質問 42
A project team is distributed across multiple countries, and they are having issues agreeing on what is being delivered and how it should be developed. Which of the following should the project manager do to alleviate some of the tension between team members, break down cultural barriers, and improve communication?

  • A. Discuss this issue with senior management and recommend that the team be co-located.
  • B. Monitor performance and discuss the issues in detail at the next retrospective.
  • C. Hold daily standup meetings with the two teams at a time that works best for everyone.
  • D. Ask the team to communicate only through email to clearly document issues.

正解: C

 

質問 43
When using Agile Earned Value Management (EVM), progress should be measured at which level?

  • A. Iteration
  • B. Release
  • C. Task
  • D. Product

正解: B

 

質問 44
When does Adaptation occur in Scrum?

  • A. During Sprint Planning
  • B. At the Sprint Review
  • C. At all four formal Scrum events
  • D. As Part of the Sprint Retrospective
  • E. In the daily Scrum

正解: C

 

質問 45
What is a high-level representation of the features or themes that are to be delivered in each release?

  • A. Release plan
  • B. Product roadmap
  • C. Iteration plan
  • D. Product Backlog

正解: B

 

質問 46
A project team identifies a number of technical challenges with features in the next sprint.
What should they do?

  • A. Determine who is best qualified to address the challenges
  • B. Ask the product owner to assign the tasks to the most appropriately skilled resources
  • C. Request direction from the technical manager
  • D. Encourage the product owner to reallocate the features to another sprint

正解: B

解説:
Explanation/Reference:

 

質問 47
The Product Owner and Scrum Master are never part of the Development Team.

  • A. True
  • B. False

正解: B

解説:
Explanation

 

質問 48
Agile development prevents technical debt.

  • A. True
  • B. False

正解: B

 

質問 49
During an iteration planning meeting, the team suggests changes to add product value that will require extra work and impact the schedule. What should the agile project leader do?

  • A. Ask the product owner for approval to proceed.
  • B. Try to include as many changes as possible.
  • C. Finish the product as it was initially planned.
  • D. Re-estimate the project.

正解: A

 

質問 50
The smallest amount of functionality that delivers customer value is best described as a:

  • A. Userstory map.
  • B. Right sized story.
  • C. Minimum marketable feature.
  • D. Function point analysis.

正解: C

解説:
Explanation/Reference:
Explanation:

 

質問 51
Which of the following is a list of valid Agile project planning practices?

  • A. Estimation, Spike Solutions, and Iteration planning
  • B. Release planning, Iteration planning, and Estimation
  • C. Iteration planning, Continuous Integration, and Estimation
  • D. Vision, Release planning, and Performance Optimization

正解: B

解説:
Explanation/Reference:

 

質問 52
The agile team disagrees with the business stakeholders on completing some epics.
What could help eliminate misunderstandings?

  • A. Consider previous sprint demo feedback when planning the next sprint
  • B. Include the reasons for the project in the contract
  • C. Begin planning every four iterations
  • D. Agree on requirements with all stakeholders

正解: A

 

質問 53
Suppose your team velocity is 8 story points, and the product backlog items are ordered by priority as shown below. If you are in a Sprint Planning meeting and need to commit to the User Stories for the next iteration, which ones will you select?

  • A. Story 1, 2, and 4
  • B. Story 2, 3, and 4
  • C. Story 1 and 2
  • D. Story 1, 2, and 3

正解: A

 

質問 54
Information transmission is greatest amongst team members who are working on:

  • A. The same task through pair programming.
  • B. The same group of tasks individually.
  • C. Different tasks on the same project.
  • D. Individual tasks in the same work area.

正解: A

 

質問 55
For a "caves and commonroom arrangement, the most appropriate prerequisite is that the people in the room must be working on:

  • A. Whatever they choose.
  • B. Individual projects.
  • C. The same set of multiple projects,
  • D. The same project.

正解: D

解説:
Explanation/Reference:

 

質問 56
Scrum practices are facilitated by the:

  • A. Scrum team.
  • B. ScrumMaster.
  • C. Product Owner.
  • D. Project Sponsor.

正解: B

 

質問 57
Information transmission is greatest amongst team members who are working on:

  • A. The same task through pair programming.
  • B. The same group of tasks individually.
  • C. Different tasks on the same project.
  • D. Individual tasks in the same work area.

正解: A

解説:
Explanation/Reference:
Explanation:

 

質問 58
A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated.
What should the Scrum Master do?

  • A. Ensure that the next sprint planning meeting reviews the satisfaction histogram
  • B. Ensure that the product owner reviews the contents of the information radiator
  • C. Point out that the team chose to work on other requirements to speed up the project
  • D. Point out that it is the responsibility of the product owner to clarify requirements

正解: C

 

質問 59
A project team estimates that they should complete 30 story points in the current iteration.
Partway through the iteration they realize that they will complete 50 story points at their current rate.
The team should:

  • A. Increase their estimated velocity.
  • B. Release members to meet the estimated velocity.
  • C. Shorten the iteration to meet the estimated velocity.
  • D. Continue to work with the estimated velocity.

正解: B

 