質問 # 39
Thermal Spray coatings provide:
- A. Sacrificial protection
- B. Inhibitive protection
- C. Thermal protection
- D. Barrier protection
正解:A
質問 # 40
When performing a hardness test on a coating which has elastic properties the inspector is likely to likely to observe:
- A. Cold flow or creep
- B. A very low reading
- C. No difference from any other coating
- D. A very high reading
正解:A
質問 # 41
Individuals conducting Coating Surveys should:
- A. Always be trained and experienced Coating Industry
- B. Always be NACE or SSPC Protective coating Specialists
- C. Always be experienced Specification Writers
- D. Always be NACE Level 3 Certified Inspectors
正解:A
質問 # 42
Corrosion is the reverse process of
- A. hot dipping.
- B. steel manufacturing.
- C. galvanic deterioration.
- D. flaking.
正解:B
質問 # 43
You are working as an inspector in a galvanizing plant for the first time.
What are some of the hazards you need to be aware of:
- A. Risk of chemical exposure
- B. Risk of acid or caustic splashes
- C. Risk of skin
- D. a), b), and c)
正解:D
質問 # 44
WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)
- A. True
- B. False
正解:A
質問 # 45
Application of Thermal Spray Coatings requires:
- A. The same skills as welding
- B. The same skills as liquid coatings
- C. Specialized skills supported by training and experience
- D. No particular skills
正解:C
質問 # 46
You are working as the only in-house NACE Level 2 Inspector in a shop setting when an independent 3 rd party NACE Level 3 Inspector, representing the owner, presents you with a copy of a Non Conformance Report (NCR) he has written for a NACE2/SSPC SP 10 centrifugal blast which you had previously approved.
Your FIRST preferred course of action is to:
- A. Consult your supervisor
- B. Review the NCR with the other Inspector
- C. Verbally challenge the NCR
- D. Request a re-blast of the item in question
正解:A
質問 # 47
You are the NACE Level 2 Inspector on a project where overcoating of galvanized steel is being performed. The specification references SSPC SP 16 as the surface preparation method. At the pre-job meeting operations personnel make it clear that abrasive blasting will not permitted. The Owner's representative asks you what other methods might be used.
Of the options shown below, what would be the preferred option in this situation?
- A. SP 1 followed by SP 3
- B. SP 1 followed by caustic etching
- C. SP 1 followed by acid etching
- D. SP 1 followed by SP 2
正解:D
質問 # 48
The coating applicator has ignored a enface preparation hold point and applied coating over the surface without a sign off from you as the inspector.
Your FIRST preferred course of action is to:
- A. Ignore the situation
- B. Stop the job
- C. Advise the Owner and write a Non-Conformance report
- D. Require the Applicator to remove the coating
正解:D
質問 # 49
Dehumidification is defined as the removal of moisture vapor from the air to
- A. raise its relative humidity.
- B. lower its dew point,
- C. lower its temperature
- D. provide worker comfort.
正解:B
質問 # 50
A failure caused by applying a coating too thinly is known as
- A. cracking.
- B. chalking.
- C. failure to cure.
- D. pinholes.
正解:D
質問 # 51
A single component water borne acrylic coating cures by:
- A. Co-Reaction
- B. Oxidation
- C. Coalescence
- D. Solvent Evaporation
正解:C
質問 # 52
The Inspectors' goal at the Pre-Job Conference is to:
- A. Take accurate meeting minutes for distribution
- B. Discuss contractual requirements
- C. Obtain a clear understanding of the Specification
- D. Manage the meeting so it doesn't go off topic
正解:C
質問 # 53
You can use magnifiers to examine all of the following EXCEPT
- A. Surface cleanliness
- B. Surface profile
- C. Blisters
- D. Mill scale
正解:A
質問 # 54
When ASIN D 3363 is specified the Inspector must:
- A. Use the correct solvent
- B. Record the highest value attained
- C. Record the two end points identified in the standard
- D. Record the percentage of failure
正解:C
質問 # 55
You are the NACY Coating Inspector on a tank lining project where desiccant dehumidification is being used. Since the first shift of abrasive blasting your readings have indicated relative humidity below 40%; however on the second shift of coating application your readings are indicting 80%.
Your FIRST preferred course of action is to:
- A. Call your supervisor
- B. Advise the coating applicator supervisor of your readings
- C. Check to See if the dehumidification equipment is operating correctly
- D. Document the readings at the end of the shift
正解:B
質問 # 56
As a NACE Level 2 Inspector, NACE clearly indicates that you ate qualified to independently produce final documentation for a shop project.
- A. True
- B. False
正解:A
質問 # 57
Which product, is used in conjunction with other coatings such as FBE when the lines run through wetlands or a body of water?
- A. Coal Tar Enamel
- B. 2-Layet Polyethylene (PE)
- C. Concrete
- D. 3-Layet Polyethylene (PE)
正解:C
質問 # 58
NACE No.13/ SSPC 6 identifies the use of:
- A. Various methods of cleaning
- B. Watterjetting only
- C. Steam cleaning only
- D. Abrasive blasting only
正解:A
質問 # 59
The solvent sensitivity/solvent wipe test (ASTM D4752) is used to determine the cure of
- A. urethanes.
- B. inorganic zincs.
- C. powder coatings.
- D. epoxies.
正解:B
質問 # 60
The Concrete Repair Institute's comparators can be used to assess:
- A. Surface cleanliness prior to coating
- B. Contamination levels prior to coating
- C. Surface profile prior to coating
- D. Compressive and tensile strength prior to coating
正解:C
質問 # 61
NACE International Standards are developed by:
- A. Government mandates
- B. Standard committees
- C. International mandates
- D. Regional mandates
正解:B
質問 # 62
In powder coatings, when the particles of powder begin to flow but are not fully liquid, they are in what stage?
- A. Flow stage
- B. Cure stage
- C. Wetting stage
- D. Gel stage
正解:A
質問 # 63
......
NACE-CIP2-001認定試験は、コーティングインスペクターレベル1認定をすでに完了しており、コーティング検査の分野で少なくとも2年の経験がある個人を対象としています。この試験では、表面の準備、コーティングの適用、コーティング検査、コーティングテストなど、幅広いトピックをカバーしています。この試験では、保護コーティング、海洋コーティング、工業用コーティングなど、さまざまな種類のコーティングもカバーしています。この試験は、候補者のコーティング検査原則に関する知識と理解、および実際の状況でこの知識を適用する能力をテストするように設計されています。
問題集全額返金保証付き!NACE-CIP2-001問題公式問題集:https://www.passtest.jp/NACE/NACE-CIP2-001-shiken.html
厳密検証されたNACE-CIP2-001試験問題集PDF[2025年最新] 時間限定無料アクセスPassTest:https://drive.google.com/open?id=1Zzy5vgkWAawejvQaj6pdYzJTDld4IFLo