質問 # 43
Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?
- A. Feasibility analysis
- B. B. Force-field analysis
- C. PEST analysis
- D. Gap analysis
正解:A
解説:
A force-field analysis is a tool that helps to identify and analyze the factors or forces that support or oppose a change or an initiative. It can help to facilitate the decision-making process when stakeholders do not agree on the value of an initiative by showing the pros and cons of the initiative, as well as the relative strength and importance of each factor. A force-field analysis can also help to develop strategies to increase the supporting forces or decrease the opposing forces, or both, to achieve the desired outcome. A PEST analysis is a tool that helps to examine the external factors that affect an organization or an initiative, such as political, economic, social, and technological factors. It does not help to facilitate the decision-making process when stakeholders do not agree on the value of an initiative, as it does not show the internal factors or the balance of forces. A feasibility analysis is a tool that helps to evaluate the viability and suitability of a project or an initiative, as well as the risks and benefits associated with it. It does not help to facilitate the decision-making process when stakeholders do not agree on the value of an initiative, as it does not show the supporting and opposing forces. A gap analysis is a tool that helps to compare the current state and the desired state of a process, a product, or a service, and identify the gaps or differences between them. It does not help to facilitate the decision-making process when stakeholders do not agree on the value of an initiative, as it does not show the factors or forces that influence the initiative. References: PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline1, PMI Guide to Business Analysis2, Business Analysis for Practitioners: A Practice Guide3, What is Force Field Analysis: Definition and Example
質問 # 44
Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?
- A. Waterfall
- B. Linear
- C. Agile
- D. Iterative
正解:C
解説:
Explanation/Reference: https://www.sealights.io/agile-testing/agile-testing-8-principles-7-challenges-and-how-to-master- them/
質問 # 45
Company A has been awarded a contract to finalize the development of a product that Company B was not able to finish. The business analyst is given a copy of the documentation left by Company B.
To which of the following documents should the business analyst pay the most attention to ensure the project succeeds this time?
- A. Clauses in the contract
- B. Business use cases
- C. Application design documentation
- D. Test case documentation
正解:B
質問 # 46
A business analyst is developing a traceability matrix to determine whether or not any gaps exist and to identify any discrepancies.
Which critical field is needed to ensure that the traceability matrix is usable?
- A. Owner
- B. Status
- C. Hierarchy
- D. Requirements description
正解:D
質問 # 47
A new product was designed and delivered to the customer. The product exceeded customer expectations but did not meet the baseline budget for the product. What could be the issue?
- A. Risks identified in the risk management plan were not addressed properly.
- B. Requirements were not properly traced and monitored.
- C. The sponsor approved the release of the product without reviewing the budget.
- D. There is no issue since the product exceeded the customer expectations.
正解:A
解説:
According to the PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline, one of the tasks under the domain of Planning is to "Develop a risk management plan for business analysis activities and monitor risks, issues, and assumptions" (Task 9). This implies that the business analyst is responsible for identifying, analyzing, and managing the risks that may affect the business analysis activities and deliverables. If the risks are not addressed properly, they may result in deviations from the baseline budget, schedule, scope, or quality of the product. Therefore, the issue in this scenario could be that the risks identified in the risk management plan were not addressed properly.
質問 # 48
What should the business analyst do to ensure that all requirements meet a quality checklist before the development and testing phase?
- A. Obtain approval from engineering for partial testing of the requirements.
- B. Assign a verification method to each requirement.
- C. Negotiate with the client to standardize the requirements.
- D. Validate the requirements deemed important by the stakeholders.
正解:B
質問 # 49
A new project's goal is to replace an existing system. What is an input into solution evaluation and decision making in this context?
- A. Technical readiness of the development team
- B. New solution design specification
- C. Customer metrics on the existing system
- D. Cost-benefit analysis of the existing system
正解:D
質問 # 50
The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and with a lean budget.
What should the team do to reduce the risk of rework?
- A. Organize a new elicitation workshop.
- B. Ask the project sponsor to prioritize the requirements.
- C. Validate the requirements before continuing with development.
- D. Perform a Pareto analysis on the requirements.
正解:C
解説:
Validating the requirements is a key activity to reduce the risk of rework, especially for a project with a tight timeline and a lean budget. Validating the requirements means ensuring that they are aligned with the business needs, objectives, and expectations of the stakeholders, and that they are clear, complete, consistent, feasible, and testable. Validating the requirements can help the business analyst and the project team to identify and resolve any errors, gaps, conflicts, or ambiguities in the requirements before they are implemented, and to avoid any unnecessary changes or rework later in the project lifecycle. References: PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline1, page 20; Business Analysis for Practitioners: A Practice Guide2, page 100.
質問 # 51
What should the business analyst do during the first steps of a project?
- A. Identify stakeholders and their interests.
- B. Align the sponsor expectations along the project goals.
- C. Identify the classes of users and their requirements.
- D. Evaluate the sources for requirements and prioritize them.
正解:A
解説:
Explanation
One of the first steps of a project is to identify the stakeholders and their interests. Stakeholders are the individuals or groups who have an interest or influence in the project or its outcome. Identifying the stakeholders and their interests helps to understand their needs, expectations, roles, responsibilities, and communication preferences. It also helps to manage their involvement and engagement throughout the project life cycle, and to address any potential conflicts or issues that may arise. The other options are not the first steps of a project. Identifying the classes of users and their requirements is part of the requirements elicitation process, which occurs after the project initiation phase. Aligning the sponsor expectations along the project goals is part of the project charter development, which is also done after the project initiation phase.
Evaluating the sources for requirements and prioritizing them is part of the requirements analysis process, which occurs after the requirements elicitation process. References: PMI-PBA
Examination Content Outline,
page 10; PMI-PBA
Reference List, page 1, BABOK
Guide v3, page 50; 3.
質問 # 52
A business analyst is working on a project to implement a new call management system for a help desk. They expected the average time interval to answer a call to decrease over time, but the interval has increased instead.
Which technique should the business analyst use to investigate the problem?
- A. Root cause analysis
- B. Interviews
- C. Observation
- D. Process modeling
正解:A
解説:
Root cause analysis (RCA) is a technique that can be used to investigate the problem of increased call interval in a new call management system. Root cause analysis is a method of identifying and resolving the underlying causes of a problem or an issue, rather than treating the symptoms or the effects. Root cause analysis involves asking questions, collecting data, analyzing evidence, finding patterns, drawing conclusions, and recommending solutions. Root cause analysis can help to prevent recurrence of the problem, improve performance, reduce risks, and increase customer satisfaction. Interviews are a technique that can be used to elicit information from stakeholders, but they may not be sufficient to investigate the problem in depth and find its root causes. Observation is a technique that can be used to understand how stakeholders perform their work in their own environment, but it may not be able to explain why the problem occurs and what causes it. Process modeling is a technique that can be used to represent how activities are performed in a process, but it may not be able to identify and resolve the problem in the process. References: PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline1, page 15; Business Analysis for Practitioners:
A Practice Guide2, page 95.
質問 # 53
Which tool should be used to improve the communication of product needs with the stakeholders and to improve their understanding?
- A. Modeling tool integrated into a version control feature that ensures that team knowledge is captured
- B. Document management system and a relationship matrix that groups all related documents
- C. Workflow management tool that documents the flow of information
- D. Requirements management tool that documents requirements and their properties and relationships.
正解:D
質問 # 54
A business analyst is working on a highly complex project and has elicited a large number of requirements from stakeholders in several departments. Due to the large number of requirements, the stakeholders have determined that they would like to prioritize them to minimize a potentially large scope.
Which technique could the business analyst use to manage requirements?
- A. SMART goals
- B. RAC! models
- C. Storyboarding
- D. MoSCoW
正解:D
解説:
Explanation
The MoSCoW technique is a prioritization technique that helps to rank requirements according to their importance and urgency. The acronym stands for Must have, Should have, Could have, and Won't have. This technique can help the business analyst to manage requirements by focusing on the most critical ones and minimizing the scope creep. References: = PMI Professional in Business Analysis (PMI-PBA)
Examination
Content Outline, page 19.
質問 # 55
A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.
Which of the following types of surveys would be most appropriate to create and why?
- A. A closed-ended survey using the Likert scale to rank specific areas of the current business process
- B. A closed-ended survey to pose several multiple-choice questions and ask the users if the current business process Is correct
- C. An open-ended survey to allow users the opportunity to explain their opinions on the current business process
- D. An open-ended survey to collect different opinions on the current business process
正解:A
解説:
A closed-ended survey using the Likert scale is a type of survey that asks respondents to indicate their level of agreement or disagreement with a series of statements related to the current business process. This type of survey is useful for gathering data that can be used in a statistical analysis to measure user satisfaction, identify pain points, and evaluate the performance of the current business process. A closed-ended survey is also easier to administer and analyze than an open-ended survey, which requires more time and effort to code and interpret the responses. References: PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline1, page 17; Business Analysis for Practitioners: A Practice Guide2, page 91.
質問 # 56
A business analyst captures an application's current limitations and consults with end users to identify new features for the next version.
What can be used to analyze this information and determine project scope?
- A. Requirements traceability matrix
- B. Capability table
- C. As-is process
- D. Root cause analysis
正解:B
解説:
A capability table is a tool that lists the current capabilities of an application and compares them with the desired capabilities identified by the end users. A capability table can help the business analyst to analyze this information and determine project scope by showing the gaps between the current and future states of the application, and prioritizing the new features that will address those gaps. A capability table can also help to define the high-level requirements and objectives of the project. References: = PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline (2019), page 11; Business Analysis for Practitioners: A Practice Guide (2015), page 67.
質問 # 57
When modeling processes or analyzing tasks, business rules can be uncovered by asking about:
- A. tasks that overlap with each other.
- B. reasons for choosing a particular course of action.
- C. task transitions that hinder organizational performance.
- D. work that may be performed out of sequence.
正解:B
質問 # 58
A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.
Which of the following types of surveys would be most appropriate to create and why?
- A. A closed-ended survey to pose several multiple choice questions and ask the users if the current business process is correct
- B. An open-ended survey to allow users the opportunity to explain their opinions on the current business process
- C. A closed-ended survey using the Likert scale to rank specific areas of the current business process
- D. An open-ended survey to collect different opinions on the current business process
正解:A
質問 # 59
Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s) versioning?
- A. Problem or opportunity statement
- B. Project plan
- C. Traceability matrix
- D. Statement of work
正解:C
質問 # 60
......
PMI-PBA認定試験は、ビジネス分析でキャリアを促進しようとしている専門家にとって優れた投資です。それは雇用主によって高く評価されている世界的に認められた資格であり、競争の激しい雇用市場で個人が際立っているのを助けることができます。この認定は、候補者にビジネス分析を包括的に理解することを提供します。これにより、より良い意思決定を行い、組織の成功に貢献することができます。
全問PMI-PBA問題集とPMI Professional in Business Analysis (PMI-PBA)トレーニングコース:https://www.passtest.jp/PMI/PMI-PBA-shiken.html
無料テストエンジンPMI Professional in Business Analysis (PMI-PBA)認定試験:https://drive.google.com/open?id=1jkt1tjqfq30hjbLil841-kR6I9HE2rGF