質問 # 86
Which of the following sources of information would be most appropriate for a company to use to measure and monitor customer satisfaction?
- A. Software quality's attributes that have been classified as "critical" by key customers
- B. Feedback from customers regarding reliability data, especially concerning increases in the mean time to failure in the company's products
- C. Comprehensive surveys covering all aspects of the customer experience
- D. Market analysis reports that incorporate customer preferences when comparing the features of the company's products with those of its key competitors
正解:C
解説:
Comprehensive surveys covering all aspects of the customer experience are the most appropriate source of information for a company to use to measure and monitor customer satisfaction. These surveys provide a holistic view of the customer's interactions with the product and service, covering various dimensions such as product quality, usability, support, and overall satisfaction. By gathering detailed feedback across these areas, companies can identify strengths and areas for improvement, ensuring that customer satisfaction is accurately measured and monitored.References:
* Hill, Nigel, Roche, Greg, and Allen, Rachel."Customer Satisfaction: The Customer Experience Through the Customer's Eyes." Cogent Publishing, 2007.
* ISO 10004:2012, Quality management - Customer satisfaction - Guidelines for monitoring and measuring.
質問 # 87
Which of the following statements describes the output from a code coverage monitor?
- A. Lines of code are executed in the correct order.
- B. Lines of code and branches or paths have been executed.
- C. Data types are manipulated by the correct modules.
- D. Calculated values are documented, including where the calculations were made.
正解:B
解説:
A code coverage monitor measures the extent to which the source code of a program is executed during testing. The primary output from a code coverage monitor is an indication of which lines of code, branches, or paths have been executed. This helps in identifying untested parts of a codebase, ensuring more comprehensive testing, and improving overall software quality.
References:
* "Effective Software Testing: 50 Specific Ways to Improve Your Testing" by Elfriede Dustin
* IEEE Standard 829-2008 for Software and System Test Documentation
質問 # 88
Which of the following activities generally requires the most effort after the release of a software system?
- A. Performing maintenance
- B. Training the users
- C. Revising documentation
- D. Customer acceptance
正解:A
解説:
After a software system is released, maintenance generally requires the most effort over the software lifecycle. Maintenance includes corrective work to fix defects, adaptive work to support changed environments, perfective work to improve functionality or performance, and preventive work to reduce future problems. Software often remains in use for years, and user needs, operating systems, interfaces, regulations, security threats, and business processes continue to change. Customer acceptance usually occurs before final release or deployment completion. Revising documentation and training users are important support activities, but they are smaller in scope than ongoing maintenance. In software quality engineering, post-release maintenance often consumes a large portion of total lifecycle cost and effort. Therefore, performing maintenance is the correct answer.
質問 # 89
Which of the following items is an appropriate topic to be discussed in a daily scrum meeting?
- A. A change in the product roadmap which impacts current future releases
- B. An impediment one of the team member was facing yesterday
- C. A product backlog item from the current sprint and move it to future sprints
- D. The list of all product backlog items that need to be addressed in current sprint
正解:B
解説:
The daily scrum meeting (or daily stand-up) is a time-boxed event in agile methodologies designed for the team to synchronize activities and discuss any impediments.
* Three Questions: During the daily scrum, team members typically address three questions: What did I do yesterday? What will I do today? Are there any impediments in my way?
* Focus on Impediments: Discussing impediments is crucial as it allows the team to identify and address obstacles that may hinder progress, facilitating prompt resolution.
* Short-Term Planning: The daily scrum focuses on the immediate tasks and issues, not on long-term planning or changes to the product roadmap.
質問 # 90
Which of the following statements best describes the purpose of a matrix diagram?
- A. It shows the size of gaps between current and ideal performance areas.
- B. It shows which problems offer the greatest potential for improvement.
- C. It allows a systematic comparison between sets of information.
- D. It allows a team to rank priorities and then quickly come to a consensus.
正解:C
解説:
A matrix diagram is a quality tool used to show relationships between two or more sets of information. In software quality engineering, it can compare requirements to test cases, defects to root causes, risks to controls, stakeholders to requirements, or process steps to responsibilities. The purpose is to make relationships visible so teams can analyze coverage, dependencies, gaps, and strength of association. Ranking priorities and reaching consensus is more closely related to prioritization tools or nominal group techniques.
Showing problems with the greatest improvement potential is often done with Pareto analysis. Showing gaps between current and desired performance may involve gap analysis. Therefore, the matrix diagram's main purpose is systematic comparison between information sets.
質問 # 91
Which of the following baselines is typically established after completion and approval of system requirements?
- A. Functional
- B. Allocated
- C. Product
- D. Development
正解:A
解説:
The functional baseline is typically established after the completion and approval of system requirements. This baseline includes the functional requirements and specifications that describe what the system is supposed to do. It serves as a reference point for further development and testing, ensuring that all subsequent work aligns with the agreed-upon functional requirements.
質問 # 92
One reason for seeding errors into a program before testing begins is to
- A. determine whether the error exists in the program or the test case
- B. identify gaps in the program specifications document
- C. determine the percentage of total errors the test can find
- D. assess how well the test handles a program with a large number of errors
正解:C
解説:
Error seeding is a technique used to estimate test effectiveness and the number of remaining defects. Known errors are intentionally inserted into the software before testing. After testing, the percentage of seeded errors found is compared with the number of real errors found. If testers find a high percentage of seeded errors, there is more confidence that the test process is effective. If many seeded errors are missed, the testing approach may be weak. The goal is not to determine whether a specific error is in the program or test case, nor to overload the program with many errors. It also does not directly identify specification gaps. The main purpose is estimating the percentage of total errors testing can detect.
質問 # 93
Which of the following must be included in a software defect report to track detection effectiveness?
- A. Root cause of the defect
- B. Who found the defect
- C. Software component containing the defect
- D. The phase the defect was introduced
正解:D
解説:
Purpose of Tracking Defects:The goal is to understand not only where defects are found but also where they originate. This allows for better prevention strategies and process improvements.
Importance of Defect Introduction Phase:Knowing the phase where the defect was introduced helps in pinpointing weak areas in the development process. This can lead to targeted improvements.
Effectiveness in Detection:To effectively track detection efficiency, it is crucial to map defects back to their introduction phase to analyze and optimize earlier phases for defect prevention.
質問 # 94
Which of the following statements is true about component reuse?
- A. The more a developer knows about the implementation, the more reusable a component will be.
- B. Development costs are improved by reusable components.
- C. Information-hiding impedes the development of reusable components.
- D. Modifying a previously used module is an example of module reuse.
正解:B
解説:
Component reuse in software development offers several advantages, one of the primary being the improvement of development costs. This means that:
* Cost Efficiency:Reusing components reduces the need for developing new modules from scratch, saving time and resources.
* Consistency and Quality:Reused components are typically well-tested and reliable, enhancing the overall quality of the software.
Reusable components help streamline the development process, leading to faster and more cost-effective software production.
References:
* Software Engineering: A Practitioner's Approach by Roger S. Pressman
* Component-Based Software Engineering: Putting the Pieces Together by George T. Heineman and William T. Councill
質問 # 95
Which of the following steps comes first during release planning for waterfall-type projects?
- A. Select the set of requirements that will be included in the release.
- B. Determine which problems will be corrected in the next release.
- C. Confirm the implemented software meets the specified requirements.
- D. Define the scope of the software being developed.
正解:D
解説:
Scope Definition:In the waterfall model, the first step in release planning is to define the scope of the software. This involves understanding what the software is supposed to do, the boundaries of the project, and the major features and functionalities to be included.
Importance of Scope:Defining the scope provides a clear understanding and agreement among stakeholders about what the project will deliver, preventing scope creep and ensuring all parties are aligned.
References:Software Engineering Body of Knowledge (SWEBOK) and IEEE standards emphasize the importance of scope definition as an initial phase in project planning.
質問 # 96
Which of the following describes when a test plan should be changed?
- A. After each code review
- B. When the configuration management tool is updated
- C. After product stability has been assessed
- D. After changes to the design specifications
正解:D
解説:
A test plan should be changed after changes to the design specifications. This ensures that the tests remain relevant and accurately reflect the new design and functionality of the software. Keeping the test plan updated with design changes helps ensure comprehensive test coverage and alignment with the project ' s requirements.
Reference: IEEE 829-2008 (IEEE Standard for Software and System Test Documentation), which outlines the importance of maintaining an up-to-date test plan to reflect changes in design and requirements.
質問 # 97
A sprint started with 354 requirements. As the sprint progressed, 14 requirements were introduced, 6 requirements were removed, and 28 requirements were changed. What was the requirements volatility for this sprint?
- A. 13.5%
- B. 11.9%
- C. 8.8%
- D. 15.7%
正解:A
解説:
Requirements volatility is calculated as the percentage of change in the total number of requirements during a sprint. The formula to calculate volatility is:
Volatility=(Introduced+Removed+Changed)Initial×100\text{Volatility} = \frac{(\text{Introduced} +
\text{Removed} + \text{Changed})}{\text{Initial}} \times
100Volatility=Initial(Introduced+Removed+Changed)×100
Using the given data:
* Initial requirements = 354
* Introduced = 14
* Removed = 6
* Changed = 28
Volatility=(14+6+28)354×10013.5%\text{Volatility} = \frac{(14 + 6 + 28)}{354} \times 100 \approx
13.5\%Volatility=354(14+6+28)×10013.5%
質問 # 98
Which of the following aspects of information systems is disaster recovery primarily concerned with protecting?
- A. Confidentiality
- B. Integrity
- C. Availability
- D. Authorization
正解:C
解説:
Disaster recovery is primarily concerned with ensuring that information systems can continue to operate or be quickly restored to operation after a disaster.
* Objective: The main objective of disaster recovery is to ensure that the system remains available, or can be quickly made available, after an interruption or disaster.
* Key Elements: This involves having backups, redundant systems, and recovery plans that can be quickly executed to restore system functionality.
* Focus on Availability: While integrity and confidentiality are also important, the immediate concern of disaster recovery is to ensure that systems are available to users to maintain business continuity.
質問 # 99
Which of the following best describes a process audit?
- A. An internal review of the quality policy
- B. An investigation of the quality management system
- C. The evaluation of established procedures
- D. The verification that product characteristics are met
正解:C
解説:
A process audit evaluates whether established procedures, methods, and work instructions are being followed and whether they are effective for producing the required software quality outcomes. In software quality engineering, process audits focus on development, testing, configuration management, defect reporting, reviews, and other defined lifecycle activities. The purpose is to verify conformance to approved processes and identify opportunities for corrective action or improvement. An investigation of the entire quality management system is more closely related to a system audit. Verification that product characteristics are met describes a product audit. Reviewing the quality policy alone is too narrow. Therefore, the best description of a process audit is the evaluation of established procedures.
質問 # 100
An organization uses the plan-do-check-act (PDCA) cycle to align its processes to an international quality standard, which of the following activities would be performed during the "act" step?
- A. Performing internal audits of the system
- B. Identifying actions to be performed during the pilot
- C. Documenting the problems to present to management
- D. Making quality system revisions
正解:D
解説:
PDCA Cycle Overview:The Plan-Do-Check-Act (PDCA) cycle is a continuous improvement process used to align processes with quality standards.
Act Phase:In the 'Act' step, the organization acts on the findings from the 'Check' step to implement changes that improve the process. This typically involves making revisions to the quality system.
Quality Improvements:By making revisions based on the findings from audits and performance evaluations, the organization continuously improves its processes and aligns them better with international standards.
質問 # 101
Under design control, the design phase should proceed until
- A. system elements of the smallest structure are defined and specified
- B. every possible design variation has been explored
- C. the developers understand the level of work expected
- D. the allocated time for system design has been reached
正解:A
解説:
In the design control phase of software development, it is critical to ensure that the design phase proceeds until system elements of the smallest structure are defined and specified. This ensures that all components of the system are thoroughly planned and documented, which helps in minimizing errors and misunderstandings later in the development process. Detailed design specifications provide a clear roadmap for developers and facilitate better quality control and testing.
References:
* "Software Engineering: A Practitioner's Approach" by Roger S. Pressman
* IEEE Standard 1016-2009 for Information Technology-Systems Design
質問 # 102
The benefits of having the data owner collect the data is that data owners
- A. have in-depth knowledge of the data: therefore, the data they collect will be bias-free
- B. know which are the best statistical tools and techniques for data analysis
- C. are more likely to detect anomalies in the data as it is being collected., which helps increase accuracy
- D. can process data as it is being created, which increases collection speed
正解:C
解説:
Data owners are typically individuals or groups who have deep understanding and control over a specific set of data. They are well-versed in the context, nuances, and expected patterns of the data they manage. This in-depth knowledge allows them to:
* Detect Anomalies: Because data owners understand what the data should look like under normal circumstances, they are more likely to spot inconsistencies or errors as data is being collected.
* Increase Accuracy: By catching and correcting anomalies early in the data collection process, data owners can ensure that the data remains accurate and reliable.
* Immediate Action: Anomalies can be addressed on the spot, reducing the time and effort required for post-collection data cleaning and correction.
質問 # 103
Who is responsible for walking through business scenarios to determine the completeness of the defined requirements?
- A. The quality function representative
- B. The product developer
- C. The analyst
- D. The tester
正解:C
解説:
The analyst is responsible for working through business scenarios to determine whether the defined requirements are complete, consistent, understandable, and aligned with stakeholder needs. In requirements engineering, analysts elicit, document, analyze, and validate requirements by examining user workflows, business rules, use cases, scenarios, and expected outcomes. Walking through scenarios helps reveal missing requirements, unclear assumptions, exception paths, interface needs, and conflicting stakeholder expectations.
Testers may later use scenarios to design validation tests, and quality representatives may help verify requirement quality. Product developers may review feasibility and design implications. However, the primary responsibility for confirming requirement completeness through business scenario analysis belongs to the analyst because that role owns requirements analysis and stakeholder interpretation.
質問 # 104
The Equity Theory states that for rewards to be motivational they must be distributed
- A. at key milestones
- B. as deserved
- C. based on seniority
- D. based on profit
正解:B
解説:
Equity Theory, proposed by John Stacey Adams, posits that employees are motivated when they perceive that their efforts and rewards are fair compared to others. Here ' s a detailed explanation:
* Equity Theory Overview : This theory suggests that individuals compare their job inputs (effort, skill, experience) and outputs (salary, recognition) with those of others.
* Perceived Fairness : Employees are motivated when they believe that their rewards are proportional to their contributions compared to others.
* Motivation through Fair Distribution : Fair and deserved rewards reduce feelings of inequity and dissatisfaction, leading to higher motivation and performance.
* Implications in the Workplace : Ensuring rewards are as deserved helps in maintaining morale and reducing turnover.
:
" Work and Motivation " by Victor Vroom.
" Motivation and Work Behavior " by Richard M. Steers and Lyman W. Porter.
質問 # 105
Which of the following metrics is included in earned value management?
- A. The budgeted cost of work performed
- B. The actual cost of outstanding work
- C. The actual cost of scheduled work
- D. The actual delay in project schedule
正解:A
解説:
Earned Value Management (EVM) includes several key metrics, one of which is the budgeted cost of work performed (BCWP). Here's a detailed explanation:
* Earned Value (EV) : Represents the value of work actually performed in terms of the budget assigned for that work.
* Planned Value (PV) : The budgeted cost for the work planned/scheduled.
* Actual Cost (AC) : The actual cost incurred for the work performed.
* Performance Measurement : BCWP is crucial for comparing planned work with actual progress and costs, helping in performance measurement and project forecasting.
:
" Project Management: A Systems Approach to Planning, Scheduling, and Controlling " by Harold Kerzner.
PMI's " A Guide to the Project Management Body of Knowledge (PMBOK Guide) " .
質問 # 106
The following graph depicts errors per 1,000 lines of code (KLOC) for modules S, T, U, and V.

The program manager should be most concerned about which module?
- A. T
- B. U
- C. S
- D. V
正解:B
解説:
Error Analysis: Module U has the highest total number of errors per KLOC, with significant issues in header comments (H), commented out code (C), and data initialization errors (D).
Quality Concern: The high error rate indicates potential underlying quality issues in Module U that need to be addressed to improve overall software quality.
Prioritization: According to defect prioritization guidelines, modules with the highest error rates should be investigated and corrected first to mitigate risks and improve reliability.
質問 # 107
Which of the following activities generally requires the most effort after the release of a software system?
- A. Performing maintenance
- B. Training the users
- C. Revising documentation
- D. Customer acceptance