最高で有効なPMI-ACP試験問題と解答PDF PMI-ACP問題集(最近更新された210問あります) [Q72-Q92]

Share

最高で有効なPMI-ACP試験問題と解答PDF PMI-ACP問題集(最近更新された210問あります)

試験問題解答はPMI-ACP学習ガイド


PMI-ACP 認定試験は、プロジェクトマネジメント協会(PMI)によって実施される試験で、プロジェクトマネジメントの認定資格、標準、およびリソースを提供する非営利のプロフェッショナル会員協会です。PMI-ACP 試験は、アジャイル実践ガイドに基づいており、Scrum、Kanban、Lean、XP などのさまざまなアジャイル方法をカバーしています。

 

質問 # 72
An agile coach realizes that a team responsible for a major release is a few months behind schedule The marketing department is unaware of this delay and is planning to start the marketing campaign and announce the release What should the agile coach do?

  • A. In the upcoming retrospective, discuss ways to improve sharing protect status information.
  • B. Meet with the agile team lead to discuss ways to improve team velocity and get back on track.
  • C. Meet with the marketing stakeholders to explain that the team will miss the planned release date.
  • D. Use this as a learning opportunity and allow the team to hand* the situation when the marketing campaign begins.

正解:C


質問 # 73
The length of time to recover the cost of a project investment is the:

  • A. Net Present Value
  • B. Earned Value
  • C. ROI
  • D. Payback Period

正解:D


質問 # 74
The following chart lists stories for a release of an Agile project:
If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

正解:B


質問 # 75
If there are multiple Scrum teams working on a product, each needs its own definition of Done.

  • A. True
  • B. False

正解:B


質問 # 76
The purpose of a Sprint retrospective is for the Scrum team to:

  • A. Review stories planned for the next sprint and provide estimates,
  • B. Demonstrate completed user stories to the Product Owner.
  • C. Determine what to stop doing, start doing, and continue doing.
  • D. Individually provide status updates on user stories in progress.

正解:C


質問 # 77
Team A is working on the second sprint of a product release Team B.
Which is an interdependent team located on the same floor requires extensive and frequent information to complete its sprint goal What should the agile team lead do?

  • A. Create a central repository for information, and provide access to team B
  • B. Provide team B with the information on an "as needed" basis
  • C. Email ail stakeholders with status updates
  • D. Use an information board that will be visible to an passing through the workspace

正解:A


質問 # 78
Feature X has a value of 12 and the total value of all features is 35. If the feature is estimated to cost 56%, what is the priority of this feature using relative weighting?

  • A. 0.61
  • B. 0.34
  • C. 0.625
  • D. 1.64

正解:A


質問 # 79
Which of the following BEST describes Horizontal Market Software?

  • A. Developed for many organizations
  • B. Developed and used across many industries
  • C. Developed for one organization
  • D. Developed for a dedicated customer

正解:B


質問 # 80
_____________ an estimate refers to estimating a story based on its relationship to one or more other stories.

  • A. Triaging
  • B. Aggregating
  • C. Triangulating
  • D. Disaggregating

正解:C


質問 # 81
In Kanban, a diagram that describes the overall flow and provides a measurement for every significant step in the workflow is the:

  • A. Parking Lot Chart
  • B. Cumulative Flow diagram
  • C. Kanban board
  • D. Burn Down Chart

正解:B


質問 # 82
An executive sponsor of a new scrum team actively attends scrum ceremonies.
How does this benefit the team?

  • A. It provides high-level project updates to the sponsor
  • B. It helps to quickly resolve issue using the sponsor's influence
  • C. It helps the team to focus on and meet sprint goals
  • D. It reminds the team about who sponsors the project

正解:C


質問 # 83
In agile approaches, negotiation is viewed as:

  • A. A healthy process of give and take
  • B. A zero-sum game
  • C. A winner-takes-all challenge
  • D. A failproof win-win scenario

正解:A


質問 # 84
Which of the following sets of tools is least likely to be utilized by an Agile team?

  • A. Smart board, card wall
  • B. Digital camera, task board
  • C. WBS, PERT charts
  • D. Wiki, planning poker cards

正解:C


質問 # 85
The measure of productivity of a Kanban team is:

  • A. Throughput
  • B. Cycle time
  • C. Work in Progress
  • D. Velocity
  • E. Lead Time

正解:A


質問 # 86
A development team has finished identifying the tasks they will be accountable for during the next sprint. Which of the following tools best provides transparency into the progress throughout the sprint?

  • A. Gantt chart
  • B. Burndown chart
  • C. Hours expended chart
  • D. Management baseline chart

正解:B

解説:
Explanation/Reference:


質問 # 87
Non-functional requirements should be written as user stories whenever possible.

  • A. True
  • B. False

正解:B


質問 # 88
During its first sprint a new scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories. What should the team do?

  • A. Send a member to automation framework training when funds are available
  • B. Cross-tram some members in the automation framework to broaden their capacity with that skill
  • C. Avoid using test automation by swarming on the testing tasks and using manual testing
  • D. Ask the product owner to add team members to boost this particular skill set

正解:D


質問 # 89
Based on the backlog metrics in the chart, what can explain the jump in points at the end of iteration 4?

  • A. The team neglected to account for support and maintenance costs associated with other supported products
  • B. The team discovered that previously accepted work could be greatly improved and added story points associated with that work
  • C. The team realized that some stories were underestimated relative to other stories and reestimated as needed
  • D. The team learned that the product owner needed to increase the output in the next release

正解:D


質問 # 90
According to the Agile Manifesto, which of the following describes the more valued items?

  • A. Working software, individual interactions, responding to change, and comprehensive documentation
  • B. Customer collaboration, following a plan, working software, and individual interactions
  • C. Responding to change, individual interactions, processes and tools, and customercollaboration
  • D. Individual interactions, working software, customer collaboration, and responding to change

正解:D

解説:
Explanation/Reference:


質問 # 91
The key elements of a user story in Agile development are:

  • A. a written description, the story points estimate, and the planned release.
  • B. tests to determine when the story is done, a written description, and the planned release.
  • C. conversations about the story, a written description, and success criteria about the story.
  • D. the story points estimate, conversations about the story, and an agreed priority.

正解:C


質問 # 92
......