質問 # 23
Generally,for safety considerations, waterjetting hose connections use
- A. filters.
- B. a long wand.
- C. a whip-lock device.
- D. an oil/water separator.
正解:C
質問 # 24
The solvent sensitivity/solvent wipe test (ASTM D4752) is used to determine the cute of
- A. inorganic zincs.
- B. urethanes.
- C. powder coatings.
- D. epoxies.
正解:A
質問 # 25
Because a NACE Level 2 Inspector has been trained in specific destructive tests, it is up to the Inspector to decide If and when a destructive test is required.
- A. False
- B. True
正解:A
質問 # 26
The main reason dehumidification Is used during coating operations is to
- A. control the environment
- B. avoid repetitive blasting/coating operations.
- C. reduce the possibility of missing the recoat window.
- D. allow the contractor to guarantee the completion date.
正解:A
質問 # 27
NACE Level 2 Inspectors have been authorized to perform:
- A. All types of inspection without supervision
- B. Visual inspection and Non-destructive testing
- C. Visual inspection only
- D. Visual inspection, Non-Destructive and Destructive testing
正解:D
質問 # 28
When performing testing in accordance with ASTM D 2583 the Inspector may observe:
- A. Adhesion failure
- B. Cohesion failure
- C. Glue failure
- D. Cold flow or creep
正解:D
質問 # 29
When NACE/SSPC W31 is referenced; what type of equipment would the Inspector expect to see on the job:
- A. Power Tools
- B. Abrasive Blasting Equipment
- C. Water Jetting Equipment
- D. Scarifiers
正解:C
質問 # 30
When environmental enclosures ate being used an inspector needs to be concerned about:
- A. Air changes
- B. Lighting
- C. a), b), and c)
- D. Structural integrity
正解:C
質問 # 31
An Inspection and Test Plan is required when:
- A. It is always required
- B. When the Owner specifies one
- C. When the Inspector requests one
- D. When the Coating Applicator requests one
正解:A
質問 # 32
You are theNACE Coating Inspector on a tank lining project and are asked to perform ahigh voltage holiday test after thecoating applicators have completed their final repairs. After meeting all the confined space entry permit you enter the tank and notice a very strong odor of solvent.
Your first course or action should be to:
- A. Exit the tank and document the incident in your dally report
- B. Don your air supplied respirator and continue the testing
- C. Exit the tank and Immediately and report the problem to the nearest safety supervisor
- D. Investigate to find the source of the odor
正解:C
質問 # 33
Coating Surveys are legally required:
- A. On high pressure gas lines and fireproofed structures
- B. On food and beverage vessels and can linings
- C. On water tanks and potable water pipelines
- D. On commercial marine vessels and offshore platforms
正解:D
質問 # 34
You are NACE Level 2 Inspector working on a tank lining job where a mobile centrifugal blast unit is being used to blast the tank floor to a NACE No. 1/SSPC SP 5. The Contractor has completed his final blast and has called for a hold point inspection. This is the 1st time you have seen field based centrifugal blast cleaning.
You observe what appears to be staining on the substrate however the Contractor assures you this is normal when using centrifugal blast units and what you are seeing is what is defined In the standard as an acceptable variation in appearance.
Your FIRST preferred course of action Is to:
- A. Shut the job down
- B. Review the standard with the Contractor and re-inspect the floor
- C. Request that the Contractor re-blast the floor
- D. Call your supervisor
正解:B
質問 # 35
When measuring the Dry Film Thickness of liquid coatings applied to galvanized ferrous substrates the most commonly used instrument Is the:
- A. Tooke Gauge
- B. Magnetic Gauge
- C. Eddy Current Gauge
- D. Ultra Sonic DFT Gauge
正解:D
質問 # 36
You have Just received your NACE CIP Level 2 certification when you are asked to supervise a team of uncertified field pipeline inspectors.
Your FIRST preferred course of action is to:
- A. Meet with the prospective employer to determine the scope of your role
- B. Review the NACE Attestation prior to making a decision
- C. Advise the prospective employer that you cannot accept the position
- D. Accept the assignment without hesitation
正解:A
質問 # 37
Which concrete smoothing technique Involves scrubbing a mixture of cement mortal over the concrete surface using a cement sack, gunny sack, or sponge rubber float?
- A. Stoning
- B. High-pressure water washing
- C. Acid etching
- D. Sacking
正解:D
質問 # 38
In powder coatings, when the particles of powder begin to flow but are not fully liquid, they are in what stage?
- A. Cure stage
- B. Wetting stage
- C. Flow stage
- D. Getstage
正解:C
質問 # 39
You are the NACE Coating Inspector ona tank lining project where desiccant dehumidificationis being used.
Since the first shift ofabrasive Wasting your readings have indicated relative humidity below 40%; however on the second shift of coating application your readings are indicting 80%.
Your FIRST preferred course of action is to:
- A. Check to see if the dehumidification equipment is operating correctly
- B. Call your supervisor
- C. Document the readings at the end of the shift
- D. Advise the coating applicator supervisor of your readings
正解:D
質問 # 40
......