質問 # 100
Which of the following techniques is used to identify ambiguous or unverifiable requirements?
- A. Team peer review
- B. Resource checklist
- C. Fishbone analysis
- D. Traceability matrix
正解:A
解説:
Team peer review is a technique that is used to identify ambiguous or unverifiable requirements. Team peer review is a technique that involves having a group of peers or experts examine and evaluate the requirements for quality, completeness, correctness, clarity, consistency, and testability. Team peer review can help to identify any ambiguous or unverifiable requirements that may cause confusion, misunderstanding, or errors in the project. Team peer review can also provide feedback and suggestions for improvement or resolution of any issues or defects in the requirements. Fishbone analysis is not a technique that is used to identify ambiguous or unverifiable requirements. Fishbone analysis is a technique that is used to identify the root causes of a problem or an effect by analyzing its contributing factors and their relationships. Fishbone analysis can help to understand why a problem exists or why an effect occurs, but it does not directly examine or evaluate the quality of the requirements. Resource checklist is not a technique that is used to identify ambiguous or unverifiable requirements. Resource checklist is a tool that is used to identify and document the resources needed to perform business analysis activities, such as people, tools, facilities, equipment, etc.
Resource checklist can help to plan and manage the resources required for business analysis work, but it does not assess or verify the quality of the requirements. Traceability matrix is not a technique that is used to identify ambiguous or unverifiable requirements. Traceability matrix is a tool that is used to track and document the relationships and dependencies among requirements and other project elements, such as design, test cases, risks, issues, etc. Traceability matrix can help to monitor and control changes to requirements and ensure alignment with project objectives and stakeholder needs, but it does not measure or validate the quality of the requirements. References: Business Analysis for Practitioners: A Practice Guide 1, page 162-163; PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline 2, page 19-20.
質問 # 101
A company has launched a new online sales application and engaged a focus group to test how quickly the customer could place an order. The focus group also provided feedback on their satisfaction.
Which metrics tool should the business analyst use to record the results?
- A. Focus group
- B. Customer
- C. Sales and marketing
- D. Business completion
正解:D
解説:
Explanation/Reference:
質問 # 102
A business analyst captures an application's current limitations and consults with end users to identify new features for the next version.
What can be used to analyze this information and determine project scope?
- A. As-is process
- B. Requirements traceability matrix
- C. Root cause analysis
- D. Capability table
正解:D
解説:
A capability table is a tool that lists the current capabilities of an application and compares them with the desired capabilities identified by the end users. A capability table can help the business analyst to analyze this information and determine project scope by showing the gaps between the current and future states of the application, and prioritizing the new features that will address those gaps. A capability table can also help to define the high-level requirements and objectives of the project. References: = PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline (2019), page 11; Business Analysis for Practitioners: A Practice Guide (2015), page 67.
質問 # 103
The business analyst has been assigned to a project involving a low number of stakeholders. Which technique should be used to elicit requirements?
- A. Interview
- B. Document analysis
- C. Interface analysis
- D. Survey
正解:A
質問 # 104
The business analyst receives multiple changes from different stakeholders during the requirements gathering phase of a project. How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?
- A. Perform inspections through the lifecycle of the project to detect any gaps and adjust the requirements baseline.
- B. Record all the requirements in a matrix, review it regularly, and get approval from stakeholders.
- C. Plan regular meetings with stakeholders to review the requirements baseline update and to discuss changes.
- D. Establish a risk traceabllity matrix and designate someone to manage each risk with the appropriate response.
正解:D
質問 # 105
What should the business analyst do during the first steps of a project?
- A. Align the sponsor expectations along the project goals.
- B. Identify the classes of users and their requirements.
- C. Evaluate the sources for requirements and prioritize them.
- D. Identify stakeholders and their interests.
正解:D
解説:
Explanation/Reference: https://www.glowtouch.com/business-analysis-process-flow/
質問 # 106
A business analyst is working with the project manager, company auditors, and project stakeholders to determine whether formal signoff should be required for the project. For which reason would the business analyst recommend formal signoff to the group?
- A. The industry is unregulated.
- B. The project impact is contained within a small department of the company.
- C. The organization follows an iterative project life cycle.
- D. Errors in the product could result in financial solvency.
正解:D
解説:
The business analyst would recommend formal signoff to the group if errors in the product could result in financial solvency. Formal signoff is a process that ensures that the stakeholders agree on and approve the requirements and deliverables of the project. Formal signoff can help to reduce ambiguity, confusion, or disputes among the stakeholders and increase their accountability and commitment to the project. Formal signoff is especially important when errors in the product could result in financial solvency, as it implies that there is a high level of risk, complexity, or regulation involved in the project and that any mistake or defect could have severe consequences for the organization or its customers. The industry being unregulated is not a reason to recommend formal signoff to the group, as it implies that there is less need for compliance or verification of the product quality or performance. The project impact being contained within a small department of the company is not a reason to recommend formal signoff to the group, as it implies that there is less stakeholder involvement or interest in the project outcome or value. The organization following an iterative project life cycle is not a reason to recommend formal signoff to the group, as it implies that there is more flexibility and adaptability in the project scope and deliverables and that feedback and validation are obtained frequently throughout the project. References: Business Analysis for Practitioners: A Practice Guide 1, page 113-114; PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline 2, page 17.
質問 # 107
A business analyst is working on a project to implement a new call management system for a help desk. They expected the average time interval to answer a call to decrease over time, but the interval has increased instead.
Which technique should the business analyst use to investigate the problem?
- A. Interviews
- B. Root cause analysis
- C. Process modeling
- D. Observation
正解:B
解説:
Explanation
Root cause analysis (RCA) is a technique that can be used to investigate the problem of increased call interval in a new call management system. Root cause analysis is a method of identifying and resolving the underlying causes of a problem or an issue, rather than treating the symptoms or the effects. Root cause analysis involves asking questions, collecting data, analyzing evidence, finding patterns, drawing conclusions, and recommending solutions. Root cause analysis can help to prevent recurrence of the problem, improve performance, reduce risks, and increase customer satisfaction. Interviews are a technique that can be used to elicit information from stakeholders, but they may not be sufficient to investigate the problem in depth and find its root causes. Observation is a technique that can be used to understand how stakeholders perform their work in their own environment, but it may not be able to explain why the problem occurs and what causes it. Process modeling is a technique that can be used to represent how activities are performed in a process, but it may not be able to identify and resolve the problem in the process. References: PMI Professional in Business Analysis (PMI-PBA)
Examination Content Outline1, page 15; Business Analysis for Practitioners: A Practice Guide2, page 95.
質問 # 108
A sponsor requests a new requirement The business analyst explains that most of the information needed for this requirement does not exist and that the requirement cannot be implemented. The business analyst recommends deferring the requirement until the needed information is available and then adding it to a subsequent project The sponsor agrees.
What should the business analyst do next?
- A. Ask the stakeholders to review the requirement before any other action is taken.
- B. Communicate that the status of this requirement has changed.
- C. Bring the subsequent project to the change control board (CCB).
- D. Mark the requirement as complete so that it is not forgotten.
正解:A
質問 # 109
While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis favors a custom-developed solution, either built internally or using contract labor.
To prepare the recommendation, what should the business analyst do?
- A. Recommend the SVP's choice, as it is most likely to be adopted.
- B. Formulate a weighted-ranking matrix.
- C. Perform solution evaluation.
- D. Review the stakeholder analysis.
正解:B
解説:
Explanation
A weighted-ranking matrix is a technique that involves assigning scores and weights to different criteria and options to compare and prioritize them. A weighted-ranking matrix can help the business analyst to prepare the recommendation by quantifying and ranking the three different solution options based on their alignment with the business objectives, benefits, costs, risks, and other factors. A weighted-ranking matrix can also help to justify and communicate the recommendation with evidence and transparency. References: = PMI Professional in Business Analysis (PMI-PBA)
Examination Content Outline (2019), page 11; Business Analysis for
Practitioners: A Practice Guide (2015), page 66.
質問 # 110
The business analyst is seriously concerned about the possibility of differing interpretations of data items mentioned in the requirements documents. Which course of action should the business analyst take to minimize the risk of misunderstanding?
- A. Ask the development teams for a formal acceptance of the requirements specification.
- B. Write a data dictionary that accompanies the requirements specification.
- C. Hold a workshop with the development teams to explain the details of the requirements specification.
- D. Plan a peer review of the requirements specification.
正解:C
質問 # 111
A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create project plans, schedule meetings, and provide meeting minutes.
In the scenario above, what is the role of the technical staff and testing team from Company A?
- A. Responsible
- B. Consult
- C. Inform
- D. Accountable
正解:D
解説:
Explanation/Reference:
質問 # 112
A business analyst is trying to complete the requirement documentation of a project and finds that the developers have started development. The business analyst should first facilitate the:
- A. requirements sign-off with the customer.
- B. requirements acceptance with the customer.
- C. requirements validation with the testers.
- D. requirements gathering workshops with the stakeholders.
正解:A
解説:
Explanation
The requirements sign-off is a process that involves obtaining the formal approval and acceptance of the requirements from the customer and other stakeholders. The requirements sign-off confirms that the requirements are clear, complete, correct, and consistent, and that they meet the customer's needs and expectations. The requirements sign-off also establishes a baseline for the development and testing of the solution, and serves as a reference point for managing changes and resolving issues. The business analyst should first facilitate the requirements sign-off with the customer before the developers start development, to ensure that the requirements are agreed upon and validated by all parties, and to avoid rework, delays, and conflicts later in the project. References: PMI Professional in Business Analysis (PMI-PBA)
Examination
Content Outline1, page 18; Business Analysis for Practitioners: A Practice Guide2, page 92.
質問 # 113
A business analyst created requirements for production of a product extract file for several systems. After reviewing the complex systems and dividing the processes into manageable tasks, the business analyst is able to identify the tasks required to implement the deliverable.
Which analysis technique has the business analyst used?
- A. Decomposition
- B. Organization
- C. Interface
- D. Dependency
正解:A
解説:
Decomposition is an analysis technique that breaks down a complex system, process, or problem into smaller and simpler components. It helps to identify the tasks, activities, functions, features, and requirements that are necessary to implement the deliverable. Decomposition also helps to organize, structure, and prioritize the components based on their dependencies and relationships. Organization, dependency, and interface are not analysis techniques, but rather aspects or results of decomposition . References: PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline, page 10; Business Analysis for Practitioners: A Practice Guide, page 131-132
質問 # 114
A business analysl is working on a project to implement a new call management system for a help desk. They expected the average time interval to answer a call to decrease over time, but the interval has increased instead.
Which technique should the business analyst use to investigate the problem?
- A. Interviews
- B. Root cause analysis
- C. Process modeling
- D. Observation
正解:B
質問 # 115
Two weeks prior to the delivery date, a customer changes the business requirements. What should the business analyst do?
- A. Trace the requirements and measure the impact of the requested changes on the existing delivery date.
- B. Schedule a review by the change control board (CCB) to determine next steps.
- C. Ask the developers to implement the changes.
- D. Deliver the existing product and then begin work on the requested changes.
正解:A
解説:
The business analyst should trace the requirements and measure the impact of the requested changes on the existing delivery date. Tracing the requirements means identifying the source, dependencies, and relationships of the requirements, and ensuring their alignment with the business needs, objectives, and expectations.
Measuring the impact of the changes means assessing how the changes will affect the scope, schedule, cost, quality, and risk of the project. These actions can help the business analyst and the project team to evaluate the feasibility and priority of the changes, and to communicate the implications and alternatives to the customer and other stakeholders. References: PMI Professional in Business Analysis (PMI-PBA) Examination Content Outline1, page 23; Business Analysis for Practitioners: A Practice Guide2, page 131.
質問 # 116
A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems.
Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?
- A. Rules modeling
- B. Interface modeling
- C. Enterprise modeling
- D. Data modeling
正解:D
質問 # 117
The human resources, engineering, and marketing departments have provided feedback on the business needs for a new product. After analyzing the feedback from the three departments, it would be best to:
- A. negotiate to best meet each department's objectives.
- B. vote on the product's highest-value business needs
- C. collaborate on a product scope that aligns with the company's objectives.
- D. delegate the decision to be made by the product sponsor.
正解:C
質問 # 118
A business analyst has received a test result report that shows evidence of defective functionality. The business analyst checks the test result again and verifies that the functionality behaves according to the requirements.
At this point, the business analyst should first:
- A. change the requirement according to the test result.
- B. ask the tester to perform the test again.
- C. verify that the test case is incorrect.
- D. let the users decide if the test result is acceptable.
正解:C
質問 # 119
When managing a product backlog, which statement best describes how to determine the value of backlog items?
- A. The stakeholders follow the value-ranking criteria.
- B. The stakeholders provide input about backlog value when the item is first identified.
- C. The stakeholders provide recommendations with the product owner having the final say.
- D. The stakeholders do not typically play a major role.
正解:C
質問 # 120
A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.
Which of the following types of surveys would be most appropriate to create and why?
- A. A closed-ended survey using the Likert scale to rank specific areas of the current business process
- B. A closed-ended survey to pose several multiple-choice questions and ask the users if the current business process Is correct
- C. An open-ended survey to collect different opinions on the current business process
- D. An open-ended survey to allow users the opportunity to explain their opinions on the current business process
正解:A
解説:
A closed-ended survey using the Likert scale is a type of survey that asks respondents to indicate their level of agreement or disagreement with a series of statements related to the current business process. This type of survey is useful for gathering data that can be used in a statistical analysis to measure user satisfaction, identify pain points, and evaluate the performance of the current business process. A closed-ended survey is also easier to administer and analyze than an open-ended survey, which requires more time and effort to code and interpret the responses. References: PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline1, page 17; Business Analysis for Practitioners: A Practice Guide2, page 91.
質問 # 121
A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.
What is the best approach to resolve this issue?
- A. Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.
- B. Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.
- C. Suggest re-estimating the requirement and following the change control process.
- D. Meet with the customer and apologize for misunderstanding the business's need.
正解:C
解説:
The best approach to resolve this issue is to suggest re-estimating the requirement and following the change control process. This would allow the project team to assess the impact of the change request, evaluate the feasibility and cost of the modification, and obtain the approval of the stakeholders before implementing the change. A change control process is a method used to manage change requests for projects and big initiatives. It's part of a change management plan, which defines the roles for managing change within a team or company1. Meeting with the customer and apologizing for misunderstanding the business's need is not sufficient, as it does not address the root cause of the problem or propose a solution. Providing the stakeholder with a copy of the approved requirements baseline and moving forward without making a change is not acceptable, as it ignores the stakeholder's feedback and dissatisfaction. Requiring development resources to work overtime to modify the deliverable to satisfy the stakeholder is not advisable, as it may compromise the quality of the work, increase the project cost and risk, and demoralize the team. References: PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline2, PMI Guide to Business Analysis3, Business Analysis for Practitioners: A Practice Guide4, What Is a Change Control Process? (with Example Change Log)
質問 # 122
While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis favors a custom-developed solution, either built internally or using contract labor.
To prepare the recommendation, what should the business analyst do?
- A. Recommend the SVP's choice, as It is most likely to be adopted.
- B. Formulate a weighted-ranking matrix.
- C. Perform solution evaluation
- D. Review the stakeholder analysis.
正解:B
質問 # 123
......
PMI-PBA認定試験は、要件管理、利害関係者の関与、誘発と分析、ソリューション評価と検証、ビジネス分析の計画と監視など、ビジネス分析に関連する幅広いトピックをカバーしています。この試験は、これらのトピックに関する候補者の知識だけでなく、この知識を現実世界のプロジェクト環境に適用する能力をテストするように設計されています。この認定は雇用主によって高く評価されており、雇用市場の競争力を専門家に提供します。
PMI PMI-PBAは、「PMI Professional in Business Analysis」とも呼ばれるビジネスアナリストに特化した認定試験です。この認定試験は、プロジェクトマネジメント、ビジネスアナリシス、その他関連分野における専門家に認定と資格を提供する、世界的に認知された組織であるProject Management Institute(PMI)が提供しています。
100%更新されたのはPMI PMI-PBA限定版PDF問題集:https://www.passtest.jp/PMI/PMI-PBA-shiken.html
無料PMI Professional in Business Analysis PMI-PBA公式認定ガイドPDFダウンロード:https://drive.google.com/open?id=1vW7Gwd_xPKc9j3_O-FPUuJnkM092Z1j2