質問 # 44
A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

  • A. Cultural differences
  • B. Technological factors
  • C. Resource allocation
  • D. Communication security

正解:A

解説:
Explanation
Cultural differences are the most important aspect for the project manager to consider when assigned to a multinational project with team members from different continents. Cultural differences refer to the variations in beliefs, values, norms, behaviors, customs, and communication styles among people from different countries or regions. Cultural differences can affect how team members interact, communicate, collaborate, negotiate, make decisions, solve problems, manage conflicts, and perform tasks. The project manager should be aware of and respect the cultural differences among team members and foster a positive and inclusive team culture that leverages diversity and promotes trust and cooperation.


質問 # 45
During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

  • A. Validate the business case.
  • B. Create a project schedule
  • C. Update the project charter.
  • D. Determine budget constraints.

正解:C

解説:
Explanation
Update the project charter. Updating the project charter would be the next step for the project manager after identifying the project team during the project initiation phase. A project charter is a document that formally authorizes a project and defines its purpose, scope, objectives, deliverables, milestones, roles and responsibilities, assumptions, constraints, risks, budget, and timeline. A project charter can help to align the expectations and interests of all stakeholders involved in a project and provide direction and guidance for planning and executing the project.


質問 # 46
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

  • A. Update the work breakdown structure.
  • B. Review the backlog.
  • C. Establish the resource pool.
  • D. Seek baseline approval.

正解:D

解説:
The next step in the process after defining tasks, durations, resources, and costs is to seek baseline approval. A baseline is an approved version of a project plan that serves as a reference point for measuring progress and performance throughout the project lifecycle. A baseline typically includes scope, schedule, cost, quality, and risk parameters. Seeking baseline approval involves presenting the project plan to key stakeholders and obtaining their formal agreement on the project objectives and deliverables. Baseline approval can help to establish clear expectations, avoid scope creep, and facilitate change control during project execution.
The NEXT step after defining tasks, durations, resources, and costs during the planning phase is to seek baseline approval. Baseline approval involves finalizing the project plan and gaining approval from stakeholders, establishing the plan as the baseline for the project's performance. References: CompTIA Project+ Study Guide Section 3.4.1


質問 # 47
A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

  • A. Decline because it is not included in the project scope.
  • B. Assess the impact of the request and create a change request
  • C. Revise the baseline of the project plan by adding the new requirements.
  • D. Create new functional and non-functional requirements for mobile devices.

正解:B

解説:
Explanation
Assess the impact of the request and create a change request. The project manager should assess the impact of the request and create a change request in response to the stakeholder asking to add mobile device functionality to a project that is on track to be completed under budget and ahead of schedule. A change request is a document that formally proposes and records a modification or addition to some aspect of a project, such as scope, schedule, cost, quality, or resources. A change request can help to communicate and justify the need and rationale for the change and its implications on the project objectives and deliverables. A change request also helps to initiate the change control process, which involves reviewing, approving, implementing, and monitoring the change12


質問 # 48
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

  • A. Fixed-price contract
  • B. Time and materials contract
  • C. Cost-plus agreement
  • D. Master service agreement
  • E. Statement of work

正解:B

解説:
Explanation
The project manager should put in place a time and materials contract before work begins for a third party that needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. A time and materials contract is a type of contract where the buyer pays the seller based on the actual time spent and materials used during the project. A time and materials contract is suitable for projects that have uncertain or variable scope, duration, or cost. A time and materials contract can provide flexibility and adaptability for both parties and allow them to adjust to changing requirements or circumstances.


質問 # 49
An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?

  • A. The ticket system provided access by default without any approval.
  • B. The project manager did not perform proper project planning.
  • C. Sensitive data was incorrectly classified during the audit process.
  • D. The system is lacking proper access controls.

正解:D

解説:
Explanation
The system is lacking proper access controls if a third-party vendor was able to see secured project information in a recently implemented system that resulted in a fine for the organization. Access controls are security mechanisms that regulate who or what can view, use, or modify data or resources in a system or network. Access controls typically involve authentication and authorization processes that verify the identity and permissions of users or devices before granting them access. Access controls can help to protect data confidentiality, integrity, and availability and prevent unauthorized access, misuse, or theft12


質問 # 50
A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

  • A. Conduct a retrospective.
  • B. Perform a gap analysis.
  • C. Review existing artifacts.
  • D. Collate the lessons learned.

正解:C

解説:
The project manager should review existing artifacts to get an understanding of the purpose of the project. Existing artifacts are documents or records that provide information about the project background, context, scope, objectives, requirements, stakeholders, and deliverables. They may include documents such as project proposal, project charter, business case, feasibility study, statement of work (SOW), or contract. Reviewing existing artifacts can help to clarify the project vision and expectations and provide a basis for planning and executing the project.


質問 # 51
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

  • A. Change control log
  • B. Gantt chart
  • C. Issue log
  • D. Milestone chart

正解:A

解説:
The project manager should use a change control log to document the effects of the hurricane delay on the project. A change control log is a tool that records and tracks any changes that occur during the project lifecycle. It usually includes information such as change ID, description, impact, status, approval, and resolution. A change control log can help to monitor and manage the changes that affect the project scope, schedule, cost, quality, or resources and ensure that they are aligned with the project objectives and stakeholder expectations.


質問 # 52
A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

  • A. Decision board
  • B. Dashboard
  • C. Task board
  • D. Whiteboard

正解:C

解説:
A task board is a visual tool that displays team progress for stand-up meetings. A task board usually consists of columns that represent different stages or statuses of tasks, such as to do, in progress, done, or blocked. Each task is represented by a card or sticky note that can be moved across the columns as the task progresses. A task board can help to facilitate communication, collaboration, and transparency among team members and stakeholders. It can also help to track and manage work flow, prioritize tasks, identify bottlenecks, and resolve issues3


質問 # 53
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

  • A. SOW
  • B. WBS
  • C. RFI
  • D. RACI

正解:D

解説:
The RACI (Responsible, Accountable, Consulted, Informed) matrix is used to document which resources are responsible for which tasks. The RACI matrix is a tool that helps to clarify roles and responsibilities on a project. It assigns a level of responsibility to each resource involved in the project. References: CompTIA Project+ Study Guide Section 3.4.
The project manager should use a RACI matrix to document which resources are responsible for which tasks. A RACI matrix is a type of responsibility assignment matrix (RAM) that plots the roles and responsibilities of resources on a project team. RACI stands for Responsible, Accountable, Consulted, and Informed. A RACI matrix can help to clarify who does what on a project, avoid confusion and duplication of work, and improve communication and collaboration among team members.


質問 # 54
An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions would be BEST?

  • A. Electronic document and record management systems
  • B. Customer relationship management and databases
  • C. Content management and financial systems
  • D. Enterprise resource planning and end user applications

正解:A

解説:
Explanation
Electronic document and record management systems would be the best software solutions to help an institution manage the internal flow for formally responding in writing to citizens' complaints. Electronic document and record management systems are software systems thathelp organizations create, store, organize, manage, track, and distribute electronic documents and records. Electronic document and record management systems can help to improve efficiency, productivity, collaboration, compliance, and security of document and record management processes and workflows


質問 # 55
Which of the following offers administrators more direct control over operating systems?

  • A. Functions as a service
  • B. Software as a service
  • C. Infrastructure as a service
  • D. Platform as a service

正解:C

解説:
Explanation
Infrastructure as a service (IaaS) offers administrators more direct control over operating systems than other cloud service models. IaaS is a type of cloud computing service that provides virtualized computing resources such as servers, storage, network, and operating systems over the internet. IaaS allows users to rent or lease infrastructure resources on demand and pay only for what they use. IaaS gives users more flexibility and control over their infrastructure resources and enables them to configure, manage, and customize their operating systems according to their needs and preferences


質問 # 56
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

  • A. User acceptance testing
  • B. Unit testing
  • C. Smoke testing
  • D. Regression testing

正解:D

解説:
Explanation
Regression testing is a type of testing that is done on an existing system to ensure that the previous functionality still works after a change has been made. Regression testing is a process of retesting or verifying that a software system or application still performs as expected after it has been modified or updated with new features, bug fixes, patches, etc. Regression testing can help to detect any errors or defects that may have been introduced by the change and ensure that no functionality has been broken or degraded.


質問 # 57
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

  • A. Validate against the scope statement and ask for sign-off.
  • B. Run a control chart to ensure the quality of the deliverables.
  • C. Review the risk register and close up residual risks.
  • D. Start the training and handoff for the operations team.

正解:A

解説:
The project manager should validate against the scope statement and ask for sign-off after a system was implemented and testing was successfully completed. The scope statement is a document that defines and documents the project scope, objectives, deliverables, requirements, assumptions, and constraints. The scope statement can help to establish a common understanding and agreement between the project manager and the stakeholders on what the project aims to achieve and deliver. Validating against the scope statement means checking whether the project deliverables meet the agreed-upon scope criteria and quality standards. Asking for sign-off means requesting formal acceptance and approval of the project deliverables from the stakeholders.


質問 # 58
In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

  • A. Obtain the final report from release management.
  • B. Notify the functional manager that resources are released.
  • C. Allocate resources in a different project
  • D. Assemble a new project with existing resources.

正解:B

解説:
Explanation
The project manager should notify the functional manager that resources are released after completing a project successfully in a functional organization. A functional organization is a type of organizational structure where employees are grouped by their functions or specialties, such as finance, marketing, or engineering. In a functional organization, the functional manager has more authority and control over the resources than the project manager. Therefore, the project manager should inform the functional manager when the resources are no longer needed for the project and can be reassigned to other tasks or projects.


質問 # 59
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

  • A. Non-disclosure agreement
  • B. Request for information
  • C. Statement of work
  • D. Memorandum of understanding

正解:B

解説:
Explanation
The statement of work (SOW) would be the next document that a project manager should update once the need to procure goods and/or services is identified. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.


質問 # 60
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

  • A. Resources
  • B. Critical paths
  • C. Milestones
  • D. Work breakdown structures

正解:C

解説:
Explanation
Milestones are activities with zero duration that are added to a project schedule by a project manager.
Milestones are significant events or achievements in a project that mark the completion of a phase, deliverable, or task. Milestones can help to track and measure the progress and performance of a project and communicate it to stakeholders.