質問 # 18
Which information is given in the Solution Architecture Definition?

  • A. The tools and standards to be used in Evolutionary Development
  • B. A snapshot of the evolving business, solution and management products
  • C. A high-level design framework for the solution.
  • D. The strategy for testing

正解:C

解説:
The Solution Architecture Definition is an evolutionary product that provides a high-level design framework for the solution2. It is intended to cover both business and technical aspects of the solution to a level of detail that makes the scope of the solution clear but does not constrain evolutionary development2. This ensures that the solution architecture supports the business direction and the solution under development will be fit for its intended purpose3


質問 # 19
Which information is given in the Solution Architecture Definition?

  • A. The tools and standards to be used in Evolutionary Development
  • B. A snapshot of the evolving business, solution and management products
  • C. A high-level design framework for the solution.
  • D. The strategy for testing

正解:C

解説:
The Solution Architecture Definition is an evolutionary product that provides a high-level design framework for the solution2. It is intended to cover both business and technical aspects of the solution to a level of detail that makes the scope of the solution clear but does not constrain evolutionary development2. This ensures that the solution architecture supports the business direction and the solution under development will be fit for its intended purpose3


質問 # 20
What role is responsible for interpreting the needs of the Business Sponsor and communicating these to the team?

  • A. Technical Coordinator
  • B. Business Analyst
  • C. Business Visionary
  • D. Team Leader

正解:C


質問 # 21
Which practice provides an interactive environment in which all key players can contribute to the outcome?

  • A. Iterative Development
  • B. Facilitied Wordshop
  • C. Modelling
  • D. Timeboxing

正解:B

解説:
A Facilitated Workshop provides an interactive environment where all key players can contribute to the outcome3. It is a practice within Agile and DSDM that encourages collaboration and active participation from all stakeholders to shape the project's direction and solutions.


質問 # 22
Which of the following is NOT an interest into which each DSDM role is grouped?

  • A. Maintenance
  • B. Business
  • C. Management
  • D. Solution/Technical

正解:C


質問 # 23
What role is responsible for the delivery of the project from Foundations through to Deployment?

  • A. Technical Coordinator
  • B. Project manager
  • C. Business Visionary
  • D. Business Sponsor

正解:B


質問 # 24
Identify the missing words in the following sentence.
Principles 1 -Focus on the Business Need suggests that every decision taken during a project should be [?] - to deliver what the business needs to be delivered.

  • A. Made collaboratively
  • B. Share between all of the project roles
  • C. Viewed in light of the overriding project goal
  • D. The responsibility of the Business Sponsor

正解:C

解説:
Principle 1 - Focus on the Business Need suggests that every decision taken during a project should be viewed in light of the overriding project goal. This principle ensures that all decisions align with the main objective of delivering what the business needs, thus maintaining a clear focus on achieving the project's goals.


質問 # 25
In what phase is it first established whether further investigation of the project is justified?

  • A. Feasibility
  • B. Pre-Project
  • C. Foundations
  • D. Evolutionary Development

正解:A

解説:
It is during the Feasibility phase that it is first established whether further investigation of the project is justified3. This phase aims to determine if the proposed project is likely to be feasible from both a technical and business perspective.


質問 # 26
What DSDM product describes how the benefits have actually accrued following a period in live operation?

  • A. Project Review Report
  • B. Delivery Plan
  • C. Prioritized Requirement List
  • D. Benefits Assessment

正解:D

解説:
The DSDM product that describes how the benefits have actually accrued following a period in live operation is the Benefits Assessment3. This product is used to assess the actual benefits realized after the solution has been in use3.


質問 # 27
Which technique allows for testing the achievailability of objectives?

  • A. MoSCoW
  • B. Timeboxing
  • C. Modeling
  • D. Facilitated Workshop

正解:D


質問 # 28
Which purpose relates to the Consolidation in a structured Timebox?

  • A. To formality accept the structured Timebox deliverables.
  • B. To address the requirements and test the structure Timebox product.
  • C. To confirm the detail of all the requirements to be delivered by the structured Timebox.
  • D. To tie up any loose ends related to Evolutionary Development

正解:C


質問 # 29
Identify the missing words in the following sentence.
Principles 1 -Focus on the Business Need suggests that every decision taken during a project should be [?] - to deliver what the business needs to be delivered.

  • A. Made collaboratively
  • B. Viewed in light of the overriding project goal
  • C. Share between all of the project roles
  • D. The responsibility of the Business Sponsor

正解:A


質問 # 30
How is Quality ensured during Evolutionary Development?

  • A. By facilitating session to enable a group to work to achieve an agreed goal
  • B. By managing objectives in a fixed time period
  • C. By continuous verification
  • D. By understanding and managing priorities

正解:C

解説:
Quality during Evolutionary Development is ensured by continuous verification2. This involves iterative development, where all development processes, including testing, are repeated to ensure the output is complete and able to generate useful feedback2.


質問 # 31
Which responsibility relates to the role of the Business Ambassador?

  • A. Provide day-to-day detail of the requirements during timeboxes
  • B. Provide the team with strategic direction.
  • C. Responsible for the Business Case and project budget.
  • D. Resolve business issues and make financial decisions

正解:A

解説:
The responsibility of the Business Ambassador in AgilePM is to provide day-to-day detail of the requirements during Timeboxes. This role involves representing the interests of the business within the project team, ensuring that the evolving product meets the business needs. The Business Ambassador works closely with the development team to clarify requirements, provide feedback, and make decisions promptly to keep the project on track.
References:
* AgilePM Foundation Handbook
* "Agile Project Management for Dummies" by Mark C. Layton


質問 # 32
What role normally facilitates the Daily Stand.up?

  • A. Project manager
  • B. Technical Advisor
  • C. Team Leader
  • D. Business Advisor

正解:C


質問 # 33
......


AGILEPMは、世界中の組織で使用されている非常に人気のあるプロジェクト管理アプローチです。 AgilePMフレームワークは、柔軟性、適応性があり、協力的であるように設計されているため、不確実性が高いか頻繁な変更が必要なプロジェクトに最適です。 AGILEPM認定は雇用主によって高く評価されており、プロジェクト管理の分野でのトップ認定の1つとして認識されています。

 

突破受験者のシミュレーションされたAgilePM-Foundation問題集:https://www.passtest.jp/APMG-International/AgilePM-Foundation-shiken.html

売上ナンバーワン試験参照問題:https://drive.google.com/open?id=1U32BCeGjRf8nfywS9dpX_B3ZlPfF-TmY