質問 # 17
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
- A. Kanban
- B. Material requirements planning
- C. Production order release
- D. Backflushing
正解:B
解説:
If the available stock is zero and the discontinuation date is in the past, the material requirements planning (MRP) process will be affected. MRP will not create any planned orders or purchase requisitions for the discontinued component. Instead, it will create a discontinuation indicator in the MRP list and a discontinuation message in the exception message list. This will inform the planner that the component is no longer available and that a follow-up material should be used instead. Reference: [SAP Help Portal] - Discontinuation of Materials.
質問 # 18
In your plant MRP is activated.
Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.
- A. Use a specific MRP type.
- B. Use a specific material group.
- C. Use a specific MRP list.
- D. Use a specific material status.
正解:A、D
質問 # 19
You have maintained the parameters for simple discontinuation in the material master of a component.
Which business process will be affected if the available stock is zero the discontinuation date is in the past?
- A. Kanban
- B. Material requirements planning
- C. Production order release
- D. Back flushing
正解:B
質問 # 20
You are a consultant on an SAP S/4HANA Cloud Greenfield project.
Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.
- A. Stability
- B. Efficiency
- C. Accuracy
- D. Timeliness
正解:A、B
質問 # 21
What is the purpose of a reporting point confirmation in repetitive manufacturing?
Note: There are 2 Correct answers to this question?
- A. To stage different components for a production line simultaneously
- B. To provide timely updates of inventory management for the staged components
- C. To determine the work in progress along the production line
- D. To reduce the total production lead time for a long production line
正解:B、C
解説:
A reporting point confirmation is a function that allows you to backflush the material components and activities that have been consumed and performed at a specific operation in a repetitive manufacturing process. It also reduces the dependent requirements for the planned orders. You can use reporting point confirmation for the following purposes:
To determine the work in progress (WIP) along the production line, by posting the quantity that is on the production line at each reporting point. This helps you to calculate the volume and value of unfinished products.
To provide timely updates of inventory management for the staged components, by recording the withdrawal of components at a time that is close to the time of the operation in which they are used. This helps you to avoid discrepancies between the actual and planned consumption of materials. Reference: Reporting Point Confirmation, Repetitive Manufacturing Confirmation
質問 # 22
During production order creation, several valid production versions are found. How does the system choose the production version?
- A. Alphanumeric or quota arrangement
- B. Validity period or sales order
- C. Lot size or material cost
- D. Planned order or material number
正解:B
解説:
The system chooses the production version based on the validity period and the sales order. The validity period determines whether the production version is valid for the planned start date of the production order. The sales order determines whether the production version is assigned to a specific sales order item or not. If there are multiple production versions that meet these criteria, the system chooses the one with the lowest alphanumeric value. Reference: [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 113; [SAP Help Portal: Production Version]
質問 # 23
During production order creation several valid production versions are found. How does the system choose the production version?
- A. Alphanumeric or quota arrangement
- B. Lot size or material cost
- C. Planned order or material number
- D. Validity period or sales order
正解:A
質問 # 24
Your project team decides to use a maketoorder planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision? Note: There are 3 correct answers to this question.
- A. Production orders are created with sales order reference.
- B. Net requirements calculation is carried out for every sales order individually.
- C. Storage location MRP areas are required for salesorderspecific stock.
- D. Sales orders have to be ATPconfirmed (availabletopromise) to be saved.
- E. Both the reduction of maketoorder stock requirements occur on delivery.
正解:A、B、D
質問 # 25
What options does a planner have in the planning table for repetitive manufacturing?
Note: There are 2 correct answers to this question.
- A. Reschedule deallocate operations.
- B. Dispatch operations to work centers.
- C. Change the assignments of production quantities to production lines.
- D. Create new production quantities.
正解:A、C
質問 # 26
You use planning strategy Finite Scheduling with Reverse and want to allow scheduling the past. How can you parameterize this in the strategy profile?
- A. Specify a negative planning horizon.
- B. Specify a positive offset time.
- C. Specify a positive planning horizon.
- D. Specify a negative offset time.
正解:D
解説:
The planning strategy Finite Scheduling with Reverse allows you to schedule production orders backwards from the requested delivery date, taking into account the available capacity and material constraints. To allow scheduling the past, you need to specify a negative offset time in the strategy profile. The offset time defines how far in the past the system can schedule the production order start date. For example, if you specify an offset time of -5 days, the system can schedule the production order start date up to 5 days before the current date. This can help you to avoid late deliveries and reduce lead times.
質問 # 27
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?
- A. The planned order generates capacity requirements
- B. The planned order is converted to a production order.
- C. The planned order's component availability is checked.
- D. The planned order's components are copied to the picking list.
正解:A
解説:
When you assign a planned order to a production line manually, using the planning table in repetitive manufacturing, the system generates capacity requirements for the planned order. The capacity requirements are calculated based on the production line, the quantity, and the production rate of the planned order. The system also checks the availability of the production line and displays any capacity overload or underload. The planned order is not converted to a production order, nor is the component availability or the picking list affected by the manual assignment. Reference: SAP Help Portal - Assigning Planned Orders to Production Lines, SAP S/4HANA Production Planning and Manufacturing Certification Guide - Chapter 7: Repetitive Manufacturing
質問 # 28
How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.
- A. By capacity planning
- B. By order release
- C. By order confirmation
- D. By mass processing
正解:B、D
質問 # 29
What options does a planner have in the planning table for repetitive manufacturing? Note: There are 2 correct answers to this question.
- A. Reschedule deallocate operations.
- B. Dispatch operations to work centers.
- C. Change the assignments of production quantities to production lines.
- D. Create new production quantities.
正解:A、C
質問 # 30
Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA.
When can you use mode selection?
- A. When multiple operations are maintained for one product
- B. When alternative resources are used within one operation
- C. When multiple production versions are maintained for one product
- D. When multiple planned orders exist on one resource
正解:B
解説:
Mode selection is a feature that allows the system to choose the best mode for an activity based on the mode priority and the available capacity of the resources. A mode is a combination of a resource and a formula that determines the duration and quantity of an activity. An operation can have multiple activities, each with multiple modes. Mode selection can be used when an operation contains several activities, each of which is assigned several modes for different resources, and the system needs to determine which resource to use for each activity. Mode selection can also be used when an activity has several modes for the same resource, and the system needs to determine which formula to use for the activity. Mode selection can be performed during the planning explosion or during the interactive planning. Reference: Mode Selection | SAP Help Portal, Mode Selection | SAP Help Portal
質問 # 31
Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.
- A. Production orders
- B. ATP quantities
- C. Planned orders (unfirmed)
- D. Planned orders (firmed)
正解:A、D
質問 # 32
You need to model goods receipt processing time in detailed scheduling. Which modeling options do you have?
Note: There are 3 correct answers to this question.
- A. Model a goods receipt time in the material master.
- B. Model a separate inbound resource in the location master.
- C. Model a handling resource in the location master.
- D. Model a separate resource in the production data structure.
- E. Model a transportation lane and carrier selection in the location master.
正解:A、C、E
解説:
You can model goods receipt processing time in detailed scheduling by using one or more of the following options:
Model a handling resource in the location master: A handling resource is a special type of resource that represents the capacity required for goods movements within a location, such as loading, unloading, or staging. You can assign a handling resource to a location and define its availability and utilization. You can also specify the handling time per unit of material for each handling resource. The system will then calculate the goods receipt processing time based on the handling time and the quantity of the material.
Model a transportation lane and carrier selection in the location master: A transportation lane is a master data object that defines the relationship between two locations in terms of transportation modes, means of transport, transit times, and costs. You can assign a transportation lane to a location and define the transportation mode, such as truck, rail, or air. You can also specify the carrier selection, which is a rule that determines the preferred carrier for each transportation mode. The system will then calculate the goods receipt processing time based on the transit time and the carrier selection.
Model a goods receipt time in the material master: A goods receipt time is a parameter that defines the time required to post the goods receipt for a material after it arrives at the location. You can specify the goods receipt time in the material master record for each material and location combination. The system will then add the goods receipt time to the goods receipt processing time.
You cannot model goods receipt processing time in detailed scheduling by using the following options:
Model a separate resource in the production data structure: A resource is a master data object that represents the capacity required for production activities, such as machines, labor, or tools. You can assign a resource to a production data structure, such as a bill of material, a routing, or a production version. However, a resource cannot be used to model goods receipt processing time, as it is not related to goods movements.
Model a separate inbound resource in the location master: An inbound resource is a parameter that defines the maximum number of inbound deliveries that can be processed at a location at the same time. You can specify the inbound resource in the location master record for each location. However, an inbound resource cannot be used to model goods receipt processing time, as it is only a constraint for the number of deliveries, not the duration of the processing.
質問 # 33
Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.
- A. Total replenishment lead time
- B. Setup time
- C. Float after production
- D. Opening period
正解:B、C
質問 # 34
You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched, how does the insertion take place?
- A. The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.
- B. The new operation is inserted at the desired time; the previous dispatched operation is moved forward.
- C. The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.
- D. The new operation is inserted at the desired time; the previously dispatched operation is moved backward
正解:D
解説:
The graphical planning table is a tool for capacity planning and scheduling that displays the operations and the work centers in a time-oriented view. You can use the graphical planning table to create, change, or dispatch operations manually or automatically. The planning direction determines whether the operations are scheduled from the start date or the finish date of the order. If the planning direction is forward, the operations are scheduled from the start date of the order1.
If you want to insert an operation at a certain time on a work center in the graphical planning table, and the planning direction is forward, and the desired dispatching time coincides with an operation that has previously been dispatched, the insertion takes place as follows:
The new operation is inserted at the desired time; the previously dispatched operation is moved backward (B): This is the correct answer. The system inserts the new operation at the specified time and shifts the previously dispatched operation to a later time, so that the sequence and the capacity requirements of the operations are maintained. The system also adjusts the start and finish dates of the order and the subsequent operations accordingly2.
The other options are not correct for the following reasons:
The new operation is inserted at the desired time; the previous dispatched operation is moved forward (A): This is not correct. The system does not move the previously dispatched operation to an earlier time, as this would violate the planning direction and the capacity constraints of the work center. The system only moves the previously dispatched operation to a later time, as explained in option B.
The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation (C): This is not correct. The system does not insert the new operation after the previously dispatched operation, as this would not match the desired dispatching time specified by the user. The system inserts the new operation at the desired time and moves the previously dispatched operation backward, as explained in option B.
The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation (D): This is not correct. The system does not insert the new operation before the previously dispatched operation, as this would violate the planning direction and the capacity constraints of the work center. The system inserts the new operation at the desired time and moves the previously dispatched operation backward, as explained in option B.
質問 # 35
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,
- A. By Plant
- B. By Period
- C. By Industry
- D. By Material Status
正解:A、B
解説:
You can limit the validity of a BOM by plant and by period. The plant determines the organizational area of validity for the BOM, and you can assign the same BOM to different or further plants if the prerequisites are met. The period of validity for a BOM is restricted by the valid-from date and the valid-to date in the BOM header and item, which determine when the BOM becomes effective and when it ends. Reference: Validity of Bills of Material, BOM Item Validity
質問 # 36
You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched.
How does the insertion take place?
- A. The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.
- B. The new operation is inserted at the desired time; the previously dispatched operation is moved backward.
- C. The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.
- D. The new operation is inserted at the desired time; the previously dispatched operation is moved forward.
正解:B
質問 # 37
Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.
- A. Reduce run schedule quantities.
- B. Update statistics for the Business Information Warehouse.
- C. Post production costs to the planned order.
- D. Post the goods receipt for the finished product.
- E. Create associated capacity requirements.
正解:A、C、E
質問 # 38
How can you support a GMP (Good Manufacturing Practice)-compliant production process?
Note: There are 3 correct answers to this question.
- A. Recipe approval
- B. Digital signature
- C. Batch record
- D. GMP-compliant flag
- E. Approved resources
正解:A、B、C
解説:
To support a GMP-compliant production process, you can use the following features in SAP S/4HANA:
Digital signature: This allows you to electronically sign documents and transactions that are relevant for GMP compliance, such as production orders, process orders, batch records, and quality inspections. Digital signatures ensure the authenticity, integrity, and non-repudiation of the documents and transactions12.
Batch record: This is a document that records the entire production process of a batch, including the materials, resources, operations, quality data, and signatures involved. Batch records provide traceability and documentation for GMP compliance3 .
Recipe approval: This is a process that ensures that only approved recipes can be used for production. Recipes are approved by authorized users who sign them digitally. Recipe approval prevents unauthorized changes and ensures consistency and quality of the products .
Reference:
1: SAP Help Portal: Digital Signature
2: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 8: Product Compliance
3: SAP Help Portal: Batch Record
4: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 8: Product Compliance
5: SAP Help Portal: Recipe Approval
6: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 7: Process Orders
質問 # 39
You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
- A. Choose planning strategy 50 (Planning without final assembly) select the corresponding Mixed MRP indicator.
- B. Choose planning strategy 20 (MaketoOrder) select the corresponding Mixed MRP indicator.
- C. Choose planning strategy 50 (Planning without final assembly) select the corresponding Individual/Collective indicator.
- D. Choose planning strategy 20 (MaketoOrder) select the corresponding Individual/Collective indicator.
正解:D
質問 # 40
......