オンライン問題で最適なH12-425_V2.0試験練習問題(最新の468問題) [Q119-Q139]

Share

オンライン問題で最適なH12-425_V2.0試験練習問題(最新の468問題)

練習問題H12-425_V2.0素晴らしい練習用のHCIP-Data Center Facility Deployment V2.0テスト問題

質問 # 119
When UPS5000-E shares a battery pack, the battery capacity parameter of each UPS is set to the total capacity of the entire battery pack.

  • A. TRUE
  • B. FALSE

正解:A


質問 # 120
The access control management function of NETECO cannot modify the door name.

  • A. FALSE
  • B. TRUE

正解:A


質問 # 121
The FusionModule800 does not need to be charged with refrigerant on site within 30m of the connecting pipe.

  • A. False
  • B. True

正解:B


質問 # 122
The output power factor of UPS5000-A-400/500K is ( ), which is suitable for new IT loads and significantly improves the load capacity of the system.

  • A. 0.8
  • B. 0
  • C. 0.95
  • D. 0.9

正解:B


質問 # 123
NetCol5000-c row-level chilled water intelligent temperature control product has a light-load dehumidification function, which can meet the reliable dehumidification under a minimum load of 10%, and avoid the hidden danger of condensation in a low-load and high-mix environment.

  • A. False
  • B. True

正解:B


質問 # 124
One sunroof actuator can drive up to () sunroof solenoid valves at the same time.

  • A. 0
  • B. 1
  • C. 2
  • D. 3

正解:A


質問 # 125
Configure the cables of the UPS. The total current carrying capacity of the cables is greater than the rated current of the UPS to meet the requirements of the project.

  • A. False
  • B. True

正解:B


質問 # 126
Two UPS5000-E (50kVA power modules) 150kVA, rack 1+1 redundancy, in the total input power cabinet, the required total input switch is ()

  • A. 320A
  • B. 630A
  • C. 500A
  • D. 250A

正解:A


質問 # 127
When the UPS is in parallel, the input phase sequence of the main bypass of each UPS needs to be checked, and the output phase sequence of a single pair is not required.

  • A. FALSE
  • B. TRUE

正解:A


質問 # 128
If a large amount of foam appears in the oil sight glass of the NETCOL9000-A compressor for a long time, it means that the degree of overheating is too high.

  • A. FALSE
  • B. TRUE

正解:A


質問 # 129
NetCol8000-A013U 13kW small cooling capacity temperature control product adopts DC inverter compressor.

  • A. False
  • B. True

正解:B


質問 # 130
The power supply architecture supported by the new room and air-cooled series is?

  • A. Dual power supply
  • B. Other
  • C. AB is right
  • D. Circuit Power

正解:C


質問 # 131
FusionModule2000 product configuration framework, which of the following are included? (Multiple choice)

  • A. Cabinet System
  • B. Power supply and distribution system
  • C. Refrigeration system
  • D. Monitoring System

正解:A、B、C、D


質問 # 132
NETCOL5000-C temperature and humidity sensor dial-code setting error may cause:

  • A. The return air temperature or fan speed fluctuates greatly
  • B. The drainage capacity of the equipment is significantly reduced
  • C. Water leakage at the bottom of the device
  • D. The temperature and humidity sensor cannot detect the temperature and humidity

正解:D


質問 # 133
What methods does the FusionModule800 power input support?

  • A. Single or Dual
  • B. Two-way
  • C. One-way

正解:A


質問 # 134
When the differential pressure switch of the air filter of the indoor unit is closed, it means that the filter has too much dust and should be dealt with in time.

  • A. TRUE
  • B. FALSE

正解:A


質問 # 135
Which of the following components can control the lighting in the computer room and control the PAD charging?

  • A. Cabinet collector
  • B. Access Control Actuator
  • C. Actuator
  • D. Smart ETH socket

正解:C


質問 # 136
Through the optional battery inspection instrument, the ( ) of the UPS battery cell can be detected. (Multiple choice)

  • A. Internal resistance
  • B. Frequency
  • C. Voltage
  • D. Battery case temperature

正解:A、C、D


質問 # 137
UPS5000-E can maintain high efficiency in a wide load range and effectively reduce losses. Among them, the efficiency can reach 96% at 40% load, and the efficiency can reach 95% at 20% load. What is the efficiency in ECO mode?

  • A. 97%
  • B. 98%
  • C. 96%
  • D. 99%

正解:D


質問 # 138
Regarding the Fusionlodule2000 wiring, which of the following statements is wrong?

  • A. The power distribution cabinet/integrated UPS cannot be placed at the head of the column
  • B. Cross-channel routing requires installation of cable ladders
  • C. Cross-channel routing is through the control skylight
  • D. The wiring trough supports the separation of strong and weak electricity

正解:C


質問 # 139
......