質問 # 56
What activities are concurrent to Activity 2001 in the "normal" schedule?

  • A. 2003.
  • B. 1001.
  • C. 7001.
  • D. 1000.

正解:C


質問 # 57
What does the narrow band at "Y" represent?

  • A. A rework period.
  • B. You cannot tell with the information supplied.
  • C. Resource limitation period.
  • D. Activity inactivity.

正解:D


質問 # 58
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

  • A. Use the progressed portion of the critical path of all the updates previous to the current update.
  • B. Use the forward-looking critical path of the most current updates.
  • C. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
  • D. Use the progressed portion of the critical path of the baseline schedule.

正解:D


質問 # 59
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

  • A. The activities run concurrently.
  • B. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
  • C. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
  • D. The activities occur in series with a 15-day lag.

正解:D


質問 # 60
Why does activity 1001 have two successor activities?

  • A. Because the problem could not effectively work with only one successor
  • B. Because the late finish of 1001 and the late start of 7001 require two successors
  • C. Because the duration of activities 2001, 2002 and 200.f require two successors
  • D. Because there are two defined logic paths for the work

正解:D


質問 # 61
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

  • A. 06-11-02.
  • B. 06-18-02.
  • C. 06-05-02.
  • D. 06-04-02.

正解:C


質問 # 62
What does the heavy, vertical line at "X" represent?

  • A. The status or data date.
  • B. International Date Line.
  • C. Delay fault line.
  • D. Change-over limits.

正解:A


質問 # 63
Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?

  • A. 9001 and 6002 and 6002
  • B. 1001 and 6001
  • C. 1000 and 6001
  • D. 1000. 1001. and 6001

正解:A


質問 # 64
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

  • A. Expedite printing by 5 days.
  • B. Delay product release by 5 days.
  • C. Delay manufacturing by 5 days.
  • D. Expedite packaging by 5 days.

正解:B


質問 # 65
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

  • A. 20 lifts
  • B. 5 lifts
  • C. 50 lifts
  • D. 80 lifts

正解:C


質問 # 66
Activity C is a

  • A. Milestone.
  • B. Contentious activity.
  • C. 1-day activity.
  • D. Continuous activity.

正解:A


質問 # 67
What does the heavy, vertical line at "X" represent?

  • A. The status or data date.
  • B. International Date Line.
  • C. Delay fault line.
  • D. Change-over limits.

正解:A


質問 # 68
What is the free float for Activity F?

  • A. 3 months.
  • B. 2month.
  • C. 0months.
  • D. 1months.

正解:C


質問 # 69
If a new hammock activity covering activities 6001 through 6003 is developed, what are governing predecessor and successor activities?

  • A. Predecessor is Activity 5001, successor is Activity 8001
  • B. Predecessor is Activity 8001, successor is Activity 5001
  • C. Predecessor is Activity 4001. successor is Activity 9004
  • D. Predecessor is Activity 4001, successor is Activity 9003

正解:A


質問 # 70
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

  • A. Entering the time impacts of delays and change orders.
  • B. Making "downstream" logic revisions as required.
  • C. Estimating remaining durations of activities.
  • D. The correct recording of actual start dates.

正解:B


質問 # 71
What is accurate about Activity 7001 in the precedence diagram?

  • A. The LF is correct
  • B. The successor FF lag from 7001 to 11001 is not shown
  • C. The TF is not calculated correctly
  • D. The LF is not correct

正解:B


質問 # 72
What portion of Activity B is on the critical path?

  • A. First half of the activity
  • B. Last half of the activity
  • C. The whole activity
  • D. None of it

正解:D


質問 # 73
Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?

  • A. 12-27-03 and 24 days of float
  • B. 12-17-03 and 4 days of float
  • C. 12-18-03 and 25 days of float
  • D. 12-18-03 and 4 days of float

正解:B


質問 # 74
......