質問 # 21
Which two statements are true about Planning Security? (Choose two.)

  • A. Data access sets can be used to limit what a planner can see. based on Items, Organizations, Carriers, Suppliers, and Customers.
  • B. A plan can be set up to be public or private.
  • C. If a plan is set up as private, there is no way to further limit what users see within the plan.
  • D. If a plan is set up as public, there is a way to further limit what users see within the plan.

正解:A、B


質問 # 22
Which four types of supplies can be reserved to a sales order in the inventory? (Choose four.)

  • A. On-hand inventory
  • B. Purchase orders
  • C. Purchase requisitions
  • D. Transfer orders
  • E. Planned Orders
  • F. Work orders

正解:A、B、D、F


質問 # 23
Another planner has previously created a supply plan, but you now need to make some changes so that you can do some 'what-if' analysis. How can you go about duplicating this plan?

  • A. You cannot duplicate a plan that is not owned by you.
  • B. You cannot duplicate plans. You must create a completely new supply plan.
  • C. Manage Plans > Search and select supply plan > Actions > Duplicate.
  • D. Manage Plans > Search and select supply plan > Actions > Edit Plan Options > Select Copy.
  • E. Run process "Duplicate supply plans" with existing plan as parameter.

正解:C


質問 # 24
Which is the proper fulfillment strategy to plan for supply using the appropriate lead times required for processing material at a third party, based on the manufacturing work definition?

  • A. expense destination transfers
  • B. contract manufacturing
  • C. outside processing operations
  • D. drop shipments
  • E. back-to-back orders

正解:C


質問 # 25
In order for Supply and Demand Plans to run successfully, which three Configure Planning Analytic tasks must be completed? (Choose three.)

  • A. Set up Dimension Catalogs
  • B. Run the Configure Dimension Catalog process
  • C. Set up Default Catalogs
  • D. Set up Measure Catalogs
  • E. Set up Hierarchy Attributes
  • F. Set up Levels and Attributes

正解:A、D、F


質問 # 26
As part of the agreement with one of your suppliers, you must always order product by the 100s. For example, if the required supply is 105, you must order 200, if it's 275, you must order 300. Which item attributes will help you achieve this?

  • A. Maximum Order Quantity
  • B. Minimum Order Quantity
  • C. Fixed Order Quantity
  • D. Rounding
  • E. Fixed Lot Size Multiplier

正解:E


質問 # 27
A customer would like to account for the production loss in the supply planning process using the item shrinkage rate planning specification.
Which statement reflects the system behavior to meet this requirement?

  • A. Planning calculates no additional demand but creates the additional required supply based on shrinkage factor.
  • B. Planning process reduces the demand based on shrinkage factor and keeps the supply quantity as is.
  • C. Planning calculation does not support shrinkage functionality.
  • D. Planning calculation creates scrap demand to compensate for loss and maintains supply.

正解:D


質問 # 28
Identify two ways you can track performance against goals when defining measure goals. (Choose two.)

  • A. Value
  • B. Range
  • C. Attribute
  • D. Quantity
  • E. Aggregation
  • F. Specification

正解:A、C


質問 # 29
Which set of transaction types data are uploaded in Contract Manufacturing Collaboration?

  • A. Planned orders, Planned Order Commits
  • B. Component Material Issues, Work-order Completions
  • C. Component Material Issues, Work-order Completions, Shipment Confirmations
  • D. Work-order Completions

正解:B


質問 # 30
During an implementation, customer is in the process of planning supply requirements. Customer also needs to generate forecast and safety stock levels. Which plan type on the plan options should the customer be running?

  • A. Supply Plan
  • B. Demand Plan
  • C. Demand and Supply Plan
  • D. Integrated Plan
  • E. Safety Stock and Forecast Plan

正解:C


質問 # 31
Your client has reviewed all of the current graphs available for the plans, but cannot find one that shows them exactly what they want for the Days of Supply. How can this key performance indicator be added?

  • A. Go to Configure Planning Analytics > Actions > Manage Tables, Graphs, and Analysis Sets, and edit the current 'Days of Supply' graph to meet the client needs.
  • B. Open the plan and go to Actions > Manage Tables, Graphs, and Analysis Sets, and add a new graph with the requested data.
  • C. It is not possible to add new or change the current graphs.
  • D. Open the plan and go to Actions > Manage Tables, Graphs, and Analysis Sets, and edit the current 'Days of Supply' graph to meet the client needs.
  • E. Go to Configure Planning Analytics > Actions > Manage Tables, Graphs, and Analysis Sets, and add a new graph with the requested data.

正解:B


質問 # 32
During Implementation of Planning Central, your client has discovered that no Material Planners have been defined in Manage Material Planners in Planning Central.
In this situation, which three statements are true? (Choose three.)

  • A. Your client has not been assigned the Material Planner role.
  • B. You have not been assigned the Materials Planner role.
  • C. Collect Planning Data has not been run for Material Planners.
  • D. The Planner field will be null for all items.
  • E. Planned Orders will not release successfully.

正解:A、D、E


質問 # 33
Demand planner opens the pre-seeded plan summary of the demand plan and wants to analyze the forecast results. Describe the steps to review and analyze the forecast results.

  • A. Click "Revenue and Margin" tile. Review the "Revenue by Period" graph and pick a specific period. Right-click on a period, click Drill To -> Default Group -> Revenue Analysis to open the table and review the details.
  • B. Click "Forecast Comparison in the thousands" tile. Review "Forecast Comparison by Product Category" graph and pick a product category. Right-click on product category, click Drill To -> Default Group -> Forecast Analysis to open the table and review the details.
  • C. Click "Demand at Risk in thousands" tile. Review "Demand at Risk by Product Category" graph and pick a product category. Right-click on product category, click Drill To -> Default Group -> Demand Analysis to open the table and review the details.
  • D. Click "Revenue and Forecast" tile. Review "Revenue by Period" graph and pick a specific period. Right-click on a period, click Drill To -> Default Group -> Forecast Analysis to open the table and review the details.

正解:B

解説:


質問 # 34
Which four options can be set as a Demand Schedule in Supply Planning plan options? (Choose four.)

  • A. Final Transfer Order Forecast
  • B. Approved Final Bookings Forecast
  • C. Final Shipments Forecast
  • D. Final Bookings Forecast
  • E. Approved Final Shipments Forecast
  • F. Approved Final Transfer Order Forecast

正解:B、C、D、E


質問 # 35
Which four actions does Demand Management enable you to do? (Choose four.)

  • A. Simulate the impact of introducing new products in particular geographic areas.
  • B. Run an unlimited number of forecast simulations to see impacts of changes in the price, running a marketing campaign, shift in weather, demand upside request, and so on.
  • C. Simulate how changes to forecasting models and parameters have an immediate impact on the statistical forecast.
  • D. Simulate changes to the dependent options forecast for build to stock items.
  • E. Perform side-by-side analysis on a multiple number of scenarios, and see the impact on operational and financial objectives.

正解:A、B、C


質問 # 36
How can you deliver a forecast for drop shipments?

  • A. Generate manually using Planning Analytics
  • B. Excel upload using File Based Data Import Process
  • C. Create based on the supplier performance for drop shipment collection
  • D. It cannot be done at this time.
  • E. Create based on the drop shipment or booking history; the ship from will be the drop ship validation organization

正解:E


質問 # 37
Your client has high-priority customers with frequent, small volume orders.
Which two steps should a backlog planner consider if a backlog run does not produce the desired results? (Choose two.)

  • A. Edit the "Pull-in Disabled" demand attribute.
  • B. Edit the "Enforce Current Commit" or "Pull-in Enabled' demand attributes.
  • C. Isolate the problematic customer in its own Backlog Planning run.
  • D. Consider simulation.
  • E. Activate more intricate Demand Priority rules.

正解:B、D


質問 # 38
Your client wants to exclude all of the inventory from the 'Reject' subinventory from only one of their supply plans. What action must be taken to meet this requirement?

  • A. Manage Subinventories > Choose a material status in which 'Nettable' is unchecked
  • B. Manage Plans > Search and select supply plans > 'Organizations and Schedules' tab > 'Supply Schedules' > 'Subinventory Netting' > Deselect 'Reject' subinventory for each organization
  • C. Manage Subinventories > Search and select subinventory > Deselect 'Nettable'
  • D. It is not possible to exclude one subinventory from a particular supply plan.
  • E. Manage Plans > Search and select supply plans > 'Organizations and Schedules' tab > 'Organizations' > 'Subinventory Netting' > Deselect 'Reject' subinventory for each organization

正解:E


質問 # 39
What happens when a demand planner approves a demand plan and then adjusts shipment history and runs demand plan again?

  • A. The approve action makes the Adjusted Shipments Forecast and Adjusted Bookings Forecast measures "not editable." But any subsequent demand plan run can change Final Shipments Forecast and Final Bookings Forecast values.
  • B. The approve action makes the Adjusted Shipments Forecast and Adjusted Bookings Forecast measures "not editable." After a forecast is approved, the Final Shipments Forecast and Final Bookings Forecast measures remain unchanged until the forecast is approved again.
  • C. The approve action takes the data from the two final forecast measures and copies to Approved Final Shipments Forecast and Approved Final Bookings Forecast, respectively. After a forecast is approved, the approved values remain unchanged until the forecast is approved again.
  • D. The approve action takes the data from the two final forecast measures and copies to Approved Final Shipments Forecast and Approved Final Bookings Forecast, respectively. Any subsequent demand plan run can change final shipments or bookings forecast values that will automatically update the approved forecast measures.

正解:C


質問 # 40
As part of the agreement with one of our suppliers, you are supposed to order product by the 100s. But if the required supply is only 149, how many should be planned to purchase, and which item attribute will cause this to happen?

  • A. Planned Order for 100. with Minimum Order Quantity enabled
  • B. Planned Order for 150, with Rounding enabled
  • C. Planned Order for 200. Maximum Order Quantity enabled
  • D. Planned Order for 149, with Fixed Order Quantity enabled
  • E. Planned Order for 200. with Fixed Lot Size Multiplier enabled

正解:E


質問 # 41
A supply plan has just been run that contains a configured item. You notice that the sourcing rules of the base model were used instead of sourcing rules for the configured item. Why did this happen?

  • A. It is not possible to create sourcing rules for the configured item; all configured items always use the same sourcing rules as the base model.
  • B. No sourcing rules have been defined for the configured item.
  • C. No planning percentages were defined at the operation level within the work definition.
  • D. The sourcing rules of the base model had a priority of 1, while the sourcing rules of the configured item had a priority of 2.
  • E. The sourcing rules of the base model overrode the sourcing rules of the configured item.

正解:B


質問 # 42
......

検証済み材料を使うならまず1z0-1066-22テストエンジンを試そう:https://www.passtest.jp/Oracle/1z0-1066-22-shiken.html