質問 # 14
When choosing your team's way of working, you need to primarily focus on these goal diagrams.
- A. The Inception related goal diagrams
- B. All of the goal diagrams
- C. The Construction related goal diagrams
- D. The Transition related goal diagrams
- E. The Ongoing related goal diagrams
正解:A
質問 # 15
What is the last step in Ester Derby and Diana Larsen's 5-step retrospective template?
- A. Decide what to do
- B. Celebrate our successes
- C. Create a plan for executing the Improvement items
- D. Close the retrospective
- E. Set the stage
- F. Gather data
正解:D
質問 # 16
True or False: In a complex adaptive system, it is usually better to have one best practice instead of patterns of good practices
- A. False
- B. True
正解:A
質問 # 17
Push is when work is:
- A. Outsourced to a vendor.
- B. Delayed until later.
- C. Expedited to meet a deadline.
- D. Given to people.
正解:D
質問 # 18
What is the primary risk addressed by the stakeholder vision milestone?
- A. That your primary stakeholders agree to your strategy
- B. That the business case for the project is viable
- C. That a release plan for the project is realistic
- D. That your architectural strategy is likely to work
正解:A
質問 # 19
Using Lean thinking, we should be managing
- A. The value stream
- B. By letting people figure out what they need to do
- C. Our people
- D. Each step of the work
正解:A
質問 # 20
True or False: Disciplined agile projects try to maximize the work-in-progress so that it can get more work done
- A. False
- B. True
正解:A
解説:
Disciplined Agile projects do not aim to maximize work-in-progress (WIP). Instead, they aim to minimize WIP to increase efficiency and reduce waste. By limiting WIP, teams can focus on completing tasks faster and delivering value more frequently. This approach is aligned with lean principles, which discourage multitasking and encourage teams to complete work items before starting new ones. Therefore, the statement that disciplined agile projects try to maximize WIP is false. The goal is to optimize the flow of work, not overload the team with too many concurrent tasks.
Top of Form
Bottom of Form
質問 # 21
We do Plan Do Study Act (PDSA) to:
- A. Reflect if we're working on the correct things
- B. Better understand the effectiveness of our actions and to be able to improve our results
- C. Improve our plans
- D. Provide justification when something goes wrong
正解:B
質問 # 22
DA guidelines includes using design thinking. The primary advantage of design thinking is that:
- A. The team can focus on implementation while architects do design
- B. It provides good looking products
- C. It promotes customer empathy and appropriate solutions
- D. It provides out-of-the-box solutions for common problems
正解:C
質問 # 23
True or False: Fulfilling the requirements means that we delighted our customer
- A. False
- B. True
正解:A
質問 # 24
Why is the coordination meeting important for a project team?
- A. It provides a demo of the product to keep everyone up to date.
- B. It allows the stakeholders to see how well the team is working together.
- C. It allows the team to reassess the backlog to meet their needs.
- D. It provides an opportunity for the team to help itself stay in sync.
正解:D
質問 # 25
What is the role of management in Lean?
- A. Create awesome team environments.
- B. Provide minimum viable products to the team.
- C. Ensure documentation is completed
- D. Ensure decisions are not made regionally
正解:A
解説:
In Lean, the role of management is to create an environment where teams can thrive and deliver maximum value. This involves fostering a culture that encourages collaboration, continuous improvement, and innovation. Management is responsible for providing support, removing impediments, and ensuring that teams have the resources they need to be successful. The goal is to empower teams to make decisions, own their processes, and focus on delivering value to customers.
Options A, B, and D do not align with the principles of Lean management. Lean emphasizes minimizing waste (like unnecessary documentation) and does not focus on providing MVPs directly to the team (Option B). Ensuring decisions are not made regionally (Option D) is also not a core role of management in Lean.
References:
* "Lean Thinking: Banish Waste and Create Wealth in Your Corporation," James P. Womack & Daniel
T. Jones.
* PMI's Disciplined Agile Senior Scrum Master (DASSM) curriculum materials.
質問 # 26
What is the maximum frequency of delivering a valuable solution according to the DA principles?
- A. One day
- B. One week
- C. Several times a day
- D. Two weeks
正解:C
質問 # 27
Which characteristic describes a good user story according to the I.N.V.E.S.T. mnemonic?
- A. Incremental
- B. Tangible
- C. Satisfactory
- D. Valuable
正解:D
質問 # 28
A team is about to begin work on a project that will face rapidly changing with releases only every six months or so. The team does not have an agile mindset, and does not want to release often. Which lifecycle should the scrum master select?
- A. Agile
- B. Lean
- C. Program
- D. Traditional
正解:B
質問 # 29
True or False: Fulfilling the requirements means that we delighted our customer
- A. False
- B. True
正解:A
解説:
False: Fulfilling the requirements does not necessarily mean that the customer is delighted. In Disciplined Agile and other Agile frameworks, delighting customers goes beyond merely meeting the stated requirements.
It involves exceeding customer expectations, delivering unexpected value, and providing a positive user experience. A product or service may fulfill the technical or functional requirements but fail to delight if it does not provide an exceptional user experience, is not easy to use, or does not address the underlying needs or desires of the customer comprehensively. The goal is to deliver true value, which often means going beyond the baseline requirements.
質問 # 30
According to the DA manifesto, Transparency is valued over false predictability. This means that:
- A. It is pointless trying to be predictable
- B. Being open is better than pretending that we can predict the future
- C. Stakeholders don't really need to know about the goals
- D. Predictability is achieved only through transparency
正解:B
解説:
According to the Disciplined Agile (DA) manifesto, valuing transparency over false predictability means that it is better to be open and honest about uncertainties and unknowns rather than pretending to have precise control or predictability over future outcomes. This approach builds trust and enables more adaptive and responsive planning. Option A (pointless trying to be predictable) is an oversimplification, Option C (stakeholders don't need to know about the goals) is incorrect, and Option D, while partially true, does not fully capture the intention of the manifesto statement.
Top of Form
Bottom of Form
質問 # 31
What are three attributes of a leader?
- A. Takes risks
- B. Focuses on goals
- C. Inspires trust
- D. Goes with the flow
- E. Assigns tasks
正解:A、B、C
質問 # 32
Push is when work is:
- A. Outsourced to a vendor.
- B. Delayed until later.
- C. Expedited to meet a deadline.
- D. Given to people.
正解:D
解説:
In Disciplined Agile, "Push" refers to a practice where work is assigned to individuals or teams, regardless of their capacity or readiness. This is in contrast to a "Pull" system, where team members pull work when they have the capacity to handle it. A push system can often lead to overloading team members, inefficiencies, and decreased productivity. In Agile practices, a pull-based approach is generally preferred to manage work-in- progress (WIP) and to ensure a sustainable pace for the team.
Options A, C, and D do not accurately represent the concept of "Push" in the context of Disciplined Agile.
References:
* PMI's Disciplined Agile Senior Scrum Master (DASSM) curriculum materials.
* "Choose Your WoW! A Disciplined Agile Delivery Handbook for Optimizing Your Way of Working (WoW)", PMI.
質問 # 33
......
合格保証付きDASSM問題集:https://www.passtest.jp/PMI/DASSM-shiken.html
あなたを合格さすPMI DASSM試験専門はここにある:https://drive.google.com/open?id=11xs11ENy0p_8O5PTkCyj5E_lQ-ZbMhja