM recognizes two styles of Timebox: a structured Timebox and a free format Timebox1. The structured Timebox is the original DSDM-style Timebox, which provides a standard, repeatable internal structure to a Timebox. The free format Timebox allows more flexibility
質問 # 28
Which statement applies to the DSDM process?
- A. Can be configured and calibrated to cater for light or strong governance
- B. Does not require the elaboration of supporting products for complex projects
- C. Provides an approach that can be used for all projects without change
- D. DSDM projects can deliver the phases in the DSDM process in any order
正解:A
解説:
The DSDM process can indeed be configured and calibrated to cater for a range of projects, from those requiring light governance to those needing stronger governance1. This flexibility allows the DSDM process to be tailored to the specific needs of the project, ensuring that the right balance between control and agility is achieved1.
質問 # 29
Which of the following support the DSDM philosophy and principles?
- A. Plans, projects, process and people
- B. Phases, productivity, power and process
- C. People, products, phase and plans
- D. Process, people, products and practices
正解:D
質問 # 30
What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?
- A. Foundation Summary
- B. Delivery Plan
- C. Management Approach Definition
- D. Terms of Reference
正解:A
質問 # 31
What phase will decide on which projects are started, based on a clearly defined objective?
- A. Pre-Project
- B. Foundations
- C. Post-project
- D. Feasibility
正解:A
質問 # 32
How should DSDM team measure progress?
- A. Based on the completion of activities rather than the delivery of products
- B. Through a project dashboard
- C. Based on what has been delivered at the end of a Timebox.
- D. Through an analysis of the Instrumental Success Factors.
正解:C
解説:
A DSDM team should measure progress: B. Based on what has been delivered at the end of a Timebox5.
質問 # 33
Identify the missing words in the following sentence.
Principles 1 -Focus on the Business Need suggests that every decision taken during a project should be [?] - to deliver what the business needs to be delivered.
- A. Made collaboratively
- B. Share between all of the project roles
- C. Viewed in light of the overriding project goal
- D. The responsibility of the Business Sponsor
正解:C
解説:
Principle 1 - Focus on the Business Need suggests that every decision taken during a project should be viewed in light of the overriding project goal. This principle ensures that all decisions align with the main objective of delivering what the business needs, thus maintaining a clear focus on achieving the project's goals.
質問 # 34
Which competence is NOT required within the Solution Development team?
- A. Technical expertise
- B. Willingness to work with other
- C. Business knowledge
- D. All members to be multi-skilled experts
正解:D
質問 # 35
Which of the following is a DSMD principle?
- A. Build incrementally in Timeboxes
- B. Build incrementally from Feasibility onwards
- C. Build incrementally
- D. Build incrementally from firm foundations
正解:D
解説:
The DSMD (Dynamic Systems Development Method) principle of "Build incrementally from firm foundations" emphasizes the importance of having a solid understanding of the project's foundation before proceeding with incremental development. This principle ensures that each increment is built upon a stable base, which supports the overall project integrity and success.
質問 # 36
When should the quality of the evolving solution first be tesed?
- A. As part of the iterative Development process
- B. At the end of each increment
- C. At the end of a Timebox
- D. At the end of a project.
正解:A
解説:
The quality of the evolving solution should be tested as part of the iterative development process4. This approach allows for continuous integration and testing of the solution, ensuring that quality is built into the product from the beginning and maintained throughout the development cycle.
質問 # 37
What phase will decide on which projects are started, based on a clearly defined objective?
- A. Pre-Project
- B. Foundations
- C. Post-project
- D. Feasibility
正解:A
解説:
The Pre-Project phase is the stage where it is decided which projects are started, based on a clearly defined objective1. This phase ensures that only the right projects are initiated and that they are set up correctly, aligning with the DSDM philosophy that the best business value emerges when projects are aligned to clear business goals1.
質問 # 38
Which phase in the DSDM process aims to understand the scope of work and, in broad terms, how it will carried out, by whom, when and where?
- A. Foundations
- B. Pre-Project
- C. Evolutionary Development
- D. Feasibility
正解:A
解説:
The phase in the DSDM process that aims to understand the scope of work and, in broad terms, how it will be carried out, by whom, when, and where is.
質問 # 39
How is contingency typically managed in a DSDM project?
- A. Managed by varying the features to be delivered.
- B. Not needed in a DSDM project.
- C. Allowed adding a percentage to the high-level estimates.
- D. Managed by varying time and cost
正解:A
質問 # 40
......
Agile Project Management(AGILEPM)Foundation認定試験は、アジャイル環境での効果的なプロジェクト管理に必要な知識とスキルを検証するグローバルに認められた認定です。この認定は、厳格な基準と品質保証プロセスで世界的に認識されている主要な認定および認定機関であるAPMG-Internationalによって提供されます。 AGILEPM Foundation認定試験は、アジャイルプロジェクト管理の包括的な理解と、成功したプロジェクトを提供するためにどのように適用できるかについての専門家向けに設計されています。
最新のAPMG-International AgilePM-Foundationリアル試験問題集PDF:https://www.passtest.jp/APMG-International/AgilePM-Foundation-shiken.html
AgilePM-Foundation試験問題集、AgilePM-Foundation練習テスト問題:https://drive.google.com/open?id=1olcy-feu7yDt8EVwz4npVO0JvkpaFHpF