合格させるEXIN CDCSにはPassTest提供の試験問題集で2025年03月更新 [Q34-Q53]

Share

合格させるEXIN CDCSにはPassTest提供の試験問題集で2025年03月更新

完全版最新のCDCS問題集、100%カバー率問題と解答があなたをリアル試験で合格させる

質問 # 34
The pipes of a VESDA smoke detection system are installed at the air intake of the air conditioner inside the computer room.
Is this a good practice from an early smoke detection point of view?

  • A. It depends on the type of gas-based fire suppression which will be installed.
  • B. No, it will give a longer reaction time for the smoke detection system and there might also be bypass airflow.
  • C. No, the piping should be installed at the air exhaust of the air conditioner, as there can also be a fire inside the air conditioner itself.
  • D. Yes, as this reduces the amount of piping to be installed in the data center, as all air will go through the air conditioner.

正解:B

解説:
For optimal early smoke detection in a data center, it is crucial that the Very Early Smoke Detection Apparatus (VESDA) system be installed at locations where smoke will be detected as soon as it appears. Positioning the VESDA pipes at the air intake of the air conditioner inside the computer room is not ideal. This placement could result in a delayed detection response and the potential for bypass airflow to occur, which would impede the system's ability to detect smoke effectively.
Detailed Explanation:
When VESDA pipes are installed at the air intake, the detection system relies on the smoke to be drawn into the air conditioning unit before detection can occur. This setup increases the reaction time as the smoke has to travel through the intake and get processed by the air conditioner. Furthermore, bypass airflow-a phenomenon where not all the air containing smoke particles passes through the VESDA pipes-could also delay or even prevent the system from detecting smoke early.
Ideally, VESDA pipes should be positioned where smoke is likely to accumulate first, such as near the ceiling or in the return airflow path to detect smoke at the earliest possible stage. This ensures that the detection system can quickly trigger alarms, providing more time to address potential fire hazards.
EPI Data Center Specialist References:
EPI Data Center Specialist training highlights that smoke detection should prioritize early response capabilities to maximize safety. The preferred installation for VESDA pipes is generally at points where smoke would naturally accumulate, rather than relying on air conditioning intakes where airflow can vary and delay detection. In their course materials, EPI emphasizes minimizing reaction time and reducing the impact of airflow dynamics on smoke detection efficiency.


質問 # 35
The building in which the computer room is housed is required to have a sprinkler system. The building is therefore equipped with a wet pipe system.
What action, if any, should you recommend for the computer room?

  • A. Maintain the current wet pipe system.
  • B. Replace the wet pipe system with a deluge system.
  • C. Replace the wet pipe system with a pre-action system.
  • D. Replace the wet pipe system with a dry pipe system.

正解:C

解説:
In computer rooms, replacing a wet pipe system with a pre-action system is advisable. Pre-action systems provide additional protection by requiring two triggers (e.g., heat and smoke) before water is released, minimizing the risk of accidental discharge and water damage, which is crucial for safeguarding sensitive IT equipment.
Detailed Explanation:
Wet pipe systems contain water in the pipes at all times, which poses a higher risk of accidental discharge. Pre-action systems, however, only fill the pipes with water upon detection of a fire, reducing the risk of water-related damage due to leaks or malfunctions. This approach is considered best practice for environments housing sensitive electronic equipment.
EPI Data Center Specialist References:
EPI advises using pre-action fire suppression in data centers to reduce risks associated with accidental water release, providing a safer and more controlled fire response that better protects critical infrastructure.


質問 # 36
What is a significant difference between a halocarbon gas-based fire suppression system and an inert gas-based fire suppression system?

  • A. Halocarbon gas works on the basis of heat removal and inert gas works on the basis of oxygen reduction.
  • B. Inert gas harms the environment and halocarbon gas does not.
  • C. Halocarbon gas works on the basis of oxygen reduction and inert gas works on the basis of heat removal.
  • D. Inert gas has smaller-sized gas containers than halocarbon gas.

正解:A

解説:
A halocarbon gas-based fire suppression system primarily extinguishes fires through heat absorption. In contrast, an inert gas-based system works by reducing oxygen levels to a point where combustion cannot be sustained. Halocarbon agents, like FM-200, absorb heat from the fire, cooling it down, whereas inert gases, like nitrogen or argon, lower oxygen concentration.
Detailed Explanation:
Halocarbons are effective in quickly cooling flames and are suitable for electronic environments due to their fast action. Inert gases displace oxygen to suppress fires, making them ideal in occupied spaces where human safety can be managed during a fire event due to slower discharge times.
EPI Data Center Specialist References:
EPI training distinguishes between these suppression mechanisms, noting the importance of selecting the correct system based on specific needs like quick response versus oxygen displacement for environments with sensitive equipment.


質問 # 37
What is a potential disadvantage of using water mist as a fire extinguishing system?

  • A. It will rapidly increase the humidity level in the data center, which can cause a potential risk for the operation of the equipment
  • B. It only uses 10% of the water normally used in a water-based fire suppression, which might not be enough to suppress the fire
  • C. It has droplets that are too small (100-120 microns) so it can only be used for small fires
  • D. It extracts oxygen from the air creating a potential risk for humans inside the computer room

正解:A

解説:
A potential disadvantage of using a water mist fire suppression system is that it can rapidly increase the humidity within the data center, which may pose risks to sensitive electronic equipment. Excessive humidity can lead to condensation, which could damage electronics and lead to short circuits or corrosion over time.
Detailed Explanation:
Water mist systems use fine droplets to suppress fires by cooling and displacing heat. However, the moisture generated may raise the humidity level to the point where it exceeds safe operational limits for IT equipment. Therefore, while water mist systems are effective in fire suppression, they may not be ideal in environments where high humidity could damage sensitive equipment.
EPI Data Center Specialist References:
EPI guidelines advise considering the impact of humidity from fire suppression systems, particularly in environments housing electronic equipment. It's essential to weigh the benefits of fire suppression against potential risks to operational equipment when choosing suppression methods.


質問 # 38
The location of a data center is just above the Arctic Circle (North Pole). The outside air temperature is never above 21°C/70°F.
Taking energy efficiency as the highest priority, which cooling system should you recommend?

  • A. Airside economizer
  • B. Standard air conditioning units, as spares might not be readily available
  • C. Any cooling system can be efficient because the outside air temperature will not influence the temperature of the air intake of the ICT equipment
  • D. Waterside economizer

正解:A

解説:
In locations with consistently cold temperatures, such as above the Arctic Circle, an airside economizer is the most energy-efficient cooling solution. Airside economizers use cool outside air to lower indoor temperatures, reducing or even eliminating the need for mechanical cooling. Given the consistently low temperatures, this method maximizes energy efficiency by leveraging natural cooling.
Detailed Explanation:
Airside economizers are ideal in environments where outside temperatures are consistently low. By drawing in and filtering cold outdoor air, they directly cool the indoor environment, thereby reducing energy consumption significantly compared to traditional air conditioning. This cooling approach aligns with energy efficiency goals by minimizing mechanical cooling demands.
EPI Data Center Specialist References:
EPI recommends the use of airside economizers in cold climates to achieve high energy efficiency, as they allow data centers to capitalize on ambient conditions for cooling, aligning with sustainability and cost-saving practices.


質問 # 39
A computer room needs to be fitted out with a gas-based fire suppression system. The computer room will be a high-density data center with about 30% of the racks being closed circuit cooling blade-center racks.
Should the supplier of the fire suppression system be informed on the design of the racks?

  • A. No, cooling and design of racks have no influence on the fire suppression system design.
  • B. Yes, the design of the racks has an influence on the fire suppression system design.
  • C. Only when the rack height obstructs a potential fire suppression release point.
  • D. Only when the racks might block access to the fire panel.

正解:B

解説:
The design and configuration of racks, particularly high-density and closed-circuit cooling racks, directly impact the fire suppression system design. Closed-circuit cooling racks, like blade-center racks, can affect airflow and potentially trap heat, influencing how fire suppression agents are distributed within the space. Therefore, it is essential to inform the fire suppression system supplier about the rack design to ensure effective coverage and proper agent distribution.
Detailed Explanation:
High-density racks can change how smoke and heat travel, which in turn affects fire detection and suppression. Closed racks with built-in cooling can isolate airflow, requiring adjustments in fire suppression design to ensure that suppression agents reach all necessary areas, including within enclosed spaces. The supplier may need to account for these factors to ensure proper protection coverage.
EPI Data Center Specialist References:
The EPI Data Center Specialist training underscores that fire suppression systems must be tailored to the specific environmental characteristics of the data center. The design of racks, particularly high-density configurations, should always be considered to ensure that suppression agents can effectively control a fire, even in contained rack spaces.


質問 # 40
What mainly affects the cooling capacity of a raised floor tile?

  • A. Relative humidity in the computer room, temperature of the cold air, pressure under the raised floor, construction material of the tile
  • B. Percentage of the surface opening, airflow direction of the ICT equipment, temperature difference between the air intake and air exhaust of the ICT equipment, construction material of the tile
  • C. Type of ICT equipment, location of the air conditioner, pressure under the raised floor, allowable temperature in the hot aisle
  • D. Percentage of the surface opening, obstruction of the supporting construction, pressure under the raised floor, damper construction

正解:D

解説:
The cooling capacity of a raised floor tile is primarily influenced by the percentage of surface opening, the obstruction caused by the supporting construction, the pressure under the raised floor, and the damper construction. These factors dictate how much airflow can pass through the tile and how effectively cool air is distributed to the equipment in the data center.
Detailed Explanation:
The percentage of surface opening on a floor tile affects how much air can flow through, with larger openings allowing more airflow. Supporting structures beneath the floor can obstruct airflow, reducing cooling efficiency. Pressure under the raised floor impacts the velocity and volume of air that moves through the tile. Additionally, if dampers are installed, they control the airflow rate, which can be adjusted to meet specific cooling needs for the area.
EPI Data Center Specialist References:
EPI guidance on airflow management under raised floors emphasizes these factors as critical for effective cooling, especially in high-density areas. Ensuring unobstructed and adequate airflow helps maintain consistent cooling across equipment.


質問 # 41
An MCB needs to be installed in the PDU of an air-conditioner unit.
Which breaking curve should you select?

  • A. B-Curve
  • B. C-Curve
  • C. A-Curve
  • D. D-Curve

正解:B

解説:
For an MCB (Miniature Circuit Breaker) in the PDU of an air-conditioning unit, a C-Curve is recommended. C-Curve breakers are suitable for circuits with moderate inrush currents, such as those experienced in air conditioning units. They provide protection against overloads while accommodating the inrush without nuisance tripping.
Detailed Explanation:
C-Curve breakers trip when currents exceed 5 to 10 times the rated current, making them ideal for devices like air conditioners that experience moderate inrush currents upon startup. This characteristic provides a balance between protection and resilience against startup surges, preventing unnecessary trips while safeguarding the circuit.
EPI Data Center Specialist References:
EPI guidance for data center electrical systems specifies that C-Curve breakers are appropriate for equipment with inrush characteristics similar to air conditioning units, as they help prevent operational interruptions caused by typical surges during equipment start-up.


質問 # 42
A data center scores Rated-3 in mechanical, Rated-4 in electrical, and Rated-2 in architectural.
What is the overall Rating of this data center when the Rating is based on the ANSI/TIA-942?

  • A. Rated-4 since that is the highest rating received
  • B. Rated-4 since electrical is more important than mechanical and architectural
  • C. Depends on the Rating scored in telecommunications
  • D. Rated-2 since that is the lowest rating received

正解:D

解説:
According to ANSI/TIA-942 standards, the overall data center rating is determined by the lowest rating among all evaluated categories. Therefore, if a data center is rated 2 in architectural, despite being rated higher in mechanical and electrical, the overall rating is Rated-2. This approach ensures that all aspects meet a minimum standard and prevents a higher rating if any critical area does not comply.
Detailed Explanation:
ANSI/TIA-942 evaluates data centers across several areas, including mechanical, electrical, architectural, and telecommunications. The overall rating reflects the lowest rated category, ensuring that no aspect of the data center's design or operation falls below the specified level. Thus, in this case, the architectural rating of 2 dictates the final rating, ensuring a comprehensive and balanced assessment of reliability and resilience across all aspects.
EPI Data Center Specialist References:
EPI Data Center Specialist training aligns with ANSI/TIA-942, stating that the final rating must reflect the lowest score to ensure comprehensive reliability across all critical infrastructure categories. This avoids overstating the data center's resilience and ensures uniform standards across areas.


質問 # 43
A data center has its own power supply from the public utility and receives chilled water supply from the building owner.
What needs to be taken into consideration when calculating the PUE?

  • A. PUE calculations are not possible in shared buildings
  • B. You will need to take a weight factor of 0.4 for district chilled water into consideration
  • C. You will need to take the value for COP of the chiller plant into consideration
  • D. Nothing, as the chiller plant in the building also uses electrical power

正解:B

解説:
When calculating Power Usage Effectiveness (PUE) in a data center that uses chilled water from an external source, like from a building owner, a weight factor for district chilled water must be applied. This is because PUE calculations aim to measure the energy efficiency of the data center's own operations, and external utilities like district chilled water aren't directly powered by the data center. A weight factor of 0.4 is typically used to account for the energy consumed to produce and deliver the chilled water, reflecting the indirect impact on the data center's total energy consumption.
Detailed Explanation:
PUE is calculated as the ratio of the total facility energy to the IT equipment energy. If the cooling is provided by an external chilled water source, it's necessary to adjust the calculations to accurately reflect the energy impact. By incorporating the 0.4 weight factor, data centers can calculate a more accurate PUE, aligning with standard methods and industry best practices.
EPI Data Center Specialist References:
EPI training on PUE highlights the importance of adjusting for external energy sources, such as district cooling, in the calculations. This ensures that PUE values remain accurate and comparable across different data centers, even when external utilities are used.


質問 # 44
You are allowed to use a calculator for this question. A battery bank is rated at a total capacity of 600 Ah. Calculate how much charging current the rectifier should be able to supply as charging current.

  • A. 30 Amperes
  • B. 12 Amperes
  • C. 80 Amperes
  • D. 60 Amperes

正解:A

解説:
To determine the charging current for a battery bank, a general rule of thumb is that the charging current should be 5% of the total battery capacity. For a battery rated at 600 Ah, this calculation would be:
600 Ah×0.05=30 Amperes600 \, \text{Ah} \times 0.05 = 30 \, \text{Amperes}600Ah×0.05=30Amperes This ensures the battery is charged efficiently without overloading the rectifier or risking battery damage.
Detailed Explanation:
Battery charging current is typically set as a percentage of the battery's capacity to balance effective charging with longevity and safety. A 5% charging rate is standard for lead-acid batteries, which would be 30 Amperes for a 600 Ah battery bank.
EPI Data Center Specialist References:
EPI standards recommend calculating charging currents based on a percentage of the battery capacity to ensure safety and efficiency, aligning with best practices for battery management in data centers.


質問 # 45
The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.
What is the set-up in this data center?

  • A. 2+N+1
  • B. N+N(+1)
  • C. 2(N+1)
  • D. (N+1)-(N+1)

正解:C

解説:
A 2(N+1) configuration implies two independent UPS systems, each with N+1 redundancy. This configuration provides high availability by ensuring that each UPS system can independently support the load with an additional unit for redundancy. Given the 80 kW load, this setup implies that two separate N+1 systems are running, providing reliability and fault tolerance for the data center's power needs.
Detailed Explanation:
The N+1 notation denotes that each system has one additional unit beyond what is needed to carry the load, providing redundancy. With 2(N+1), there are two such setups, ensuring that if one fails, the other can still support the load without interruption, fulfilling high availability requirements.
EPI Data Center Specialist References:
EPI teaches that multiple redundant systems, such as 2(N+1), enhance data center reliability by ensuring that power is maintained even if a failure occurs in one system. This meets the stringent demands for uptime in critical environments.


質問 # 46
A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.
The intake temperature is measured at 25 °C/77 °F and a relative humidity (RH) level of 50%.
The exhaust temperature is 29 °C/84 °F and 45% RH.
The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.
The pressure under the raised floor is approximately 25 Pa/0.1 inch H₂O.
Analyze the situation and indicate what the most likely cause is for this server to crash.

  • A. The raised floor pressure is too low and/or the raised floor tile % opening is not adequate
  • B. No cause could be determined as the CFM/CMH of the air conditioning equipment is not stated
  • C. The exhaust temperature is exceeding the ASHRAE recommended values
  • D. Dust inside the server causing issues with convection-based heat transfer

正解:D

解説:
The server's repeated overheating despite adequate intake and exhaust temperatures suggests that dust buildup inside the server may be impeding heat transfer. Dust accumulation can obstruct airflow within the server, insulate components, and disrupt the convection-based cooling systems that regulate internal temperatures, leading to overheating and potential hardware failures.
Detailed Explanation:
While the intake and exhaust temperatures appear within acceptable ranges, internal dust can reduce airflow and impede cooling efficiency, causing internal components to overheat despite seemingly normal ambient conditions. Regular cleaning and maintenance are critical for preventing dust-related issues, especially in high-powered equipment like a 5kW server.
EPI Data Center Specialist References:
EPI emphasizes regular maintenance to prevent dust buildup in data center equipment. Dust can significantly impact cooling efficiency and lead to overheating, which underlines the importance of routine cleaning for optimal server performance.


質問 # 47
What should be considered when installing overhead data cabling?

  • A. All cabling should make sharp bends directly into the rack to avoid usage of additional space and blocking the airflow on top of the rack.
  • B. To maintain minimum separation from power and ensure that the fire detection and suppression systems are not hindered.
  • C. Copper data cabling should not be placed in metal cable trays.
  • D. Optical fiber cabling should always be positioned on top of the copper cabling in the same cable tray to avoid damage to the sensitive optical fiber.

正解:B

解説:
When installing overhead data cabling, it's crucial to maintain minimum separation from power cables to prevent electromagnetic interference. Additionally, cabling should be arranged so that it does not obstruct fire detection and suppression systems, allowing for proper sensor function and suppression agent dispersion in the event of a fire.
Detailed Explanation:
Separation between power and data cabling minimizes the risk of interference and helps ensure compliance with standards for signal integrity. Proper placement relative to fire suppression systems ensures that any smoke or heat can be effectively detected, and suppression agents can be evenly distributed without obstruction from cabling.
EPI Data Center Specialist References:
EPI guidelines emphasize maintaining adequate separation between power and data cables for safety and performance and ensuring cabling does not interfere with essential safety systems in data centers.


質問 # 48
A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.
Are new floor loading calculations required?

  • A. No, specifications of equipment brought into the data center will already be known during the design of the data center, and therefore the floor will be able to handle it.
  • B. No, as long as the equipment is less than 700 kg/1,500 lbs it will be within the limits.
  • C. Yes, additional floor loading calculations need to be done by the floor manager, which should be verified by the safety engineer.
  • D. Yes, a structural engineer, approved/endorsed by the building owner, should carry out new floor loading calculations.

正解:D

解説:
For heavy equipment, such as a network storage device weighing approximately 600 kg/1,300 lbs, new floor loading calculations are indeed required, particularly since the rack is non-standard. A structural engineer, approved by the building owner, should conduct these calculations to ensure the floor can safely support the new load without risking structural integrity.
Detailed Explanation:
Data centers are designed with specific floor load ratings, which are determined during the design phase based on anticipated equipment. When adding or replacing equipment that is significantly heavy or non-standard, reassessing the floor's capacity is essential to avoid overloading. A structural engineer has the expertise to verify if the existing floor can accommodate the weight and, if not, can recommend reinforcement measures.
This step ensures compliance with safety standards and helps prevent damage to the infrastructure, which could lead to costly repairs or even catastrophic failure in extreme cases.
EPI Data Center Specialist References:
EPI Data Center Specialist training advises that any changes in the data center load, particularly involving non-standard and heavy equipment, warrant a structural assessment. Ensuring compliance with floor load capacity is a critical safety and operational concern, as underscoring data center infrastructure reliability and safety is a priority in EPI's best practices.


質問 # 49
Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:
* Rated power: 30 kVA
* Rectifier input voltage: 400 V/3 phase
* Rectifier input power factor: 0.8
* Battery rated voltage: 384 V
* Number of cells: 192
* End of discharge voltage: 308 V
* Inverter output voltage: 400 V/3 phase
* Inverter output power factor: 0.8
What information is missing to perform the battery calculation?

  • A. UPS efficiency
  • B. Load imbalance on the phases
  • C. Inverter efficiency
  • D. Available battery charging current

正解:A

解説:
To determine the required capacity of the battery bank for the 15-minute runtime at full load, one must know the total power requirement that the battery bank must supply. The specifications provided include most of the necessary details, such as rated power, input voltage, battery voltage, and discharge voltage. However, one critical piece of information is missing: the UPS efficiency.
Detailed Explanation:
In a data center UPS system, the battery bank is designed to supply power for a set duration when there is an input power failure. The UPS efficiency affects the actual power the UPS can deliver to the load compared to the power it draws from the batteries. The efficiency factor is necessary to accurately calculate the required capacity of the battery bank since it determines how much input power is needed from the batteries to supply the load at full capacity. The formula typically used to determine battery capacity involves factoring in UPS efficiency, as it allows you to understand the losses within the UPS system.
If UPS efficiency is not considered, there would be an inaccurate estimation of the actual power needed from the batteries. For instance, if a UPS has 90% efficiency, only 90% of the power drawn from the batteries reaches the load. Without knowing this efficiency, it is not possible to calculate the battery bank size accurately, as you cannot accurately estimate the losses within the UPS itself.
EPI Data Center Specialist References:
According to EPI Data Center Specialist training, understanding the UPS efficiency is essential for battery sizing. Without it, the calculations could lead to either undersizing or oversizing the battery bank, which affects both reliability and cost-effectiveness of the UPS system. The EPI Data Center Specialist course emphasizes that battery sizing must account for all losses within the UPS system, with efficiency being a primary factor in these calculations.


質問 # 50
The noise levels in the data center are approximately 91 dB (A).
Do employers need to take precautions?

  • A. As long as the data is compliant to ISO/IEC 27001 it is acceptable.
  • B. No, anything less than 100 dB (A) is acceptable.
  • C. There are no regulations regarding noise levels inside a building. Regulations only apply to noise pollution outside of the building.
  • D. Yes, since it is mandated by regulations.

正解:D

解説:
In a data center with noise levels of 91 dB (A), employers are indeed required to take precautions to protect personnel, as this level exceeds commonly accepted safety thresholds for occupational noise exposure. Regulations, such as those from the Occupational Safety and Health Administration (OSHA) or similar agencies, mandate specific controls and protections for environments with high noise levels.
Detailed Explanation:
Noise levels above 85 dB (A) typically trigger requirements for hearing conservation programs. At 91 dB (A), steps like providing ear protection, conducting regular noise assessments, and possibly implementing engineering controls to reduce noise should be taken. Extended exposure to such levels can lead to hearing loss, so regulatory compliance ensures both immediate and long-term protection for personnel.
EPI Data Center Specialist References:
EPI guidelines for data center safety address noise exposure as part of the environmental safety measures. EPI recommends adhering to local occupational health regulations, as excessive noise can harm personnel and affect operational efficiency due to potential health hazards.


質問 # 51
It is assumed that EMF shielding material must be installed as the EMF levels coming from the transformer room into the computer room are measured at 100mG. The transformer room is approximately 10 meters away from the computer room and is separated by a corridor. You can assume that no physical issues are present for installing shielding material at any area/location.
Where should you recommend the shielding material to be installed?

  • A. As close as possible to the transformer room
  • B. As close as possible to the computer room
  • C. Shielding is not required to be installed as 100mG is within the acceptable levels for computer rooms
  • D. It does not matter, either close to the transformer room or the computer room is okay as there is no impact to cost or shielding material performance

正解:A

解説:
EMF shielding is most effective when installed close to the source of the EMF, which in this case is the transformer room. Shielding at the source contains the magnetic fields before they spread, minimizing exposure throughout the facility, including the computer room.
Detailed Explanation:
Placing shielding close to the EMF source minimizes the area impacted by electromagnetic interference, as it reduces the distance over which the EMF can spread. Shielding materials near the source can absorb or redirect EMF, providing the most effective reduction of EMF levels in adjacent spaces, like the data center.
EPI Data Center Specialist References:
EPI data center training advises positioning shielding close to the EMF source to contain fields more effectively and reduce interference in critical areas. This method is more efficient and cost-effective, as it limits the spread of EMF from the point of origin.


質問 # 52
You are changing the design of the fire suppression system for your computer room from a halocarbon fire suppression system into an inert-based fire suppression system. Could you use the same formula to calculate the gas content for the gas?

  • A. Yes, as long as you take the difference between the net and gross volume into account.
  • B. No, there is a significant difference in the formula for the different types of fire suppression gases.
  • C. Yes, as long as you use the same units of measure, i.e., kg/m³ or lbs/ft³.
  • D. Yes, as long as you change the 'S' factor of the formula to reflect the gas type used.

正解:B

解説:
The formula used to calculate the gas content differs significantly between halocarbon and inert-based fire suppression systems. Halocarbon systems function by absorbing heat, while inert systems work by reducing oxygen levels. Due to these differences in fire suppression mechanisms, distinct formulas are applied, factoring in the specific properties of each gas type and the required concentration levels.
Detailed Explanation:
Halocarbon systems like FM200 require a formula that accounts for the concentration needed for cooling, while inert gases like nitrogen or argon need a formula that calculates the volume based on oxygen displacement. As the design concentration and characteristics of these gases differ, it's essential to use the correct formula specific to the gas type.
EPI Data Center Specialist References:
EPI recommends consulting the specific design requirements and formulas provided by each gas manufacturer when switching fire suppression systems to ensure the correct amount of gas is deployed for effective fire suppression.


質問 # 53
......


EXIN CDCS 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • データ センターのライフ サイクルと標準: 試験のこのセクションでは、データ センターの専門家のスキルを測定し、計画と設計から実装と廃止まで、データ センターのライフ サイクルに関係するさまざまな段階をカバーします。
トピック 2
  • データ センターの環境配慮と効率: このセクションでは、データ センター運用における環境要因への対応と効率化の促進に関するデータ センター専門家の能力を評価します。データ センター管理者やエンジニアなどの対象者は、エネルギー効率、冷却管理、持続可能な実践を強化する対策を特定して実装する能力がテストされます。
トピック 3
  • データ センターの設計と実装: このモジュールの試験では、データ センターの設計と実装を担当する Exin データ センター プロフェッショナルの知識を評価します。受験者は、スケーラビリティ、冗長性、セキュリティの考慮など、効率的なデータ センター レイアウトを作成するための重要な原則を学習します。

 

最新CDCS試験問題集有効で最新の問題集:https://www.passtest.jp/EXIN/CDCS-shiken.html

検証済みCDCS試験解答合格確定させる:https://drive.google.com/open?id=1URopIvvlDt2WTcWdDr4lV3_A4gcsEIQ_