質問 # 89
The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?
- A. Conduct performance testing.
- B. Evaluate the solution with the sponsor(s).
- C. Conduct user acceptance testing.
- D. Evaluate the solution against the project charter.
正解:C
質問 # 90
The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and and with a lean budget. What should the team do to reduce the risk of rework?
- A. Organize a new elicitation workshop.
- B. Validate the requirements before continuing with development.
- C. Perform a Pareto analysis on the requirements.
- D. Ask the project sponsor to prioritize the requirements
正解:B
質問 # 91
Which tool can be used to analyze how the system responds to various combinations of input conditions with the probability of each outcome?
- A. Functional decomposition
- B. Expected monetary value
- C. Weighted criteria
- D. Decision tree
正解:D
質問 # 92
Which of the following is a method for requirements change control?
- A. Scope analysis
- B. Requirements management
- C. Communication management
- D. Baselining
正解:D
質問 # 93
A business analyst is documenting the acceptance criteria to support a minor modification in a user portal.
The analyst submits the criteria for review, but it is deemed incomplete and returned.
What could have caused the documentation to be returned?
- A. The analyst failed to gather any baseline information.
- B. The analyst utilized user stories as a requirements document tool.
- C. The analyst did not include the scope document in the acceptance criteria paperwork.
- D. The analyst performed forward and backwards traceability.
正解:C
質問 # 94
A business analyst and stakeholders have completed documentation of the acceptance criteria for the requirements of a new vehicle leasing database. A concern is raised that some of the key performance indicators may not validate the desired benefits of the implementation.
What should the business analyst do to ensure that the business need can be validated?
- A. Document a constraint
- B. Document a defect
- C. Document a business rule
- D. Document an assumption
正解:A
質問 # 95
What should the business analyst do during the first steps of a project?
- A. Identify stakeholders and their interests.
- B. Align the sponsor expectations along the project goals.
- C. Evaluate the sources for requirements and prioritize them.
- D. Identify the classes of users and their requirements.
正解:A
解説:
Explanation/Reference: https://www.glowtouch.com/business-analysis-process-flow/
質問 # 96
The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown schedule (WBS) and schedule. However, a key requirement was not implemented in the release Which is a possible reason why the requirement was not implemented?
- A. The scope management plan was not updated with the change.
- B. The requirements traceability matrix was not updated with the change.
- C. The schedule management plan was not updated with the change.
- D. The requirements management plan was not updated with the change.
正解:B
質問 # 97
An organization is in the process of replacing its current system. The business analyst is charged with ensuring that all current connections to other systems remain functional after the upgrade.
What analysis should the business analyst conduct to facilitate a successful migration?
- A. Interface
- B. User interface
- C. Systems
- D. Document
正解:C
解説:
Explanation/Reference:
質問 # 98
A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning. What technique could the business analyst use to help alleviate this concern?
- A. Swimlane diagram
- B. Decomposition model
- C. Business analysis work plan
- D. Context diagram
正解:B
質問 # 99
Which of the following is a properly written requirement statement?
- A. The pot shall be usable in the oven or on the stove.
- B. The pot shall be lightweight and heat up quickly.
- C. The pot shall prominently display the company brand.
- D. The pot shall be manufactured in the following colors: yellow, red, brown, blue.
正解:D
質問 # 100
A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible. Which activity should the business analyst initiate before beginning requirements elicitation?
- A. Define how the solution will be evaluated.
- B. Document how the relevant systems interact.
- C. Prepare the requirements traceability matrix.
- D. Draft a high-level data model.
正解:B
質問 # 101
A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning.
What technique could the business analyst use to help alleviate this concern?
- A. Context diagram
- B. Swimlane diagram
- C. Business analysis work plan
- D. Decomposition model
正解:A
質問 # 102
A business analyst is documenting the acceptance criteria to suppon a minor modification in a user portal The analyst submits the criteria for review, but it is deemed incomplete and returned.
What could have caused the documentation to be returned?
- A. The analyst failed to gather any baseline information.
- B. The analyst utilized user stories as a requirements document tool.
- C. The analyst did not include the scope document in the acceptance criteria paperwork.
- D. The analyst performed forward and backwards traceability.
正解:A
質問 # 103
A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?
- A. Project schedule and cost baseline
- B. Requirements attributes table
- C. Sequence diagram
- D. Requirements traceability matrix
正解:D
解説:
Explanation/Reference: https://opentextbc.ca/projectmanagement/chapter/chapter-9-scope-planning-project- management/
質問 # 104
The business analysts have concluded a requirements elicitation workshop. They now need to define rationale for each requirement. Which of the following pairs of items would be important to include in the rationale?
- A. Stakeholder impact and design decisions
- B. Reasons and assumptions
- C. Product vision and operational relationships
- D. Functional relationships and work breakdown structure code
正解:B
質問 # 105
A business analyst anticipates receiving requirements changes. What should the business analyst do to avoid scope creep?
- A. Meet with the stakeholder and discuss timeline impact.
- B. Define a requirements baseline and implement a change control process.
- C. Implement only the original requirements.
- D. Refer changes to the project manager.
正解:B
質問 # 106
A new product was designed and delivered to the customer. The product exceeded customer expectations but did not meet the baseline budget for the product. What could be the issue?
- A. The sponsor approved the release of the product without reviewing the budget.
- B. Requirements were not properly traced and monitored.
- C. There is no issue since the product exceeded the customer expectations.
- D. Risks identified in the risk management plan were not addressed properly.
正解:A
質問 # 107
A business analyst captures an application's current limitations and consults with end users to identify new features for the next version. What can be used to analyze this information and determine project scope?
- A. Requirements traceability matrix
- B. Root cause analysis
- C. Capability table
- D. As-is process
正解:C
質問 # 108
......